House construction

profileSam's work
h2.docx

Surname5

Residential House Construction Project

Finalized Project Scope

This project is intended to construct a new home for Mr. and Mrs. Rodgers. This article offers data on the prospective resource allocation for the project, paying keen attention to the stakeholder and time assigned to the relevant milestones and tasks. From the information, a work schedule for the project is also given, The stakeholder engagement and communication plan is also given, offering information on the stakeholders involved in each phase of construction, the extent of their activities, and the timeframe within which their engagement is relevant. Finally, the work breakdown structure for the residential house project, highlighting the scope, milestones, and tasks involved in every phase of the project.

Stakeholder Engagement-Communication Plan

PHASE

STAKEHOLDER

ENGAGEMENT

TIMEFRAME

ACTIVITIES

PRE-CONSTRUCTION

Client, design team, specialists in relevant sectors, project manager, relevant authorities.

Client, project manager, locals.

Formal discussions conducted by the entity authorized to deliver the decisions that are consistent with statutory procedure during the environmental impact assessment and decision-making process. Acquiring a building permit as well as an occupancy permit. Getting permission to utilize the environment.

Informal meetings and consultations with the locals.

Reports on environmental assessments by end of January, 2023.

Necessary permits by December, 2022.

Publication of information on measures taken by the organization as part of the environmental impact assessment processes in the usual manner. Within the environmental protocol, there is a 21-day time for public consultations. Disclosure of information about project-related choices.

Details about investing strategies. Information about processes for getting decisions.

CONSTRUCTION

Contractor and sub-contractors, client, construction workers, project manager.

Unofficial engagements within the framework of the Stakeholder Involvement Plan.

All throughout the construction process.

Reminding them about contact details and the complaint reporting process. Establishment of regulations allowing construction workers to file comments. Details for the municipality and its residents.

OPERATION

Client, supervisors, project manager.

Casual discussions within the framework of the Stakeholder Involvement Plan.

Post-completion and assessment, and all through the operation process.

Results are sent to responsible authorities in accordance with existing legislation, and relevant data is published on the construction company website.

Resource Allocation

TASK

ASSIGNED TO

PROGRESS

START

END

PRE-CONSTRUCTION

 

 

 

Site preparation

Client, Project manager

100%

12/8/22

12/11/22

Mobilization

Project manager

60%

12/11/22

12/13/22

Site clearance

Contractor

100%

12/13/22

12/17/22

Brief& design

Design team, client

100%

12/17/22

12/26/22

Exca, and disposal

Contractor

100%

12/12/22

12/18/22

CONSTRUCTION

 

 

 

 

Concrete work

Contractor, labor

30%

12/13/22

3/20/23

Woodwork-formwork

Contractor, carpenters

30%

12/15/22

3/22/23

Metal work

Contractor, blacksmiths

0%

 

3/22/23

3/25/23

Joinery

Contractor, suppliers

0% 

3/22/23

3/24/23

Finishes

Contractor, labor

0% 

3/22/23

3/25/23

POST-CONSTRUCTION

 

 

 

HVAC

Contractor, specialists

0% 

3/25/23

3/30/23

Electrical works

Electrical engineer

60%

3/31/23

4/4/23

Mechanical installations

Mechanical engineer

75%

4/5/23

4/10/23

Decorations

Interior designer

0% 

4/11/23

4/15/23

Landscaping

Land surveyor

20%

4/5/23

4/9/23

PROJECT CONCLUSION

 

 

 

 

Comprehensive tour

Client, PM, contractor

 0%

4/9/23

4/10/23

Certificate of occupancy

Contractor, local authorities

 0%

4/15/23

4/18/23

Approvals

Local authorities

 10%

4/15/23

4/18/23

Punch list

Local authorities

0% 

4/15/23

4/18/23

Handover

Contractor, PM, client

0% 

4/19/23

4/19/23

Work Schedule

WBS Structure

image5.png

image6.png

image7.png

image8.png

image9.png

image10.png

image11.png

image12.png

image13.png

image14.png

image15.png

image16.png

image17.png

image18.png

image19.png

image20.png

image21.png

image22.png

image23.png

image24.png

image25.png

image26.png

image27.png

image28.png

image29.png

image30.png

image31.png

image32.png

image33.png

image34.png

image35.png

image36.png

image37.png

image38.png

image39.png

image40.png

image41.png

image42.png

image43.png

image44.png

image45.png

image46.png

image47.png

image48.png

image49.png

image50.png

image51.png

image52.png

image53.png

image54.png

image1.png

image55.png

image56.png

image57.png

image58.png

image59.png

image60.png

image61.png

image62.png

image63.png

image2.png

image3.png

image4.png