| IT Consultant Business Startup | | | | 55 days | | | Special Notes: |
| | Design Phase | | | 27 days |
| | | Visit Manager of Facility | | 1 day | | Chris Stevens |
| | | Discuss Company Requirements | | 1 day | 3 | Chris Stevens,George Morrison |
| | | Survey Facility for Setup | | 1 day | 4 | Bill Thomas,Dan Ross,Harold Neil | Must have 1 Software, 1 Hardware, and 1 Network Engineer |
| | | Draft Layout Designs for Facility | | 1 week | 5 | Bill Thomas,Dan Ross,Harold Neil | Must have 1 Software, 1 Hardware, and 1 Network Engineer |
| | | Discuss Layout Designs with Company | | 1 day | 6 | Chris Stevens,George Morrison |
| | | Get Approval on Layout Design | | 1 day | 7FS+1 wk |
| | | Draft Equipment Requirements | | 1 week | 4,8 | Bill Thomas,Dan Ross,Harold Neil | Must have 1 Software, 1 Hardware, and 1 Network Engineer |
| | | Discuss Equipment Requirements with Company | | 1 day | 9 | Chris Stevens,George Morrison |
| | | Get Approval on Equipment | | 1 day | 10FS+1 wk |
| | Setup Phase | | | 14 days | 2 |
| | | Order Equipment | | 1 day | | Adam Williams,Fred Paulsen,Jared Lucas,George Morrison | Must have 1 Software, 1 Hardware, and 1 Network Engineer and Financial Advisor |
| | | | Order Computer Systems | 1 day | | Computer System[20] |
| | | | Order Computer Monitors | 1 day | | Computer Monitor[20] |
| | | | Order Computer Accessories | 1 day | | Computer Accessories[20] |
| | | | Order Battery Backups | 1 day | | Battery Backup[20] |
| | | | Order Printers and Fax | 1 day | | Printers[10] |
| | | | Order Network Equipment | 1 day | | Networking Hardware[5] |
| | | | Order Network Cables | 1 day | | Network Cables[50] |
| | | | Order Operating System | 1 day | | OS Software[20] |
| | | | Order Other Software | 1 day | | Other Software[20] |
| | | Receive Equipment | | 1 week | 13 |
| | | Prepare Equipment for Install | | 1 week | 23 | Adam Williams,Fred Paulsen,Jared Lucas | Must have 1 Software, 1 Hardware, and 1 Network Engineer |
| | | Install Software | | 2 days | 24 | Adam Williams,Harold Neil | Must be 2 Software Engineers |
| | | Install Network | | 2 days | 24 | Bill Thomas,Fred Paulsen | Must be 2 Network Engineers |
| | | Install Printers and Fax | | 1 day | 24 | Dan Ross,Jared Lucas | Must be 2 Hardware Engineers |
| | | Test Complete Setup | | 1 day | 25,26,27 | Bill Thomas,Dan Ross,Harold Neil,Adam Williams,Fred Paulsen,Jared Lucas | Must have 2 Software, 2 Hardware, and 2 Network Engineers |
| | Finalize and Train Phase | | | 14 days | 12 |
| | | Give Orientation to Client Company Employees | | 8 days | | Chris Stevens |
| | | | First Orientation Session | 4 days | | Bill Thomas,Dan Ross,Harold Neil | Must have 1 Software, 1 Hardware, and 1 Network Engineer |
| | | | Second Orientation Session | 4 days | 31 | Fred Paulsen,Adam Williams,Jared Lucas | Must have 1 Software, 1 Hardware, and 1 Network Engineer |
| | | Check Back with Company | | 1 day | 30FS+1 wk | Chris Stevens |