HW 11

profiledkf.j
HW9Validation1.docx

Part V – Essay

1. (10 pts) A new, hypothetical GMP plant has the following features:

a. Incoming warehouse for ingredients and components

b. Outgoing warehouse for storage and shipping of final product

c. Employee cafeteria

d. Quality Control laboratory and test instruments

e. Air handling system for production areas

f. Air handling system for office areas

g. Production equipment

h. Maintenance shop

i. Nitrogen, compressed air and vacuum systems for manufacturing areas.

j. A product to be manufactured

k. Test methods to evaluate the product

l. Office area for production manager

m. Office area for accounting people

n. Manufacturing area

1) Describe how this plant should be validated. Include those features above that require validation. Where appropriate, indicate the sequence that should be followed.

2) Describe the types of protocols that should be required for each feature discussed.