TPP 5 - Consolidated Project Management Plan (Group)

profilejarfra
GroupD_GroupFiles_Feb242020406PM.zip

Appendix A - Team Business Project Plan.mpp

Appendix B - Team Business Resource Sheet.pdf

ID Resource Name Type Material Label Initials Group Max. Units Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar Work 1 Mamma Mia Work M Owner 100% $0.00/hr $0.00/hr $0.00 Prorated Standard 87.31 hrs 2 Steve Sysadmin Work SS Contractor 100% $52.01/hr $78.02/hr $0.00 Prorated Standard 257.75 hrs 3 Webster Webdev Work WW Contractor 100% $37.51/hr $56.27/hr $0.00 Prorated Standard 168 hrs 4 Archie Architect Work AA Contractor 100% $53.43/hr $80.15/hr $0.00 Prorated Standard 112.34 hrs 5 Deborah Developer Work DD Contractor 100% $54.81/hr $82.22/hr $0.00 Prorated Standard 184 hrs

6 Zack Bollack Work ZB PM 100% $67.00/hr $100.50/hr $0.00 Prorated Standard 82.5 hrs 7 Eddie Money Work EM Accounting 100% $37.89/hr $56.84/hr $0.00 Prorated Standard 113 hrs 8 Bill Rye Work BR Food Services 100% $12.09/hr $18.14/hr $0.00 Prorated Standard 16 hrs 9 Clubber Lang Work CL Food Services 100% $12.09/hr $18.14/hr $0.00 Prorated Standard 0 hrs 10 Dusty Baker Work DB Baker 100% $13.78/hr $20.67/hr $0.00 Prorated Standard 0 hrs 11 Tony Cannoli Work TC Baker 100% $13.78/hr $20.67/hr $0.00 Prorated Standard 0 hrs 12 Porter Smith Work PS Counter Server 100% $10.70/hr $16.05/hr $0.00 Prorated Standard 0 hrs 13 Patrick Steward Work PS Counter Server 100% $10.70/hr $16.05/hr $0.00 Prorated Standard 0 hrs 14 John Weiter Work JW Counter Server 100% $10.70/hr $16.05/hr $0.00 Prorated Standard 0 hrs 15 Ivan Tory Work IT Supply/Inventory Manager 100% $37.85/hr $56.78/hr $0.00 Prorated Standard 46.5 hrs 16 Digital Phone

Equipment Material unit VZW Hardware $85.00 $25.00 Start 2 unit

17 NetSUITE ERP License

Work NS SaaS 100%$999.00/mon $0.00/hr $0.00 Start 24 Hours 40 hrs

18 NetSUITE Training Material session NST Training $975.00 $0.00 Start 1 session

19 Shopify Work S SaaS 100%$29.00/mon $0.00/hr $0.00 Start 24 Hours 24 hrs 20 Toast Installation Material unit T Setup Fee $499.00 $0.00 Start 1 unit 21 Toast Kitchen Printer Material unit T Hardware $179.00 $25.00 Start 1 unit

22 Toast Loyalty Program

Material license T SaaS $15.00 $0.00 Start 1 license

23 Toast Online Ordering

Material license T SaaS $38.00 $0.00 Start 1 license

24 Toast POS Software Material license T SaaS $100.00 $0.00 Start 2 license

25 Toast POS Terminal 1 Material unit T Hardware $768.00 $0.00 Start 1 unit

26 Toast POS Terminal 2 Material unit T Hardware $499.00 $25.00 Start 1 unit

27 Toast Receipt Printer Material unit T Hardware $129.00 $25.00 Start 1 unit

28 Verizon Business Digital Voice Line

Work V Service 100%$10.00/mon $0.00/hr $0.00 Start 24 Hours 40 hrs

29 Verizon FIOS Work V Service 100%$129.00/mon $0.00/hr $0.00 Start 24 Hours 40 hrs 30 Verizon FIOS

Activation Material session V Setup Fee $49.00 $0.00 Start 1 session

31 Verizon FIOS Wireless Router

Material unit V Hardware $299.99 $25.00 Prorated 2 unit

Page 1 TTP3 - TEAM BUSINESS

Appendix C - Team Business Task Sheet.pdf

ID WBS Task Mode Task Name Duration Start Finish Predecessors Successors Resource Names Type Cost Work Resource Group 1 1 Mamma's Sandwich Shoppe & Bakery 102.38 days Sun 3/1/20 Wed 7/22/20 Fixed Duration $52,141.99 1,211.4 hrs 2 1.1 Project Start 0 days Sun 3/1/20 Sun 3/1/20 5 Mamma Mia,Zack Bollack Fixed Units $0.00 0 hrs Owner,PM 3 1.2 Project Management 94.13 days Mon 3/2/20 Fri 7/10/20 Fixed Duration $5,932.97 141.31 hrs 4 1.2.1 Initiation 94.13 days Mon 3/2/20 Fri 7/10/20 Fixed Duration $2,925.81 69.31 hrs 5 1.2.1.1 Initial Project Meeting 4 hrs Mon 3/2/20 Mon 3/2/20 2 11,7,8,9 Archie Architect,Eddie Money,Zack Bollack,Mamma Mia,Ivan ToryFixed Units $784.68 20 hrs Contractor,Accounting,PM,Owner,Supply/Inventory Manager 6 1.2.1.2 Inputs 0.38 days Mon 3/2/20 Mon 3/2/20 Fixed Duration $189.35 7.31 hrs 7 1.2.1.2.1 Business Case 2 hrs Mon 3/2/20 Mon 3/2/20 5 11 Mamma Mia[33%] Fixed Units $0.00 0.66 hrs Owner 8 1.2.1.2.2 Environmental Factors 3 hrs Mon 3/2/20 Mon 3/2/20 5 11 Eddie Money[50%],Ivan Tory[50%],Mamma Mia[33%] Fixed Units $113.61 3.99 hrs Accounting,Supply/Inventory Manager,Owner 9 1.2.1.2.3 Organizational Processes 3 hrs Mon 3/2/20 Mon 3/2/20 5 11 Eddie Money[33%],Ivan Tory[33%],Mamma Mia[22%] Fixed Units $75.74 2.66 hrs Accounting,Supply/Inventory Manager,Owner 10 1.2.1.3 Outputs 93.25 days Mon 3/2/20 Fri 7/10/20 Fixed Duration $1,951.78 42 hrs 11 1.2.1.3.1 Project Charter 2 days Mon 3/2/20 Wed 3/4/20 5,7,8,9 12 Zack Bollack Fixed Units $1,072.00 16 hrs PM 12 1.2.1.3.2 Kickoff Meeting 2 hrs Wed 3/4/20 Thu 3/5/20 11 24 Eddie Money,Mamma Mia,Zack Bollack Fixed Units $209.78 6 hrs Accounting,Owner,PM 13 1.2.1.3.3 Progress Review Meeting 90.13 days Fri 3/6/20 Fri 7/10/20 Fixed Duration $670.00 20 hrs 14 1.2.1.3.3.1 Project Status Meeting 1 1 hr Fri 3/6/20 Fri 3/6/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 15 1.2.1.3.3.2 Project Status Meeting 2 1 hr Fri 3/20/20 Fri 3/20/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 16 1.2.1.3.3.3 Project Status Meeting 3 1 hr Fri 4/3/20 Fri 4/3/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 17 1.2.1.3.3.4 Project Status Meeting 4 1 hr Fri 4/17/20 Fri 4/17/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 18 1.2.1.3.3.5 Project Status Meeting 5 1 hr Fri 5/1/20 Fri 5/1/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 19 1.2.1.3.3.6 Project Status Meeting 6 1 hr Fri 5/15/20 Fri 5/15/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 20 1.2.1.3.3.7 Project Status Meeting 7 1 hr Fri 5/29/20 Fri 5/29/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 21 1.2.1.3.3.8 Project Status Meeting 8 1 hr Fri 6/12/20 Fri 6/12/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 22 1.2.1.3.3.9 Project Status Meeting 9 1 hr Fri 6/26/20 Fri 6/26/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 23 1.2.1.3.3.10 Project Status Meeting 10 1 hr Fri 7/10/20 Fri 7/10/20 Mamma Mia,Zack Bollack Fixed Units $67.00 2 hrs Owner,PM 24 1.2.2 Initiation COMPLETE 0 days Thu 3/5/20 Thu 3/5/20 12 27,28,29,30 Mamma Mia,Zack Bollack Fixed Units $0.00 0 hrs Owner,PM 25 1.2.3 Planning 52.56 days Thu 3/5/20 Mon 5/18/20 Fixed Duration $3,007.16 72 hrs 26 1.2.3.1 Activity Planning 0.25 days Thu 3/5/20 Thu 3/5/20 Fixed Duration $134.00 2 hrs 27 1.2.3.1.1 Activity Definitions 2 hrs Thu 3/5/20 Thu 3/5/20 24 32,37,57,61,53 Zack Bollack[25%] Fixed Units $33.50 0.5 hrs PM 28 1.2.3.1.2 Activity Sequences 2 hrs Thu 3/5/20 Thu 3/5/20 24 32,37 Zack Bollack[25%] Fixed Units $33.50 0.5 hrs PM 29 1.2.3.1.3 Activity Resources 2 hrs Thu 3/5/20 Thu 3/5/20 24 34,37 Zack Bollack[25%] Fixed Units $33.50 0.5 hrs PM 30 1.2.3.1.4 Activity Durations 2 hrs Thu 3/5/20 Thu 3/5/20 24 34,37 Zack Bollack[25%] Fixed Units $33.50 0.5 hrs PM 31 1.2.3.2 Scope Management 0.5 days Thu 3/5/20 Thu 3/5/20 Fixed Duration $268.00 4 hrs 32 1.2.3.2.1 Project WBS 4 hrs Thu 3/5/20 Thu 3/5/20 27,28 34,40,42,43 Zack Bollack Fixed Units $268.00 4 hrs PM 33 1.2.3.3 Project Cost Planning 4.88 days Thu 3/5/20 Thu 3/12/20 Fixed Duration $1,364.04 36 hrs 34 1.2.3.3.1 Cost Estimates 4 days Thu 3/5/20 Thu 3/12/20 29,30,32 35,42 Eddie Money Fixed Units $1,212.48 32 hrs Accounting 35 1.2.3.3.2 Project Budget 4 hrs Thu 3/12/20 Thu 3/12/20 34 58FS+1 day,62FS+1 day,54FS+1 day,42,43Eddie Money Fixed Units $151.56 4 hrs Accounting 36 1.2.3.4 Procurement Management 1 day Thu 3/5/20 Fri 3/6/20 Fixed Duration $303.12 12 hrs 37 1.2.3.4.1 IT System Purchases/Acquisitions 4 hrs Thu 3/5/20 Thu 3/5/20 27,28,29,30 38,49,57,61,53,58FS+2 days,62FS+2 days,54FS+2 days,43Eddie Money,Mamma Mia Fixed Units $151.56 8 hrs Accounting,Owner 38 1.2.3.4.2 IT System Contracting 4 hrs Thu 3/5/20 Fri 3/6/20 37 47,43 Eddie Money Fixed Units $151.56 4 hrs Accounting 39 1.2.3.5 Risk Management 0.75 days Tue 5/12/20 Wed 5/13/20 Fixed Duration $402.00 6 hrs 40 1.2.3.5.1 Project Risks 3 hrs Tue 5/12/20 Tue 5/12/20 32 41,42,43 Zack Bollack Fixed Units $201.00 3 hrs PM 41 1.2.3.5.2 Risk Responses 3 hrs Tue 5/12/20 Wed 5/13/20 40 42,43 Zack Bollack Fixed Units $201.00 3 hrs PM 42 1.2.3.6 Communication Plan 4 hrs Wed 5/13/20 Thu 5/14/20 32,34,35,40,41 44,43 Zack Bollack[50%],Mamma Mia Fixed Units $0.00 4 hrs PM,Owner 43 1.2.3.7 Project Schedule 2 days Thu 5/14/20 Mon 5/18/20 32,35,37,38,40,41,42 44 Zack Bollack[50%] Fixed Units $536.00 8 hrs PM 44 1.2.4 Planning COMPLETE 0 days Mon 5/18/20 Mon 5/18/20 42,43 49 Zack Bollack,Mamma Mia Fixed Units $0.00 0 hrs PM,Owner 45 1.3 IT System Design 59.44 days Fri 3/6/20 Thu 5/28/20 Fixed Duration $2,021.70 56.5 hrs 46 1.3.1 IT Contractors 2.38 days Fri 3/6/20 Tue 3/10/20 Fixed Duration $268.00 23 hrs 47 1.3.1.1 Interviews 2 days Fri 3/6/20 Tue 3/10/20 38 48 Mamma Mia,Zack Bollack[50%] Fixed Units $268.00 20 hrs Owner,PM 48 1.3.1.2 Hiring 3 hrs Tue 3/10/20 Tue 3/10/20 47 49 Eddie Money,Mamma Mia Fixed Units $0.00 3 hrs Accounting,Owner 49 1.3.2 Initial Design Specification 3.19 days Mon 5/18/20 Wed 5/27/20 37,48,44 50 Steve Sysadmin Fixed Units $1,326.26 25.5 hrs Contractor 50 1.3.3 Review Design Specification 1 day Wed 5/27/20 Thu 5/28/20 49 51 Archie Architect Fixed Units $427.44 8 hrs Contractor 51 1.3.4 Deliver Design Specification 0 days Thu 5/28/20 Thu 5/28/20 50 55,59 Mamma Mia,Zack Bollack Fixed Units $0.00 0 hrs Owner,PM 52 1.4 System Networking 13 days Tue 5/12/20 Fri 5/29/20 Fixed Duration $800.85 85.28 hrs 53 1.4.1 Networking Requirements 2 days Tue 5/12/20 Thu 5/14/20 27,37 54FS+2 days Archie Architect[33%] Fixed Units $282.11 5.28 hrs Contractor 54 1.4.2 Networking Procurement 5 days Mon 5/18/20 Wed 5/20/20 35FS+1 day,37FS+2 days,53FS+2 days 55FS+2 days Verizon FIOS,Verizon Business Digital Voice Line,Eddie MoneyFixed Units $34.75 80 hrs Service,Accounting 55 1.4.3 Networking Installation 6 hrs Thu 5/28/20 Fri 5/29/20 51,54FS+2 days 74 Verizon FIOS Activation[1 session],Digital Phone Equipment[1 unit],Verizon FIOS Wireless Router[1 unit]Fixed Units $483.99 0 hrs Setup Fee,Hardware 56 1.5 System Hardware 14.25 days Tue 5/12/20 Mon 6/1/20 Fixed Duration $3,723.90 25.28 hrs 57 1.5.1 Hardware Requirements 2 days Tue 5/12/20 Thu 5/14/20 27,37 58FS+2 days Archie Architect[33%] Fixed Units $282.11 5.28 hrs Contractor 58 1.5.2 Hardware Procurement 5 days Mon 5/18/20 Tue 5/26/20 35FS+1 day,37FS+2 days,57FS+2 days 59FS+2 days Toast Kitchen Printer[1 unit],Toast POS Software[1 license],Toast POS Terminal 1[1 unit],Toast POS Terminal 2[1 unit],Toast Receipt Printer[1 unit],Eddie Money[50%]Fixed Units $2,507.80 20 hrs Hardware,SaaS,Accounting 59 1.5.3 Hardware Installation 2 days Thu 5/28/20 Mon 6/1/20 51,58FS+2 days 74 Digital Phone Equipment[1 unit],Verizon FIOS Wireless Router[1 unit],Toast Installation[1 unit]Fixed Units $933.99 0 hrs Hardware,Setup Fee 60 1.6 System Software 67.19 days Thu 3/5/20 Tue 6/9/20 Fixed Duration $5,361.15 164.53 hrs 61 1.6.1 Software Requirements 2 days Thu 3/5/20 Wed 5/13/20 27,37 62FS+2 days,65,68,71 Archie Architect[33%] Fixed Units $282.11 5.28 hrs Contractor 62 1.6.2 Software Procurement 1 hr Fri 5/15/20 Mon 5/18/20 35FS+1 day,37FS+2 days,61FS+2 days 65FS+2 days,68FS+2 days,71Eddie Money[50%] Fixed Units $18.95 0.5 hrs Accounting 63 1.6.3 Software Installation 16 days Mon 5/18/20 Tue 6/9/20 Fixed Duration $5,060.10 158.75 hrs 64 1.6.3.1 Point of Sales Software 14 days Wed 5/20/20 Tue 6/9/20 Fixed Duration $1,817.32 32 hrs 65 1.6.3.1.1 Install Software 6 days Wed 5/20/20 Thu 6/4/20 61,62FS+2 days 66 Toast POS Software[1 license],Steve Sysadmin[50%],Toast Loyalty Program[1 license],Toast Online Ordering[1 license]Fixed Units $1,401.24 24 hrs SaaS,Contractor 66 1.6.3.1.2 Test POS Software 2 days Fri 6/5/20 Tue 6/9/20 65 74 Steve Sysadmin[50%] Fixed Units $416.08 8 hrs Contractor 67 1.6.3.2 ERP Software 4.94 days Wed 5/20/20 Tue 5/26/20 Fixed Duration $1,945.87 71.75 hrs 68 1.6.3.2.1 Install Software 5 days Wed 5/20/20 Fri 5/22/20 61,62FS+2 days 69 Steve Sysadmin[50%],NetSUITE ERP License Fixed Units $652.83 47.75 hrs Contractor,SaaS 69 1.6.3.2.2 Test Software 3 days Fri 5/22/20 Tue 5/26/20 68 74 Steve Sysadmin[50%],Deborah Developer Fixed Units $1,293.04 24 hrs Contractor

TTP3 - TEAM BUSINESS

Page 1

ID WBS Task Mode Task Name Duration Start Finish Predecessors Successors Resource Names Type Cost Work Resource Group 70 1.6.3.3 Website 3 days Mon 5/18/20 Thu 5/21/20 Fixed Duration $1,296.91 55 hrs 71 1.6.3.3.1 Code Webpage 3 days Mon 5/18/20 Tue 5/19/20 61,62 72 Deborah Developer,Shopify,Webster Webdev Fixed Units $696.75 39 hrs Contractor,SaaS 72 1.6.3.3.2 Test Webpage 2 days Tue 5/19/20 Thu 5/21/20 71 74 Webster Webdev Fixed Units $600.16 16 hrs Contractor 73 1.7 System Test 20 days Tue 6/9/20 Tue 7/7/20 Fixed Duration $21,537.20 440 hrs 74 1.7.1 Integrate System Components 5 days Tue 6/9/20 Tue 6/16/20 55,59,66,69,72 75 Archie Architect,Steve Sysadmin Fixed Units $4,217.60 80 hrs Contractor 75 1.7.2 Test Integrated Components 15 days Tue 6/16/20 Tue 7/7/20 74 76 Steve Sysadmin,Deborah Developer,Webster Webdev Fixed Units $17,319.60 360 hrs Contractor 76 1.7.3 Deliver IT System 0 days Tue 7/7/20 Tue 7/7/20 75 78 Zack Bollack Fixed Units $0.00 0 hrs PM 77 1.8 System Transition 8.5 days Tue 7/7/20 Fri 7/17/20 Fixed Duration $9,232.56 224 hrs 78 1.8.1 Prepare System Documentation 3 days Tue 7/7/20 Fri 7/10/20 76 79 Archie Architect,Deborah Developer,Steve Sysadmin,Webster WebdevFixed Units $4,746.24 96 hrs Contractor 79 1.8.2 Review System Documentation 4 hrs Fri 7/10/20 Fri 7/10/20 78 80,81 Archie Architect,Zack Bollack Fixed Units $481.72 8 hrs Contractor,PM 80 1.8.3 Deliver System Documentation 0 days Fri 7/10/20 Fri 7/10/20 79 83 Archie Architect,Zack Bollack,Mamma Mia Fixed Units $0.00 0 hrs Contractor,PM,Owner 81 1.8.4 Provide Staff Training 5 days Fri 7/10/20 Fri 7/17/20 79 83 Eddie Money,Ivan Tory,Mamma Mia,NetSUITE Training[1 session]Fixed Units $4,004.60 120 hrs Accounting,Supply/Inventory Manager,Owner,Training 82 1.9 Project Closure 2.81 days Fri 7/17/20 Wed 7/22/20 Fixed Duration $3,531.66 74.5 hrs 83 1.9.1 Document Lessons Learned 2 days Fri 7/17/20 Tue 7/21/20 80,81 84 Archie Architect,Bill Rye,Deborah Developer,Zack BollackFixed Units $2,997.28 64 hrs Contractor,Food Services,PM 84 1.9.2 Update Project Files 2 hrs Tue 7/21/20 Tue 7/21/20 83 86,89 Zack Bollack Fixed Units $134.00 2 hrs PM 85 1.9.3 Project Closure Meeting 0.25 days Tue 7/21/20 Wed 7/22/20 Fixed Duration $134.00 4 hrs 86 1.9.3.1 Gain Formal Acceptance 2 hrs Tue 7/21/20 Wed 7/22/20 84 87 Mamma Mia,Zack Bollack Fixed Units $134.00 4 hrs Owner,PM 87 1.9.4 Archive Project Files 2 hrs Wed 7/22/20 Wed 7/22/20 86 88 Zack Bollack Fixed Units $134.00 2 hrs PM 88 1.9.5 Release Resources 30 mins Wed 7/22/20 Wed 7/22/20 87 89 Archie Architect,Deborah Developer,Steve Sysadmin,Zack Bollack,Webster WebdevFixed Units $132.38 2.5 hrs Contractor,PM 89 1.10 Project Close 0 days Wed 7/22/20 Wed 7/22/20 84,88 Mamma Mia,Zack Bollack Fixed Units $0.00 0 hrs Owner,PM

TTP3 - TEAM BUSINESS

Page 2

Appendix D - Team Business Project Risk Assessment.xlsx

Risk Register

WBS Task Name Task Level Risk Description Risk Category (Risk Type) Risk Probability Risk Consequence (Impact) Initial Risk Score (Probability * Impact) Risk Handling Category Risk Handling/Control Plan Risk Owner (Risk Manager) Cost
1 Mamma's Sandwich Shoppe & Bakery 0 $51,966.99
1.1 Project Start 1 $0.00
1.2 Project Management 1 $5,932.97
1.2.1 Initiation 2 $2,925.81
1.2.1.1 Initial Project Meeting 3 Customer non-responsive or schedule conflicts People 10% $784.68 $78.47 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Project Manager $784.68
1.2.1.2 Inputs 3 $189.35
1.2.1.2.1 Business Case 4 Business case becomes obsolete or is undermined by external or internal changes Client, Cost, Schedule 10% $0.00 $0.00 Mitigate Complete a business case if not already provided Ensure purpose is well defined within the Project Charter Project Sponsor $0.00
1.2.1.2.2 Environmental Factors 4 Acts of God and lead to loss of resources, materials, and premises Environmental 10% $113.61 $11.36 Accept Ensure insurance for resource materials are in place Provide project team with emergency procedures Project Manager $113.61
1.2.1.2.3 Organizational Processes 4 Organizational processes are not clearly defined or understood Client 25% $75.74 $18.94 Mitigate Analyze organizational processes and document within process workflows Ensure processes are well defined within the Project Charter Project Sponsor $75.74
1.2.1.3 Outputs 3 $1,951.78
1.2.1.3.1 Project Charter 4 Project design and deliverable definition is incomplete Technical, Cost, Schedule 25% $1,072.00 $268.00 Mitigate Define the scope in detail using input from subject matter experts Project Manager $1,072.00
1.2.1.3.2 Kickoff Meeting 4 Customer non-responsive or schedule conflicts Schedule 10% $209.78 $20.98 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Project Manager $209.78
1.2.1.3.3 Progress Review Meeting 4 $670.00
1.2.1.3.3.1 Project Status Meeting 1 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.2 Project Status Meeting 2 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.3 Project Status Meeting 3 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.4 Project Status Meeting 4 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.5 Project Status Meeting 5 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.6 Project Status Meeting 6 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.7 Project Status Meeting 7 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.8 Project Status Meeting 8 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.9 Project Status Meeting 9 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.1.3.3.10 Project Status Meeting 10 5 Customer non-responsive or schedule conflicts Schedule 10% $67.00 $6.70 Accept Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $67.00
1.2.2 Initiation COMPLETE 2 $0.00
1.2.3 Planning 2 $3,007.16
1.2.3.1 Activity Planning 3 $134.00
1.2.3.1.1 Activity Definitions 4 Project activity definitions are incomplete Technical 25% $33.50 $8.38 Mitigate Identify all logical relationships to generate full network activity Ensure schedules remain flexible and dynamic so that durations can be immediately transmitted to remaining project activities for accurate scheduling Project Manager $33.50
1.2.3.1.2 Activity Sequences 4 Unplanned work must be accomodated Schedule 15% $33.50 $5.03 Accept Assess and prioritize unplanned work based on weighted score (value versus complexity) Communicate with Project Sponsor and Project team on the impact and determine if priorities must be shifted to address issues Project Manager $33.50
1.2.3.1.3 Activity Resources 4 Lack of resources pose risk at meeting project goals Contractual 10% $33.50 $3.35 Mitigate Track and analyze resources using resource leveling techniques Adjust project resource's workloads in accordance with estimated risks and availability Project Manager $33.50
1.2.3.1.4 Activity Durations 4 Pressure to reduce activity durations increase risk of errors Schedule 15% $33.50 $5.03 Mitigate Share the schedule with key stakeholders to reduce the risk of scope creep and errors Project Manager $33.50
1.2.3.2 Scope Management 3 $268.00
1.2.3.2.1 Project WBS 4 Unplanned work must be accommodated Schedule 15% $268.00 $40.20 Accept Assess and prioritize unplanned work based on weighted score (value versus complexity) Communicate with Project Sponsor and Project team on the impact and determine if priorities must be shifted to address issues Project Manager $268.00
1.2.3.3 Project Cost Planning 3 $1,364.04
1.2.3.3.1 Cost Estimates 4 Cost estimate exceeds project budget Financial 5% $1,212.48 $60.62 Mitigate Build in 10% contingency on costs and scheduling Use two methods of cost estimation (parametric and engineering estimate) to cross refence and provide accuracy Project Manager $1,212.48
1.2.3.3.2 Project Budget 4 Cost estimate exceeds project budget Financial 5% $151.56 $7.58 Mitigate Build in 10% contingency on costs and scheduling Cross reference cost estimates to Work Breakdown Structure (WBS) to determine of resources are appropriately aligned Project Manager $151.56
1.2.3.4 Procurement Management 3 $303.12
1.2.3.4.1 IT System Purchases/Acquisitions 4 Project funding is reduced Financial 5% $151.56 $7.58 Mitigate Closely monitor all costs in real-time to ensure activites stay aligned with approved budget Consult with Project Sponsor and Finance to plan for budget reductions based on the tolerance for risk Project Sponsor $151.56
1.2.3.4.2 IT System Contracting 4 Ineffective workflows delay in contract approvals Contractual 5% $151.56 $7.58 Mitigate Specify deadlines for performance of all stages of the agreement Consult with Project Sponsor to suspend or delay contractual work Project Sponsor $151.56
1.2.3.5 Risk Management 3 $402.00
1.2.3.5.1 Project Risks 4 Errors with estimating risks Technical 10% $201.00 $20.10 Mitigate Continuously monitor and improve upon risks Mitigate most probable and threatening risks first Consult with Project Sponsor on decision-making process Project Manager $201.00
1.2.3.5.2 Risk Responses 4 Risk responses are not clearly defined or understood Technical 10% $201.00 $20.10 Mitigate Ensure risk responses are accurate and clearly defined Consult with Project Sponsor and key stakeholders to gain acceptance Project Manager $201.00
1.2.3.6 Communication Plan 3 Lack of clarity increases number of impromptu meetings and decreases productivity Cost, Schedule, Client 25% $0.00 $0.00 Mitigate Incorporate communication frequency, goals, and key stakeholders (audience) for each communication event Use the most appropriate channel of communication for target audience such as email, face-to-face, or phone calls Project Manager $0.00
1.2.3.7 Project Schedule 3 Delay in earlier project phases jeopardizes ability to meet fixed date Schedule 25% $536.00 $134.00 Mitigate Ensure the project plan is accurate using the work breakdown structure as reference Use tracking Gantt to preemptively identify schedule slippage Project Manager $536.00
1.2.4 Planning COMPLETE 2 $0.00
1.3 IT System Design 1 $2,021.70
1.3.1 IT Contractors 2 $268.00
1.3.1.1 Interviews 3 Lack of participation from qualified candidates People 25% $268.00 $67.00 Mitigate Identify alternative sources to market job requisitions such as the employment of technical recruiters or staffing agencies Project Manager $268.00
1.3.1.2 Hiring 3 Delays in onboarding consultant and/or contractor resources Contractual 25% $0.00 $0.00 Mitigate Build in and protect lead times within the schedule to allow for onboarding of consultant and/or contractor resources Escalate to Project Sponsor and incorporate late penalties within the contract Project Sponsor $0.00
1.3.2 Initial Design Specification 2 Project design and deliverable definition is incomplete Technical 20% $1,326.26 $265.25 Mitigate Define the scope in detail using input from subject matter experts Systems Engineer $1,326.26
1.3.3 Review Design Specification 2 Participants non-responsive or schedule conflicts Schedule 5% $427.44 $21.37 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Consulting Architect $427.44
1.3.4 Deliver Design Specification 2 Project sponsor refuses to approve deliverables or delays approval Client, Cost, Schedule 10% $0.00 $0.00 Mitigate Ensure decision makers with budgetary authority are identified before project initiation Include dates within Communication Plan for sign-off points upfront Project Manager $0.00
1.4 System Networking 1 $750.85
1.4.1 Networking Requirements 2 Unclear or incomplete requirements result in need to restart requirements development Technical, Schedule 5% $282.11 $14.11 Mitigate Communicate with stakeholders to agree in advance all constraints associated with features and performance Assign action owner to verify assumptions Breakdown work packages into smaller iterations to reduce risk and properly align resources to tasks Consulting Architect $282.11
1.4.2 Networking Procurement 2 Networking equipment delayed in shipment Contractual, Cost, Schedule 15% $34.75 $5.21 Transfer Insure the shipment/parcel Contact Verizon (vendor) and request expedited shipment Project Sponsor $34.75
1.4.3 Networking Installation 2 Technical difficulties building and installing network components Technical, Schedule 5% $433.99 $21.70 Mitigate Get further details on installing the product from the Vendor's support department as soon as possible Bring in technical experts to assit in the deployment of network services Delay project if necessary Systems Engineer $433.99
1.5 System Hardware 1 $3,598.90
1.5.1 Hardware Requirements 2 Unclear or incomplete requirements result in need to restart requirements development Technical, Schedule 5% $282.11 $14.11 Mitigate Communicate with stakeholders to agree in advance all constraints associated with features and performance Assign action owner to verify assumptions Breakdown work packages into smaller iterations to reduce risk and properly align resources to tasks Consulting Architect $282.11
1.5.2 Hardware Procurement 2 Hardware is delayed in shipment Contractual, Cost, Schedule 15% $2,432.80 $364.92 Transfer Insure the shipment/parcel Contact Toast (vendor) and request expedited shipment Project Sponsor $2,432.80
1.5.3 Hardware Installation 2 Technical difficulties building and installing hardware components Technical, Schedule 30% $883.99 $265.20 Mitigate Get further details on installing the product from the Vendor's support department as soon as possible Bring in technical experts to assist in the deployment of hardware components Delay project if necessary Systems Engineer $883.99
1.6 System Software 1 $5,361.15
1.6.1 Software Requirements 2 Unclear or incomplete requirements result in need to restart requirements development Technical, Schedule 5% $282.11 $14.11 Mitigate Communicate with stakeholders to agree in advance all constraints associated with features and performance Assign action owner to verify assumptions Breakdown work packages into smaller iterations to reduce risk and properly align resources to tasks Project Manager $282.11
1.6.2 Software Procurement 2 Unable to download software from online portal Financial, Contractual, Technical 15% $18.95 $2.84 Transfer Contact Oracle (vendor) support and open up support request Access mirror portal and download software packages/binaries from alternate location Project Sponsor $18.95
1.6.3 Software Installation 2 $5,060.10
1.6.3.1 Point of Sales Software 3 $1,817.32
1.6.3.1.1 Install Software 4 Technical difficulties in installing POS software Technical 25% $1,401.24 $350.31 Mitigate Get further details on installing the product from the Vendor's support department as soon as possible Bring in technical experts to assist in the deployment of hardware components Delay project if necessary Systems Engineer $1,401.24
1.6.3.1.2 Test POS Software 4 Project sponsor does not accept the system due to lack of functionality or capabilities Cost, Schedule, Technical 5% $416.08 $20.80 Mitigate Depending on severity, either send back to engineer for correction or identify new resource with skillsets that aligns with customer requirements Delay project if necessary Project Manager $416.08
1.6.3.2 ERP Software 3 $1,945.87
1.6.3.2.1 Install Software 4 Technical difficulties in installing ERP software Technical 25% $652.83 $163.21 Mitigate Get further details on installing the product from the Vendor's support department as soon as possible Bring in technical experts to assist in the deployment of hardware components Delay project if necessary Systems Engineer $652.83
1.6.3.2.2 Test Software 4 Project sponsor does not accept the system due to lack of functionality or capabilities Cost, Schedule, Technical 5% $1,293.04 $64.65 Mitigate Consult with stakeholders on requirements in accordance with business case Identify gaps in software and incorporate revisions to correct missing features and capabilities Project Manager $1,293.04
1.6.3.3 Website 3 $1,296.91
1.6.3.3.1 Code Webpage 4 Incomplete/Incorrect requirements result in need to restart development of webpage Technical, Schedule 25% $696.75 $174.19 Mitigate Open discussion with Project Sponsor and key stakeholders to identify issues and prepare change requests Web Developer $696.75
1.6.3.3.2 Test Webpage 4 Project sponsor does not accept webpage, requires rework Cost, Schedule, Technical 5% $600.16 $30.01 Mitigate Depending on severity, either send back to developer for correction or identify new developer with skillsets that aligns with customer requirements Delay project if necessary Project Manager $600.16
1.7 System Test 1 $21,537.20
1.7.1 Integrate System Components 2 Problems of integration with internal and external systems Cost, Schedule, Technical 25% $4,217.60 $1,054.40 Mitigate Communicate with stakeholders to agree in advance all constraints associated with features and performance Consult with external (vendor) technical experts to identify remediation steps to properly integrate with external systems Consulting Architect $4,217.60
1.7.2 Test Integrated Components 2 Difficulty in integrating modules/components due to lack of functionality Technical 15% $17,319.60 $2,597.94 Mitigate Identify gaps in software and hardware components Incorporate revisions to correct missing features and capabilities Implement agile method to break down modules into smaller iterations and tackle integration issues piece by piece Project Manager $17,319.60
1.7.3 Deliver IT System 2 Project sponsor refuses to approve deliverable or delays approval Client, Cost, Schedule 10% $0.00 $0.00 Mitigate Ensure decision makers with budgetary authority are identified before project initiation Include dates within Communication Plan for sign-off points upfront Project Sponsor $0.00
1.8 System Transition 1 $9,232.56
1.8.1 Prepare System Documentation 2 System documentation design is incomplete Technical 20% $4,746.24 $949.25 Mitigate Define the scope in detail using input from subject matter experts Project Manager $4,746.24
1.8.2 Review System Documentation 2 Participants non-responsive or schedule conflicts People, Schedule 5% $481.72 $24.09 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $481.72
1.8.3 Deliver System Documentation 2 Project sponsor refuses to approve deliverables or delays approval Client, Cost, Schedule 10% $0.00 $0.00 Mitigate Ensure decision makers with budgetary authority are identified before project initiation Include dates within Communication Plan for sign-off points upfront Project Sponsor $0.00
1.8.4 Provide Staff Training 2 Sheduling issues with customer personnel Schedule 15% $4,004.60 $600.69 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Delay training until full-participation can be provided Project Manager $4,004.60
1.9 Project Closure 1 $3,531.66
1.9.1 Document Lessons Learned 2 Participants non-responsive or schedule conflicts People, Schedule 5% $2,997.28 $149.86 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $2,997.28
1.9.2 Update Project Files 2 Participants non-responsive or schedule conflicts People, Schedule 5% $134.00 $6.70 Mitigate Keep trying to arrange acceptable schedule with Sponsor and Key Stakeholders Provide Project Sponsor and Key Stakeholders with email updates including project status and budget Project Manager $134.00
1.9.3 Project Closure Meeting 2 $134.00
1.9.3.1 Gain Formal Acceptance 3 Project sponsor refuses to approve deliverable or delays approval Client, Cost, Schedule 10% $134.00 $13.40 Mitigate Ensure decision makers with budgetary authority are identified before project initiation Include dates within Communication Plan for sign-off points upfront Project Sponsor $134.00
1.9.4 Archive Project Files 2 Project files are misplaced, deleted/erased, or incomplete Client, Schedule 5% $134.00 $6.70 Mitigate Provide shared storage capability that allows for version control, recovery, and team collaboration Provide private Uniformed Resource Locator (URL) hyperlink to Project Sponsor for information dissemination Project Manager $134.00
1.9.5 Release Resources 2 Resources are prematurely released Cost, Contractual, Schedule 5% $132.38 $6.62 Mitigate Ensure the project plan and schedule are accurately followed Project Manager $132.38
1.1 Project Close 1 $0.00
Total $51,967.00 $8,052.90
15% of cost at risk

Dropdown Lists

Low Accept Technical
Medium Mitigate Cost
High Transfer Schedule
Client
Contractual
Weather
Financial
Political
Environmental
People

TPP-5 Consolidated Project Plan - Team Business - Draft (Feb24).docx

Project Management Plan

Group Name:

Team Business

Project Name:

Mamma’s Sandwich Shoppe & Bakery

Project Manager

Zachary Bollack

Document Revision #:

1.0

Project Management Plan | Project Name

Government of the Northwest Territories 2020 4

Table of Contents Table of Contents 1 1 Executive Summary 2 1.1 Purpose, Scope, and Objectives 2 1.2 Assumptions, Constraints and Risks 2 1.3 Project Deliverables 2 1.4 Schedule and Budget Summary 3 1.5 References 3 1.6 Definitions and Acronyms 3 2 Project Organization 3 2.1 Roles and Responsibilities 3 2.2 Stakeholder 3 3 Managerial Process Plans 3 3.1 Startup Plan 3 3.1.1 Estimates 3 3.1.2 Staffing 3 3.2 Work Plan 4 3.2.1 Work Breakdown Structure 4 3.2.2 Schedule Allocation 4 3.2.3 Budget Allocation 4 3.2.4 Quality Control 5 3.2.5 Reporting 5 3.2.6 Project Metrics 5 3.2.7 Risk Management Plan 5 3.2.8 Project Closeout Plan 5

Executive Summary

This section of the Project Management Plan provides an overview of the purpose, scope and objectives of the project for which the Plan has been written, the project assumptions and constraints, a list of project deliverables, a summary of the project schedule and budget, and the plan for evolving the Project Management Plan.

Purpose, Scope, and Objectives

Define the purpose and scope of the project.

Describe any considerations of scope or objectives to be excluded from the project or the deliverables.

Provide a concise summary of:

· the project objectives,

· the deliverables required to satisfy the project objectives, and

· the methods by which satisfaction of the objectives will be determined.

Assumptions, Constraints and Risks

Describe the assumptions on which the project is based.

Describe the imposed constraints and risks on the project such as:

· schedule,

· budget,

· resources,

· quality,

· software to be reused,

· existing software to be incorporated,

· technology to be used, and

· external interfaces.

Project Deliverables

Identify and list the following, as required to satisfy the terms of the project charter or contract:

· project deliverables (either directly in this Plan, or by reference to an external document),

· delivery dates,

· delivery location, ands

· quantities required.

Specify the delivery media.

Schedule and Budget Summary

Provide a summary of the schedule and budget for the project.

References

Andersen, E. (2006). Milestone Planning – A Different Planning Approach. Project Management Institute. Retrieved from https://www.pmi.org/learning/library/milestone-different-planning-approach-7635

Brotherton, S., Fried, R., & Norman, E. (2008, October 19). Applying the Work Breakdown Structure to the Project Management Lifecycle. Project Management Institute. Retrieved from: https://www.pmi.org/learning/library/applying-work-breakdown-structure-project-lifecycle-6979

Lutzker, D. (2002, October 3). Practical Quality Management for Project Managers. Project Management Institute. Retrieved from https://www.pmi.org/learning/library/practical-quality-management-project-managers-16

NutCache.com (n.d.). What is Critical Path in Project Management and How Can it Help Me? NutCache. Retrieved February 23, 2020 from: https://www.nutcache.com/blog/what-is-critical-path-in-project-management-and-how-can-it-help-me/

Definitions and Acronyms

Define, or provide references to documents or annexes containing the definition of all terms and acronyms required to properly understand this Plan.

Project Organization

Roles and Responsibilities

Identify and state the roles and responsibilities of the project team.

Stakeholder

Identify the stakeholders.

Managerial Process Plans

This section of the Project Management Plan specifies the project management processes for the project. This section defines the plans for project startup, risk management, project work, project tracking and project closeout.

Startup Plan

Estimates

Specify the estimated cost, schedule and resource requirements for conducting the project, and specify the associated confidence levels for each estimate.

Specify the methods, tools and techniques used to estimate project cost, schedule and resource requirements;

Specify the sources of estimate data and the basis of the estimation such as: analogy, rule of thumb, standard unit of size, cost model, historical database, etc.

Specify the methods, tools, techniques to be used to reestimate the project cost, schedule and required resources.

Specify the schedule for reestimation, which might be regular, a periodic or eventdriven (e.g.: on project milestones).

Staffing

Specify the number of required staff, providing the following details:

· number of personnel by skill level,

· numbers and skill levels in each project phase, and

· duration of personnel requirement.

Specify the sources of staff personnel (e.g.: internal transfer, new hire, contracted, etc.)

Consider using resource Gantt charts, resource histograms, spreadsheets and tables to depth staffing plan by skill level, by project phase, and by aggregations of skill levels and project phases.

Work Plan

Work Breakdown Structure

The Work Breakdown Structure (WBS), listed in Appendix C – Team Business Task Sheet, specifies the various work activities and work packages that will be performed within the Mamma’s Sandwich Shoppe & Bakery project plan. The WBS serves as the foundation of the project plan’s processes by organizing and defining the total scope of the project (Brotherton, Fried, & Norman, 2008), allowing the project team to identify the sequencing and dependencies of work activities quickly.

The activities listed within the WBS have broken down into ten (10) different level two (2) tasks, each representing a deliverable-oriented hierarchical decomposition of the work that needs to be executed by the project team. The following hierarchical diagram demonstrates the work activities broken down into three task levels:

The decomposition of these activities was based on each activity’s dependency on its previous stage or parallel activities that form the critical path to execution and completion (nutcache.com, 2019). Within each level three (3) work package, risks were identified and exposed, allowing Team Business’ project team to accurately identify the necessary resource requirements, schedule duration, and cost estimates.

Schedule Allocation

Once the project work activities were defined and sequenced within the WBS, the activities were then transferred into a Gantt chart using the Microsoft Project productivity tool allowing the project schedule to be easily read and understood by all key stakeholders. The project activity durations were allocated by implementing a bottom-up approach where each work task is estimated based on the subtasks and estimated activity duration within each work package and aggregated. The associated Gantt chart within the Microsoft Project Plan, see Appendix A – Team Business Project Plan, demonstrates all of the critical stages within the project, listed on the y-axis, and their durations as bar charts with the time scale on the x-axis.

There were a few opportunities for concurrent work activities, such as within the Project Management phase, where activities were defined and sequenced to comprise the WBS; additionally, within these activities, costs were planned and estimated concurrently with systems acquisitions and contracting processes. The consolidation of these activities allowed the project planning phase to be executed in a more desirable timeline allowing for a more rapid delivery timeframe and formed the critical path. The critical path, or series of interrelated task dependencies that enable the project to be completed in the shortest amount of time, within the schedule is depicted in the following diagram:

Milestones serve as the exit gates or critical checkpoints that signify the successful completion of a project phase or project goal (Anderson, 2006). There are nine (9) milestones listed within Mamma’s Sandwich Shoppe & Bakery project plan:

Budget Allocation

The budget that supports Mamma’s Sandwich Shoppe & Bakery project was derived by using the WBS alongside investigating resource information from various sources such as the United States Bureau of Labor and Statistics and vendor websites that provided licensing quotes for their hardware, networking, or system licensing and components. This budget was incorporated into Team Business’ project plan within the Resource Cost Sheet, see Appendix B – Team Business Resource Sheet.

The estimated costs for resources allocated to this project include the costs for the personnel (internal and external), IT system hardware, Software-as-a-Service licenses, Internet Service Provider services, Service and License activation fees, and system training. The Project Plan listed in Appendix C – Team Business Task Sheet lists out each of these activities in greater detail with its associated costs.

1

Mamma’s Sandwich Shoppe & Bakery

$52,141.99

1.1

Project Start

$0

1.2

Project Management

$5,932.97

1.3

IT Systems Design

$2,021.70

1.4

System Networking

$800.85

1.5

System Hardware

$3,723.90

1.6

System Software

$5,361.15

1.7

System Test

$21,537.20

1.8

System Transition

$9,232.56

1.9

Project Closure

$3,531.66

1.10

Project Close

$0

Project Risks

$8,052.90

Total Estimated Costs

$60,194.99

The overall anticipated budget to support the project and project team is $60,194.99, which includes the $52,141.99 estimated project cost with an additional 15% overhead, or $8,052.90 projected for risk responses. These projected costs are 40% below the anticipated budget providing additional funding for unanticipated risks while allowing Mamma Mia to integrate other IT initiatives for her business.

Quality Control

To provide customer satisfaction and ensure that the project plan meets Mamma Mia’s business needs, total quality management is implemented to accurately asses, validate, and verify the needs and requirements of the organization to drive the project plan and align its resources appropriately.

The initial steps within the quality assurance and quality control process are first to gather the technical requirements based on Mamma’s Sandwich Shoppe & Bakery’s use-case. These steps were identified within the task and subtasks to 1.2.1.2 – Project Management, where Mamma’s business case, environmental factors, and organizational processes were identified and used to define the project plan. To strengthen the project plan and ensure all activities were conducive to the overall project, each requirement was verified to be clearly understood and quantified based on feedback from Mamma Mia, known as the voice of the customer.

Once these requirements were defined, the WBS was generated and distributed to all key stakeholders in the form of an activity network diagram that exemplified all logical relationships, or interdependencies, of the project’s activities to help demonstrate the workflow of the project. Additionally, risks and risk responses were identified within a risk register, see Appendix D – Team Business Project Risk Assessment which provided the overall cost of quality (COQ) that demonstrated any costs attributed to quality such as risk prevention/aversion, failures, and non-conformance costs (Lutzker, 2002).

Furthermore, comprehensive test planning was incorporated within the project plan under the both 1.6 – System Software and 1.7 – System Test work activities, testing each of their requirements and configurations, such as the Enterprise Resource Planning software, Point of Sale software, and e-commerce webpage and then testing the integration of these components to support Mamma Mia’s business case. The final tests executed upon delivery is the User Acceptance Testing, which provides the information necessary for the project team to identify any defects and establish a change control process to remediate any issues.

Reporting

Specify the reporting mechanisms, report formats and information flows to be used in communicating the status of requirements, schedule, budget, quality, and other desired or required status metrics within the project and to entities external to the project.

Specify the methods, tools and techniques of communication.

Specify a frequency and detail of communications related to project management and metrics measurement that is consistent with the project scope, criticality, risk and visibility.

Project Metrics

Specify the methods, tools, and techniques to be used in collecting and retaining project metrics.

Specify the following metrics process information:

· identification of the metrics to be collected,

· frequency of collection, and

· processes for validating, analyzing, and reporting the metrics.

Risk Management Plan

Specify the risk management plan for identifying, analyzing, and prioritizing project risk factors.

Specify plans for assessing initial risk factors and for the ongoing identification, assessment, and mitigation of risk factors throughout the life cycle of the project.

Project Closeout Plan

Identify the plans necessary to ensure orderly closeout of the project.

Specify the following:

· a staff reassignment plan

· a process for archiving project materials,

· a process for capturing project metrics in the business projects database,

· a process for postmortem debriefings of project personnel, and

· a plan for preparation of a final report to include lessons learned and an analysis of project objectives achieved.

· plans for assuring that safety, privacy, and security requirements are met,

· special facilities or equipment specification,

· product installation plans,

· user training plans,

· integration plans,

· data conversion plans,

· system transition plans,

· product maintenance plans, or

· product support plans.

Mamma's Sandwich Shop & Bakery

Project Start

Project Mgmt

IT System Design

System Networking

System Hardware

System Software

System Test

System Transition

Project Closure

Project Close

Initiation

Planning

IT Contractors

Initial Design

Review Design

Deliver Design

Reqs

Procure

Install

Reqs

Procure

Install

Reqs

Procure

Install

Integrate

Test

Delivery

Prepare Documents

Review Documents

Deliver Documents

Training

Lessons Learned

Update Files

Closure Meeting

Archive Files

Release Resources

Project Start

Project Mgmt

Project Planning

System Networking

System Hardware

System Software

System Test

System Transition

Initiation

Project Charter

Kickoff Meeting

Activity Planning

Procurement Mgmt

IT System Design

Integration

Delivery

Project Close

Documentation

Training

Lessons Learned

Project Files

Release Resources

M1 1.1 Project Start

M2 1.2.2 Project Initiation COMPLETE

M3 1.2.4 Project Planning COMPLETE

M4 1.3.4 Deliver IT Design Specs

M5 1.7.3 Deliver IT System

M6 1.8.3 Deliver IT System Documentation

M7 1.8.4 Provide Staff Training

M8 1.9.3.1 Gain Closure Accept -ance

M9 1.10 Project Close

Page 1 of 7