Project Management (Microsoft Project (WBS))

profilegd1222
Gee_Week2Scope-Schedule-Budget.docx

1

8

Walmart Store

Gene A. Duplantier

Tasks and Milestone

Task Name

Duration

Business Plan Document

30 days

Project Planning

30 days

Funding

10 days

Budgeting

10 days

Goods and services/Procurement

10 days

Scheduling

0 days

Store Design

45 days

Security System

4 days

Interior Design

15 days

Lightening

15 days

Furnishings

4 days

Art and drawings

4 days

Decisions on paints and Color Schemes

3 days

Floor Space/ In store Displays

0 days

Windows Displays

30 days

Communication networks

10 days

Exterior Design

13 days

Lightening

10 days

Signage

2 days

Landscaping

2 days

Parking

2 days

Cleaning and Upgrading

7 days

Constructions and design

1 day

Vendor selections

1 day

Interior

2 days

Bathrooms

2 days

Cashier Counters

2 days

Customer service area

1 day

Employees area

1 day

Utilities

4 days

Electrical

2 days

Gas

2 days

Water

2 days

Sewer

1 day

Communication networks

23 days

Bid process

1 day

Vendor selections

1 day

Vendor Contracts

2 days

Cabling

2 days

Phone System

2 days

Application Implementation

3 days

Point Of sale

3 days

Inventory Management

2 days

Integrate SKU Data

2 days

Quality Review

3 days

Code Compliance

1 day

Occupancy Certificate

1 day

Head Office Review

2 days

Staffing

2 days

Advertising

1 day

Interviewing

1 day

Hiring

2 days

Training

1 day

Merchandising

11 days

Assemble Displays

1 day

Price Ticketing

1 day

SKU Scan

3 days

Display Merchandise

3 days

Gift Cards

3 days

Display Store Policies

4 days

Marketing

11 days

Staff Business Cards

4 days

Branded Shopping Bags

2 days

New Location Updates

5 days

New Location Updates

13 days

New Catalog

5 days

Print Media

5 days

Internet

3 days

Grand Opening

4 days

Special Guest Invitation

2 days

Advertising

3 days

Catering

1 day

Entertainment

1 day

Budget Estimates

 

Project Initiation

Project Planning

Project Execution

Project Shutdown

Category

Expense Totals

Business Plan Document

 

 

 

 

Project Planning

 

 

 

 

Funding

$ 120.00

$ 341.00

$ 200.00

$ 120.00

$ 781.00

Budgeting

$ 140.00

$ 230.00

$ 219.00

$ 340.00

$ 929.00

Goods and services/Procurement

$ 200.00

$ 210.00

$ 340.00

$ 230.00

$ 980.00

Scheduling

$ 260.00

$ 190.00

$ 461.00

$ 120.00

$ 1,031.00

Store Design

 

 

 

 

Security System

$ 380.00

$ 150.00

$ 703.00

$ 200.00

$ 1,433.00

Interior Design

$ 440.00

$ 130.00

$ 824.00

$ 390.00

$ 1,784.00

Lightening

$ 500.00

$ 110.00

$ 945.00

$ 580.00

$ 2,135.00

Furnishings

$ 560.00

$ 90.00

$ 1,066.00

$ 770.00

$ 2,486.00

Art and drawings

$ 620.00

$ 70.00

$ 1,187.00

$ 960.00

$ 2,837.00

Decisions on paints and Color Schemes

$ 680.00

$ 50.00

$ 1,308.00

$ 1,150.00

$ 3,188.00

Floor Space/ In store Displays

$ 740.00

$ 30.00

$ 1,429.00

$ 1,340.00

$ 3,539.00

Windows Displays

 

 

 

 

Communication networks

$ 860.00

$ 672.00

$ 1,671.00

$ 1,720.00

$ 4,923.00

Exterior Design

 

 

 

 

Lightening

$ 980.00

$ 91.17

$ 1,913.00

$ 2,100.00

$ 5,084.17

Signage

 

 

 

 

Landscaping

$ 1,100.00

$ 128.17

$ 2,155.00

$ 2,480.00

$ 5,863.17

Parking

$ 1,160.00

$ 146.67

$ 2,276.00

$ 2,670.00

$ 6,252.67

Cleaning and Upgrading

 

 

 

 

Constructions and design

$ 1,280.00

$ 183.67

$ 2,518.00

$ 3,050.00

$ 7,031.67

Vendor selections

$ 1,340.00

$ 202.17

$ 2,639.00

$ 3,240.00

$ 7,421.17

Interior

$ 1,400.00

$ 220.67

$ 2,760.00

$ 3,430.00

$ 7,810.67

Bathrooms

$ 1,460.00

$ 239.17

$ 2,881.00

$ 3,620.00

$ 8,200.17

Cashier Counters

$ 1,520.00

$ 257.67

$ 3,002.00

$ 3,810.00

$ 8,589.67

Customer service area

$ 1,580.00

$ 276.17

$ 3,123.00

$ 4,000.00

$ 8,979.17

Employees area

$ 1,640.00

$ 294.67

$ 3,244.00

$ 4,190.00

$ 9,368.67

Utilities

 

 

 

 

Electrical

$ 1,760.00

$ 331.67

$ 3,486.00

$ 4,570.00

$ 10,147.67

Gas

$ 1,820.00

$ 350.17

$ 3,607.00

$ 4,760.00

$ 10,537.17

Water

$ 1,880.00

$ 368.67

$ 3,728.00

$ 4,950.00

$ 10,926.67

Sewer

$ 1,940.00

$ 387.17

$ 3,849.00

$ 5,140.00

$ 11,316.17

Communication networks

 

 

 

 

Bid process

$ 2,060.00

$ 424.17

$ 4,091.00

$ 5,520.00

$ 12,095.17

Vendor selections

$ 2,120.00

$ 442.67

$ 4,212.00

$ 5,710.00

$ 12,484.67

Vendor Contracts

$ 2,180.00

$ 461.17

$ 4,333.00

$ 5,900.00

$ 12,874.17

Cabling

$ 2,240.00

$ 479.67

$ 4,454.00

$ 6,090.00

$ 13,263.67

Phone System

$ 2,300.00

$ 498.17

$ 4,575.00

$ 6,280.00

$ 13,653.17

Application

Implementation

 

 

 

 

Point Of sale

$ 2,420.00

$ 535.17

$ 4,817.00

$ 6,660.00

$ 14,432.17

Inventory Management

$ 2,480.00

$ 553.67

$ 4,938.00

$ 6,850.00

$ 14,821.67

Integrate SKU Data

$ 2,540.00

$ 572.17

$ 5,059.00

$ 7,040.00

$ 15,211.17

Quality Review

 

 

 

 

Code Compliance

$ 2,660.00

$ 609.17

$ 5,301.00

$ 7,420.00

$ 15,990.17

Occupancy Certificate

$ 2,720.00

$ 627.67

$ 5,422.00

$ 7,610.00

$ 16,379.67

Head Office Review

$ 2,780.00

$ 646.17

$ 5,543.00

$ 7,800.00

$ 16,769.17

Staffing

 

 

 

 

Advertising

$ 2,900.00

$ 683.17

$ 5,785.00

$ 8,180.00

$ 17,548.17

Interviewing

$ 2,960.00

$ 701.67

$ 5,906.00

$ 8,370.00

$ 17,937.67

Hiring

$ 3,020.00

$ 720.17

$ 6,027.00

$ 8,560.00

$ 18,327.17

Training

 

 

 

 

Merchandising

$ 3,140.00

$ 757.17

$ 6,269.00

$ 8,940.00

$ 19,106.17

Assemble Displays

$ 3,200.00

$ 775.67

$ 6,390.00

$ 9,130.00

$ 19,495.67

Price Ticketing

$ 3,260.00

$ 794.17

$ 6,511.00

$ 9,320.00

$ 19,885.17

SKU Scan

$ 3,320.00

$ 812.67

$ 6,632.00

$ 9,510.00

$ 20,274.67

Display Merchandise

$ 3,380.00

$ 831.17

$ 6,753.00

$ 9,700.00

$ 20,664.17

Gift Cards

$ 3,440.00

$ 849.67

$ 6,874.00

$ 9,890.00

$ 21,053.67

Display Store Policies

$ 3,500.00

$ 868.17

$ 6,995.00

$ 10,080.00

$ 21,443.17

Marketing

 

 

 

 

Staff Business Cards

$ 3,620.00

$ 905.17

$ 7,237.00

$ 10,460.00

$ 22,222.17

Branded Shopping Bags

$ 3,680.00

$ 923.67

$ 7,358.00

$ 10,650.00

$ 22,611.67

New Location Updates

$ 3,740.00

$ 942.17

$ 7,479.00

$ 10,840.00

$ 23,001.17

New Location Updates

$ 3,800.00

$ 960.67

$ 7,600.00

$ 11,030.00

$ 23,390.67

New Catalog

$ 3,860.00

$ 979.17

$ 7,721.00

$ 11,220.00

$ 23,780.17

Print Media

$ 3,920.00

$ 997.67

$ 7,842.00

$ 11,410.00

$ 24,169.67

Internet

$ 3,980.00

$ 1,016.17

$ 7,963.00

$ 11,600.00

$ 24,559.17

Grand Opening

 

 

 

 

Special Guest Invitation

$ 4,100.00

$ 1,053.17

$ 8,205.00

$ 11,980.00

$ 25,338.17

Advertising

$ 4,160.00

$ 1,071.67

$ 8,326.00

$ 12,170.00

$ 25,727.67

Catering

$ 4,220.00

$ 1,090.17

$ 8,447.00

$ 12,360.00

$ 26,117.17

Entertainment

$ 4,280.00

$ 1,108.67

$ 8,568.00

$ 12,550.00

$ 26,506.67

Total Costs

$ 128,340.00

$ 30,442.67

$ 255,167.00

$ 350,760.00

$ 764,709.67

References

Maserang, S. (2002). project Management: Tools & Techniques. Retrieved from www.umsl.edu: http://www.umsl.edu/~sauterv/analysis/488_f02_papers/ProjMgmt.html

Ridgwell, M. (2010, 01 28). How to Successfully Closeout a Project. Retrieved from network.projectmanagers.net: http://network.projectmanagers.net/profiles/blogs/how-to-successfully-closeout-a