Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9

Week 10Week 11Week 12Week 13Week 14Week 15Week 16Week 17Week 18Week 19Week 20Week 21Week 22Week 23Week 24Week 25Week 26

Task ID

TasksDurationDependencies

AKick Off Meeting and Client Communication1 Week-

BObjective 1 - Functional Requirements7 Weeks

A

CStakeholder Mapping4 Weeks

A

D

Stakeholder Identification1 Week

A

E

Stakeholder Meetings/ Conversations1 Week

A,D

F Stakeholder Priorisation2 Weeks

A,D

G Stakeholder Matrix (incl. Prioritisation and Objectives)1 Week

A,D,E,F

HSoftware Benchmarking3 Weeks

C

I Data Collection Process1 Week

C

J Benchmark Analysis2 Weeks

C,I

KObjective 2 - Structural Requirements8 Weeks

B

LSystem Environment Analysis3 Weeks

B

M Interview with the IT Leader/ Application Owners1 Week

B

N Producing of IT Environment Graphics2 Weeks

B,M

O Need Analysis1 Week

B,M,N

PPersonnel Analysis3 Weeks

L

Q Project Role Planning (Which roles are necessary?)2 Weeks

L

R Actual State Analysis (Does the company has the staff?)1 Week

L,Q

SRisk Identification and Analysis8 Weeks

B

T Risk Identification4 Weeks

B

U Risk Evaluation3 Weeks

B,T

V Risk Ranking (Matrix)2 Weeks

B,T,U

WObjective 3 - Resources Requirements7 Weeks

K

XProject Time Planning3 Weeks

K

Y Project Break Down and Time Estimation2 Weeks

K

Z Draw Network Diagram1 Week

K,Y

AA Draw Gantt Chart1 Week

K,Y,Z

ABLife-Cycle Cost Analysis4 Weeks

X

AC Analysing Types of Costs and Necessary Activities2 Weeks

X

AD Data (Cost) Collection for Revealed Activities2 Weeks

X, AC

AE Cost Accumulation1 Week

X,AC,AD

AFProducing the Study3 Weeks

B,K,W

AGRecommendations2 Weeks

B,K,W

AHStudy Submission1 Week

B,K,W,AF,AG

AIPresentation of the Results1 Week

B,K,W,AF,AG

AJ

Evaluation Meeting1 Week

B,K,W,AF,AG

Key:

Slack Time

Ancillary Process

W

AF

Gantt Chart

Critical PathBK

Timeframe (6 months = 26 Weeks)

AJ