long term investment management
Question 1 (1 point)
Vance incorporated is considering investing in a project with the following expected cash flows: -124, 89, 37, 27. If Vance's expected cost of capital is 0.10, what is the expected NPV of the project?
Your Answer:
Question 1 options:
|
|
|
Answer |
A company invests -$100k in a new project and expects the following cash flows: Year 1 $50k, Year 2 $30k, year 3 $40k. What is the company's expected IRR?
Question 2 options:
|
|
10.18% |
|
|
9.34% |
|
|
11.15% |
|
|
6.17% |
Heinlein Inc is considering investing in a project with a cost of $100k. If the project is expected to produce cash flows of $50k in year 1, $134k in year 2, and $208k in year 3, what is the payback period.
Your Answer:
Question 3 options:
|
|
|
Answer |
Vance LLC is considering investing in the following projects. Vance's WACC is 9.5%. Which of the following projects should Vance accept? More than one answer is possible.
Question 4 options:
|
|
A. IRR 11% |
|
|
B. IRR 9% |
|
|
C. IRR 10% |
|
|
D. IRR 8% |
Heinlein Inc is considering investing in a project with a cost of $100k. The project is expected to produce cash flows of $50 in year 1, 85 in year 2, and 235 in year 3. If the discount rate is 0.10 what is the discounted payback period.
Your Answer:
Question 5 options:
|
|
|
Answer |
Which of the following is correct?
Question 6 options:
|
|
The MIRR and the IRR methods always give the same result. |
|
|
The NPV and the IRR methods always give the same result. |
|
|
The NPV and the MIRR methods always give the same result. |
|
|
The IRR and the MIRR methods always give the same result. |
Which of the following is correct?
Question 7 options:
|
|
If the cost of capital is 5% project 1 should be accepted. |
|
|
If the cost of capital is 10% project 1 should be accepted. |
|
|
If the cost of capital is 12% project 1 should be accepted. |
|
|
If the cost of capital is 5% project 2 should be accepted. |
If the Present Value of all estimated futures costs of a 10 year new investment project is 140, and the future value of all expected profits is 190, what is the projects MIRR?
Your Answer:
Question 8 options:
|
|
|
Answer |
Which of the following statements is correct?
Question 9 options:
|
|
Project 1 has larger cash flows in later time periods than project 2. |
|
|
Project 2 has larger cash flows in later time periods than project 1. |
|
|
There is no way of telling from the graph where the cash flows take place. |
|
|
The price of long term bonds is more sensitive to interest rate changes than the price of short bonds. |
Project Salerino has the following cash flows: CF0 = -100, C01 = -150, C02 = 330, C03 = 690, C04 = -40. What is the PV of only the costs to Salerino if the cost of capital is 0.09?
Your Answer:
Question 10 options:
|
|
|
Answer |
3
oSs_13666424
4
False
1
247982
405441
4
oSs_13666425
7
8
9
oSs_13666430
10
False
1
256259
412631
10
oSs_13666431