| Analysis and Design task durations |
| Project name | Year | Task name | Duration |
| Accounts Payable | 2018 |
| | | Interview process | 5 days |
| | | Development of User Questionnaire | 2 days |
| | | Identification of risks | 1.5 days |
| | | DFD diagram | 4 days |
| | | UML diagram | 4 days |
| | | Layout of 1 report | 4 hours |
| | | Layout of 1 user screen | 2 hours |
| | | Testing plan | 5 days |
| | | Implementation plan | 3 days |
| Human Resources | 2017 |
| | | Interview process | 4 days |
| | | Development of User Questionnaire | 2 days |
| | | Identification of risks | 1 day |
| | | DFD diagram | 3.5 days |
| | | UML diagram | 2 days |
| | | Layout of 1 report | 2 hours |
| | | Layout of 1 user screen | 4 hours |
| | | Testing plan | 7 days |
| | | Implementation plan | 3 days |
| Payroll | 2019 |
| | | Interview process | 6 days |
| | | Development of User Questionnaire | 1 day |
| | | Identification of risks | 2 days |
| | | DFD diagram | 4.5 days |
| | | UML diagram | 5 days |
| | | Layout of 1 report | 1 day |
| | | Layout of 1 user screen | 4 hours |
| | | Testing plan | 5 days |
| | | Implementation plan | 3.5 days |