Calculation Sheet

ID Job Description Immediate Predecessors Planned Duration (Weeks) Staff (Number) Rate/Person/Week Task Cost (BAC)
A 1.0 ASSEMBLE ENGINE MOUNT Start 2 4 $1,440 $11,520
B 2.0 FIN PREPARATION Start 1 3 $1,440 $4,320
C 3.0 MARK FIN AND LAUNCH LUG LINES Start 1 3 $1,440 $4,320
D 4.0 INSERTING ENGINE MOUNT A 2 3 $1,440 $8,640
E 5.0 ATTACH FINS D 1 3 $1,440 $4,320
F 6.0 ATTACH SHOCK CORD Start 2 3 $1,440 $8,640
G 7.0 ASSEMBLE NOSE CONE Start 1 2 $1,440 $2,880
H 8.0 ATTACH PARACHUTE/SHOCK CORD G 1 1 $1,440 $1,440
I 9.0 ATTACH LAUNCH LUG E 1 1 $1,440 $1,440
J 10.0 PAINTING THE ROCKET I 1 4 $1,440 $5,760
K 11.0 APPLICATION OF DECALS J 1 1 $1,440 $1,440
L 12.0 APPLYING CLEAR COAT K 1 1 $1,440 $1,440
M 13.0 DISPLAY NOZZLE ASSEMBLY K 1 3 $1,440 $4,320
N 14.0 ROCKET PREFLIGHT L 1 2 $1,440 $2,880
O 15.0 PREPARE FOR TEST LAUNCH N 1 1 $1,440 $1,440
24 weeks Level of Effort
Blended Rate= $1,440 11 weeks duration

Performance Sheet

BCWS (PV) TASK Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 BAC Totals
A 1.0 ASSEMBLE ENGINE MOUNT $0
B 2.0 FIN PREPARATION $0
C 3.0 MARK FIN AND LAUNCH LUG LINES $0
D 4.0 INSERTING ENGINE MOUNT $0
E 5.0 ATTACH FINS $0
F 6.0 ATTACH SHOCK CORD $0
G 7.0 ASSEMBLE NOSE CONE $0
H 8.0 ATTACH PARACHUTE/SHOCK CORD $0
I 9.0 ATTACH LAUNCH LUG $0
J 10.0 PAINTING THE ROCKET $0
K 11.0 APPLICATION OF DECALS $0
L 12.0 APPLYING CLEAR COAT $0
M 13.0 DISPLAY NOZZLE ASSEMBLY $0
N 14.0 ROCKET PREFLIGHT $0
O 15.0 PREPARE FOR TEST LAUNCH $0
Equipment $0
Material $0
$0
Weekly Total $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Cumulative Cost (PV) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
ID ACWP (AC) TASK Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 AC Totals
A 1.0 ASSEMBLE ENGINE MOUNT $0
B 2.0 FIN PREPARATION $0
C 3.0 MARK FIN AND LAUNCH LUG LINES $0
D 4.0 INSERTING ENGINE MOUNT $0
E 5.0 ATTACH FINS $0
F 6.0 ATTACH SHOCK CORD $0
G 7.0 ASSEMBLE NOSE CONE $0
H 8.0 ATTACH PARACHUTE/SHOCK CORD $0
I 9.0 ATTACH LAUNCH LUG $0
J 10.0 PAINTING THE ROCKET $0
K 11.0 APPLICATION OF DECALS $0
L 12.0 APPLYING CLEAR COAT $0
M 13.0 DISPLAY NOZZLE ASSEMBLY $0
N 14.0 ROCKET PREFLIGHT $0
O 15.0 PREPARE FOR TEST LAUNCH $0
Equipment $0
Material $0
$0
Weekly Total $0 $0 $0
Cumulative Cost (AC) $0 $0 $0
ID BCWP (EV) TASK Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 EV Totals
A 1.0 ASSEMBLE ENGINE MOUNT $0
B 2.0 FIN PREPARATION $0
C 3.0 MARK FIN AND LAUNCH LUG LINES $0
D 4.0 INSERTING ENGINE MOUNT $0
E 5.0 ATTACH FINS $0
F 6.0 ATTACH SHOCK CORD $0
G 7.0 ASSEMBLE NOSE CONE $0
H 8.0 ATTACH PARACHUTE/SHOCK CORD $0
I 9.0 ATTACH LAUNCH LUG $0
J 10.0 PAINTING THE ROCKET $0
K 11.0 APPLICATION OF DECALS $0
L 12.0 APPLYING CLEAR COAT $0
M 13.0 DISPLAY NOZZLE ASSEMBLY $0
N 14.0 ROCKET PREFLIGHT $0
O 15.0 PREPARE FOR TEST LAUNCH $0
Equipment $0
Material $0
$0
Weekly Total $0 $0 $0
Cumulative Cost (EV) $0 $0 $0
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16
Cumulative Cost (PV) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Cumulative Cost (AC) $0 $0 $0
Cumulative Cost (EV) $0 $0 $0
BAC= 0
BCWS (PV)= 0
ACWP (AC)= 0
BCWP (EV)= 0
SV= BCWP-BCWS CV= BCWP-ACWP
SV= CV=
SV= $0 CV= $0
Project is $xxK behind schedule Project is $xxK over budget
SPI= BCWP/BCWS CPI= BCWP/ACWP
SPI= CPI=
SPI= 0 CPI= 0
For every dollar spent on scheduled effort we realize $0.xx worth of progress. For every dollar spent, we realize $0.xx of planned result.
EAC = BAC/CPI PM Eval= +10% to -5% EAC
EAC = PM Eval= EAC/BAC
EAC = $0.00 PM Eval= 0% EAC
The PM's EAC isxx% over/under BAC and is/is not in trouble.
May 22-28
May 29-Jun 4
Jun 5-Jun 11
Jun 12-Jun18
Jun 19-Jun 25
Jun 26-Jul 2
Jul 3-Jul9
Jul 10-Jul 16
Jul 17-Jul23
Jul 24-Jul30
Jul 31-Aug 6
Aug 7-Aug 13

Performance Sheet

Cumulative Cost (PV)
Cumulative Cost (AC)
Cumulative Cost (EV)
BAC=$xxx,xxxx EAC=$xxx,xxx
Planned Value (PV) Section
Earned Value (EV) Section
Actual Cost (AC) Section
Cumulative or S-Curve Graph
Performance Measures Section