Diagram Charter
By Monday 12 October
1)
Suppose that you have some activities such as listed below the table.
a. Develop network diagram
b. Calculate Earliest Start, Earliest Finish, Latest Start, Latest Finish, and Slacks values
c. Define Critical Path
NOTE: Expected Project Time is 85 days.
|
No |
Activity |
Duration |
Predecces- sors |
Earliest |
Latest |
Total Slack |
||
|
|
|
|
|
Start |
Finish |
Start |
Finish |
|
|
1 |
Gathering Data |
4 |
- |
|
|
|
|
|
|
2 |
Interview |
1 |
- |
|
|
|
|
|
|
3 |
Analyze Data |
2 |
1,2 |
|
|
|
|
|
|
4 |
Define User Requirements |
5 |
3 |
|
|
|
|
|
|
5 |
Define System Requirements |
9 |
3 |
|
|
|
|
|
|
6 |
Develop Use Case Model |
1 |
4,5 |
|
|
|
|
|
|
7 |
Develop Class Diagram |
2 |
5 |
|
|
|
|
|
|
8 |
Develop State Machine Diagram |
4 |
6 |
|
|
|
|
|
|
9 |
Develop Activity Diagram |
3 |
6 |
|
|
|
|
|
|
10 |
Develop Sequence Diagram |
1 |
6 |
|
|
|
|
|
|
11 |
Develop ERD |
2 |
7 |
|
|
|
|
|
|
12 |
Prepare Analyse Report |
2 |
8,9,10,11 |
|
|
|
|
|
|
13 |
Design Database |
3 |
12 |
|
|
|
|
|
|
14 |
Design Software Architecture |
5 |
12 |
|
|
|
|
|
|
15 |
Develop Software |
45 |
13,14 |
|
|
|
|
|
|
16 |
Testing Software |
5 |
15 |
|
|
|
|
|
|
17 |
Fix problem |
10 |
15 |
|
|
|
|
|
|
18 |
Prepare Report |
5 |
16,17 |
|
|
|
|
|
|
19 |
Deployment |
5 |
18 |
|
|
|
|
|
2)
Suppose you have a project about developing a Learning Management system software like Moodle.
So, try to create WBS using only one of these methods:
a) by product or
b) by phases or
c) by product & some phases
3)
Suppose you have a project about developing a Learning Management system software like Moodle.
Create an Activity Diagram for this project.