House construction
Surname5
Residential House Construction Project
Finalized Project Scope
This project is intended to construct a new home for Mr. and Mrs. Rodgers. This article offers data on the prospective resource allocation for the project, paying keen attention to the stakeholder and time assigned to the relevant milestones and tasks. From the information, a work schedule for the project is also given, The stakeholder engagement and communication plan is also given, offering information on the stakeholders involved in each phase of construction, the extent of their activities, and the timeframe within which their engagement is relevant. Finally, the work breakdown structure for the residential house project, highlighting the scope, milestones, and tasks involved in every phase of the project.
Stakeholder Engagement-Communication Plan
|
PHASE |
STAKEHOLDER |
ENGAGEMENT |
TIMEFRAME |
ACTIVITIES |
|
PRE-CONSTRUCTION |
Client, design team, specialists in relevant sectors, project manager, relevant authorities.
Client, project manager, locals. |
Formal discussions conducted by the entity authorized to deliver the decisions that are consistent with statutory procedure during the environmental impact assessment and decision-making process. Acquiring a building permit as well as an occupancy permit. Getting permission to utilize the environment.
Informal meetings and consultations with the locals.
|
Reports on environmental assessments by end of January, 2023.
Necessary permits by December, 2022.
|
Publication of information on measures taken by the organization as part of the environmental impact assessment processes in the usual manner. Within the environmental protocol, there is a 21-day time for public consultations. Disclosure of information about project-related choices.
Details about investing strategies. Information about processes for getting decisions. |
|
CONSTRUCTION |
Contractor and sub-contractors, client, construction workers, project manager. |
Unofficial engagements within the framework of the Stakeholder Involvement Plan. |
All throughout the construction process. |
Reminding them about contact details and the complaint reporting process. Establishment of regulations allowing construction workers to file comments. Details for the municipality and its residents. |
|
OPERATION |
Client, supervisors, project manager. |
Casual discussions within the framework of the Stakeholder Involvement Plan. |
Post-completion and assessment, and all through the operation process. |
Results are sent to responsible authorities in accordance with existing legislation, and relevant data is published on the construction company website. |
|
|
|
|
|
|
Resource Allocation
|
TASK |
ASSIGNED TO |
PROGRESS |
START |
END |
|
PRE-CONSTRUCTION |
|
|
|
|
|
Site preparation |
Client, Project manager |
100% |
12/8/22 |
12/11/22 |
|
Mobilization |
Project manager |
60% |
12/11/22 |
12/13/22 |
|
Site clearance |
Contractor |
100% |
12/13/22 |
12/17/22 |
|
Brief& design |
Design team, client |
100% |
12/17/22 |
12/26/22 |
|
Exca, and disposal |
Contractor |
100% |
12/12/22 |
12/18/22 |
|
CONSTRUCTION |
|
|
|
|
|
Concrete work |
Contractor, labor |
30% |
12/13/22 |
3/20/23 |
|
Woodwork-formwork |
Contractor, carpenters |
30% |
12/15/22 |
3/22/23 |
|
Metal work |
Contractor, blacksmiths |
0%
|
3/22/23 |
3/25/23 |
|
Joinery |
Contractor, suppliers |
0% |
3/22/23 |
3/24/23 |
|
Finishes |
Contractor, labor |
0% |
3/22/23 |
3/25/23 |
|
POST-CONSTRUCTION |
|
|
|
|
|
HVAC |
Contractor, specialists |
0% |
3/25/23 |
3/30/23 |
|
Electrical works |
Electrical engineer |
60% |
3/31/23 |
4/4/23 |
|
Mechanical installations |
Mechanical engineer |
75% |
4/5/23 |
4/10/23 |
|
Decorations |
Interior designer |
0% |
4/11/23 |
4/15/23 |
|
Landscaping |
Land surveyor |
20% |
4/5/23 |
4/9/23 |
|
PROJECT CONCLUSION |
|
|
|
|
|
Comprehensive tour |
Client, PM, contractor |
0% |
4/9/23 |
4/10/23 |
|
Certificate of occupancy |
Contractor, local authorities |
0% |
4/15/23 |
4/18/23 |
|
Approvals |
Local authorities |
10% |
4/15/23 |
4/18/23 |
|
Punch list |
Local authorities |
0% |
4/15/23 |
4/18/23 |
|
Handover |
Contractor, PM, client |
0% |
4/19/23 |
4/19/23 |
Work Schedule