| Business Startup | | | 90 days |
| | Construct Business Plan | | 43 days |
| | | Research Marketable Propulsion Options | 30 days | | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Administrative Staff |
| | | Focus Options Into Business Vision | 15 days | 3 | Administrative Staff |
| | | Research Existing Hyd. Businesses | 10 days | 3 | Administrative Staff |
| | | Focus Hydrogen Goals | 15 days | 5 | Administrative Staff |
| | | Prepare Goal Presentation to Public | 15 days | 6 | Public Relations Rep. |
| | | Announce Business Intentions to Public | 1 day | 7 | Public Relations Rep. |
| | Financial Research | | 40 days | 4 |
| | | Research Potential Costs | 10 days | | Accountant |
| | | Develop Budget | 15 days | | Accountant |
| | | Contact Potential Investors | 15 days | 11 | Public Relations Rep. |
| | | Contact Governmental Grant Agency | 15 days | 11 | Public Relations Rep. |
| | | Research Business Loans | 15 days | 11 | Public Relations Rep. |
| | | Appeal to Local Community Representatives | 30 days | 10SS | Public Relations Rep. |
| | | Re-evaluate Budget with Known Finances | 10 days | 12,13,14,15 | Administrative Staff,Accountant |
| | File Governmental Applications etc. | | 60 days | 16 |
| | | Employ Lawyer for Legal Guidance | 5 days | | Administrative Staff |
| | | Acquire Business License | 2 days | 18 | Lawyer |
| | | Apply for EPA Permits | 60 days | 18 | Lawyer,HASMAT Specialists |
| | Facility Location and Layout | | 23 days | 16 |
| | | Define Minimum Required Specifications | 10 days | | Structural Engineer |
| | | Scout Potential Locations | 10 days | 22 | Structural Engineer |
| | | Apply for Lease | 2 days | 23 | Accountant |
| | | Apply for Required Permits | 5 days | 24 | Lawyer |
| | | Lease Facility and Land | 1 day | 25 | Lawyer,Accountant |
| | Hire Workforce | | 17 days | 16 | Administrative Staff |
| | | Design and Submit Want-ad in Newspaper | 1 day | | Administrative Staff |
| | | Review Applicants | 5 days | 28 | Administrative Staff |
| | | Administer Placement Testing | 3 days | 29 | Administrative Staff |
| | | Schedule Interviews | 5 days | 30 | Administrative Staff |
| | | Hire Qualified Applicants | 2 days | 31 | Administrative Staff |
| Pre-R&D | | | 30 days | 31 |
| | Acquire Experimental Resources | | 17 days |
| | | Determine Required Resources | 5 days | | Mechanical Engineers,Chemists,Physicists |
| | | Locate Vendor | 5 days | 35 | Sales |
| | | Purchase Resources | 15 days | 20 | Administrative Staff |
| | Equipment Gathering | | 17 days |
| | | Determine Required Equipment | 5 days | | Mechanical Engineers,Machinists,Physicists |
| | | Contact Equipment Dealers | 5 days | 39 | Sales |
| | | Purchase Equipment | 15 days | 20 | Administrative Staff |
| | Research Prototype Options | | 30 days |
| | | Research Current Hydrogen Technology | 10 days | | Mechanical Engineers,Electrical Engineers,Chemists,Physicists |
| | | Brainstorm Prototype Designs | 5 days | 43 | Mechanical Engineers,Electrical Engineers,Chemists,Physicists |
| | | Marketing Analysis | 4 days | 43 | Accountant |
| | | Choose Initial Prototype Design | 10 days | 44,45 | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Administrative Staff |
| | | Run Virtual Simulation | 5 days | 46 | Mechanical Engineers,Electrical Engineers,Chemists,Physicists |
| | Setup Facilities | | 15 days | 41,37,26 |
| | | Locate and Hire Moving Company | 1 day | | Administrative Staff |
| | | Move Equipment to Desired Space | 5 days | 49 | Moving Company |
| | | Move in Office Equipment | 2 days | 50 | Moving Company |
| | | Move in Other Resources (Metal, Hydrogen etc.) | 15 days | 50 | Moving Company |
| | | Check Any Missing Items | 2 days | 52,51 | Administrative Staff |
| Begin Research and Development | | | 0 days | 33 |
| R&D | | | 269 days | 53 |
| | Construct Prototype | | 80 days | | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Machinists |
| | | Modify Conventional Automobile | 30 days | | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Machinists |
| | | Construct Internal Combustion Engine | 30 days | | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Machinists |
| | | Build Working Prototype From Auto and Engine | 30 days | 58SS,57SS | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Machinists |
| | Test Prototype | | 119 days | 59 |
| | | Choose and Prepare Driver | 1 day | | Administrative Staff |
| | | Rent Time at Local Test Track | 3 days | 61 | Administrative Staff |
| | | Perform Real-time Testing | 3 mons | 62 | Driver[300%] |
| | | Evaluate Prototype Testing and Abilities | 5 days | 63FF,62 | Physicists,Mechanical Engineers |
| | | Determine Prototype Flaws | 5 days | 64FF | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Machinists |
| | Modify Prototype | | 70 days | 65 |
| | | Correct Prototype Design Flaws | 30 days | | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Machinists |
| | | Repeat Testing Until Acceptable Prototype is Constructed | 30 days | 67SS | Driver,Machinists,Electrical Engineers,Chemists,Physicists,Mechanical Engineers |
| | | Apply for U.S. Patents for Prototype | 30 days | 68 | Administrative Staff,Lawyer |
| Market Prototype | | | 90 days | 69 |
| | Research Market | | 5 days | | Sales |
| | Research Demographics | | 5 days | | Sales |
| | Contact Automobile Manufacturers | | 15 days | 72,71 | Sales |
| | Demonstration of Prototype | | 5 days | 73 | Driver,Public Relations Rep. |
| | Sign Contracts with Dealers | | 1 day | 74 | Administrative Staff,Sales |
| | Commercial | | 85 days | 71,72 |
| | | Hire Film Agency | 2 days | | Administrative Staff |
| | | Decide on Desired Commercial | 2 days | 77 | Advertising Agency |
| | | Run the Commercial for a Duration | 30 days | 78 | Advertising Agency |
| | | Keep the Commercial Running if Successful | 3 mons | 79 | Advertising Agency |
| Pre-Production | | | 18 days | 75 |
| | Locate New Facilities | | 5 days | | Structural Engineer |
| | Follow-up for Additional Government Funding | | 5 days | | Accountant |
| | Apply for Loan | | 5 days | | Accountant |
| | Contact Industrial Suppliers for Needed Resources | | 5 days | | Administrative Staff |
| | Lease Manufacturing Facilities | | 2 days | 82 | Administrative Staff |
| | Hire Manufacturing Workforce | | 5 days | 86 | Administrative Staff |
| | Purchase/Lease Manufacturing Equipment | | 2 days | 86 | Administrative Staff |
| | Setup Manufacturing Facilities | | 15 days | 88 |
| | | Locate and Hire Moving Company | 1 day | | Administrative Staff |
| | | Move Equipment to Desired Space | 5 days | 90 | Moving Company |
| | | Move in Office Equipment | 2 days | 90 | Moving Company |
| | | Move in Production Supplies | 15 days | 90 | Moving Company |
| | | Setup Inventory Control | 3 days | 93,92,91 | Administrative Staff |
| Begin Production | | | 0 days | 94 |
| Production | | | 300 days | 94 |
| | Produce Product as Necessary | | 3 mons | | Machinists[300%] |
| | Sell Product to Dealers | | 1 mon | | Sales |
| | Receive Feedback on Product | | 6 mons | 97 | Public Relations Rep. |
| | Expand Sales Market | | 6 mons | 97 | Sales |
| Post-Production Modifications | | | 45 days | 99 |
| | Review Feedback on Product | | 5 days | | Mechanical Engineers,Electrical Engineers,Chemists,Administrative Staff,Sales,Physicists |
| | Correct Flaws in Product | | 30 days | 102 | Mechanical Engineers,Electrical Engineers,Chemists,Physicists |
| | Modify Product Design and Continue Production | | 30 days | 103 | Mechanical Engineers,Electrical Engineers,Chemists,Physicists,Machinists |