Q1. Answer the following questions with given project network data .

a) Draw the network diagram (Use the data box for each activity)

b) Calculate Forward, Backward, Slack, CPM duration (weeks)

c) List the all paths and calculate durations for each (show the CPM path)

Q2. Prepare task identification table according to Q3 results .

Q3. List the Rules for developing a project network diagram .

ActivityPredecessorDuration

A-10

B-15

C-9

DA,B17

EC12

FC13

GD, E19

HF, G11

ID,G,H14

ActivityDurationESEFLSLFSlack

A

B

C

D

E

F

G

H

I