14.1 You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 200 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.)

14.2 You are expected to have the gift bags in Problem 14.1 ready at 5 p.m. However, you need to personalize the items (monogrammed pens, note pads, literature from the printer, etc.). The lead time is 1 hour to assemble 200 Js once the other items are prepared. The other items will take a while as well. Given the volunteers you have, the other time estimates are item K (2 hours), item L (1 hour), and item M (4 hours). Develop a time-phased assembly plan to prepare the gift bags.

14.3 As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, two springs, and four clamps. The base is assembled from one clamp and two housings. Each clamp has one handle and one casting. Each housing has two bearings and one shaft. There is no inventory on hand.

a. Determine the gross quantities needed of each item if you are to assemble 50 brackets.

b. Compute the net quantities needed if there are 25 of the base and 100 of the clamp in stock. PX

14.13 Electro Fans has just received an order for one thousand 20-inch fans due week 7. Each fan consists of a housing assembly, two grills, a fan assembly, and an electrical unit. The housing assembly consists of a frame, two supports, and a handle. The fan assembly consists of a hub and five blades. The electrical unit consists of a motor, a switch, and a knob. The following table gives lead times, on-hand inventory, and scheduled receipts.

A. Prepare a net material requirements plan.

Data Table for Problem 14.13

COMPONENT

LEAD TIME

ON-HAND INVENTORY

LOT SIZE*

SCHEDULED RECEIPT

20” Fan

1

100

Housing

1

100

Frame

2

Supports (2)

1

50

100

Handle

1

400

500

Grills

2

200

500

Fan Assembly

3

150

Hub

1

Blades

2

100

Electrical Units

1

200 Knobs in week 2

Motor

1

Switch

1

20

12

Knob

1

25