Homework 2
JIT Implementation using Value Analysis A Case Study, ISEN5881
Consider the steel cabinet manufacturing line with the following process flow diagram. (see Figure 1**) Processing, storage/handling time (Hrs) 0.3 Hr 0.15 96 hrs. (storage time) 8 Hrs. (storage time) 0.20 Hrs 0.1 Hrs Inspection, And Rework 3.0 Hrs. (storage time) 0.5 Hrs. (Storage time) 0.1 Hrs Inspection and 0.1 Hrs for Rework 0.5 Hrs 3.00 Hrs 1.5 Hr , 0.1 Hrs for Inspection and 0.1 Hrs for Rework
34 hours ( 2.5 hours from plant to Company To Customers warehouse and 31.5 hrs. From warehouse to customers
Figure 1**
Steel coil preprocessing stamping
Buffer Inventory
1 Step Cabinet Manufacturing
Inspect (QC station)
Rework
Buffer Inventory
Spray and Dry
Buffer Inventory
Rework
Inspect (QC station)
Inspect (QC Station)
Rework
Coil Storage
Final assembly
** See “Legend” for Figure 1 on page 3.
The value-added analysis using a flow chart is a mechanism to improve cycle times and productivity by visually separating value-adding from non-value-adding activities. The process is very straightforward and explained here. Follow this procedure apply it to the case study.
Lis 1. List all of the steps in the process from beginning to end (Figure 1)
2. Figure 1 shows a box for every step, in sequence.
3. Use the production rate in each box and determine the Total Cycle Time.
4. Identify those steps that do not add value to the process. Non value-added operations.
.
5. to separate the value-added and non-value-added activities, move the boxes representing non- value-added processes to the right of the value added steps (as shown in Fiq.. 2)
. 6 From the information collected in step 5 determine the Non-Value-Added Cycle Time. This is the maximum waste that could be eliminated from the processing operations
. 7. Repeat step 5 and 6 above for all operations and then determine the Value Added Cycle time. . Now determine the ratio R1= value added time as % of total cycle time)
. 8. Move the boxes representing the value-added processes to the left of the value- adding steps (see Fig 2) Calculate the percentage of the current Total Cycle Time that is spent on Non-Value- Added operations. Construct a pie chart to communicate the analysis performed in steps 7 and 8 above. A recent study by a group of Industrial Engineers proved that some operation simplification and./or modifications could eliminate waste and substantially shorten the total cycle time. The following assumptions/facts must be used as the basis for elimination some non-value-added operations
• Assume A)-The existing Layout could not be modified, B)-The existing layout could be modified
• A stock entering a buffer storage must be moved to the next process within 0.5 hours
• Only one Inspection-Rework station should be used throughout the manufacturing cycle (You need to determine which one to keep). Note that, all other inspection functions could be incorporated into the individual processes. In addition, the items found defective in a processing station will be allowed to move through the system (with no further processing) and will be rejected at the end of the line.
• Steel coil inventory time should be reduced to 10 hours.
10.
.
10. After step 8, the remaining processes are usually called Target Processes. a)- Develop the Diagram of the new layout (similar to figure 2) with Target Processes only, and determine the total Target Cycle Time. b)- Determine the ratio R2= value added time as % of total cycle time). Compare R1 and R2 and comment on the changes/improvements because of waste elimination.
c)- Analyze the Non-Value-Added steps (in the improved system) and suggest at least 3 alternatives method of improving those non value added activities.
.
APPENDIX
V Value-Added Non-Value-Added
Figure 2
Symbols used in Figure 1: Symbol Used to indicate Processing Unit Storage (buffer or offline storage) Rework/Reclamation station Material/product handling (Time requires insignificant) Material/product handling (Time requires significant)
Operation 2
Operati on 1
Operati on c
R e w o r k