Quality management Plan for Construction.

profilesus3848
GarageApartmentGanttChartTeam.xlsx

GanttChart

Garage apartment Project Schedule
Innovation Rennovation
Project Start Date 44683.0 Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead 2 May 2022 9 May 2022 16 May 2022 23 May 2022 30 May 2022 6 Jun 2022 13 Jun 2022 20 Jun 2022
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
WBS
Vertex42: Work Breakdown Structure Level 1: 1, 2, 3, ... Level 2: 1.1, 1.2, 1.3, ... Level 3: 1.1.1, 1.1.2, 1.1.3, … - The WBS uses a formula to control the numbering, but the formulas are different for different levels. Copy and Paste the cells in the WBS column from the examples at the bottom of the worksheet.
TASK
Vertex42: Task Description Enter the name of each task and sub-task. Use indents for sub-tasks.
LEAD
Vertex42: Task Lead Enter the name of the Task Lead in this column.
PREDECESSOR
Vertex42: Predecessor Tasks: You can use this column to enter the WBS of a predecessor for reference. The PRO version uses formulas to automatically calculate the Start Date based on the Predecessor.
START
Vertex42: Task Start Date You can manually enter the Start Date for each task or use a formula to create a dependency on a Predecessor. For example, you could enter =enddate+1 to set the Start date to the next calendar day, or =WORKDAY(enddate,1) to set the Start date to the next work day (excluding weekends), where enddate is the cell reference for the End date of the Predecessor task.
END
Vertex42.com Templates: End Date: The End Date is calculated based on the Start Date and the Calendar Days columns.
DAYS
Vertex42: Duration (Calendar Days) The duration is the number of calendar days for the given task. The duration is calculated as the End Date minus the Start Date plus 1 day, so that a task starting and ending on the same day has a duration of 1 day. Note: The conditional formatting used to create the gantt chart references this column.
% DONE
Vertex42: Percent Complete Update the status of this task by entering the percent complete (between 0% and 100%).
WORK DAYS
Vertex42: Work Days Counts the number of work days, excluding the weekends (Saturday and Sunday). In the PRO version, you can customize the work week and list specific non-working days like holidays. In the PRO version, the default input is the Work Days instead of the Calendar Days.
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Project Planning
1.1 Planning Project manager Mon 5/02/22 Fri 5/06/22 5 100% 5
1.2 Understanding the client requirement. Sat 5/07/22 Wed 5/11/22 5 100% 3
1.3 Estimate budget. Planner Thu 5/12/22 Sun 5/15/22 4 100% 2
1.4 Plans and drawing. Architect Mon 5/16/22 Thu 5/19/22 4 100% 4
1.5 Create plot with measurement. Architect Fri 5/20/22 Tue 5/24/22 5 100% 3
1.6 Create project schedule. Project Manger Wed 5/25/22 Tue 5/31/22 7 100% 5
2 Structure
2.1 Grading and drain. Wed 6/01/22 Sat 6/04/22 4 100% 3
2.2 Procuring concrete, Iron, and gravel. Tue 6/05/18 Tue 6/05/18 1 100% 1
2.3 Foundation. Mon 6/06/22 Wed 6/08/22 3 100% 3
2.4 Footings. Thu 6/09/22 Tue 6/14/22 6 80% 4
3 Framing
3.1 Framing material estimation Wed 6/15/22 Wed 6/15/22 1 0% 1
3.2 Order framing materials and set delivery date. Thu 6/16/22 Thu 6/16/22 1 0% 1
3.3 Frame, beams, ties, and trusses. Fri 6/17/22 Sun 6/19/22 3 0% 1
3.4 Frame exterior walls. Mon 6/20/22 Sat 6/25/22 6 0% 5
3.5 Frame windows. Sun 6/26/22 Tue 6/28/22 3 0% 2
4 Plumbing
4.1 Sewer connection Wed 6/29/22 Thu 6/30/22 2 0% 2
4.2 Bath connections. Fri 7/01/22 Mon 7/04/22 4 0% 2
4.3 Water heater connections. Tue 7/05/22 Wed 7/06/22 2 0% 2
5 Electrical
5.1 Main switch board. Thu 7/07/22 Sat 7/09/22 3 0% 2
5.2 Outlets and external outlets. Sun 7/10/22 Wed 7/13/22 4 0% 3
5.3 Heating and air connection. Thu 7/14/22 Tue 7/19/22 6 0% 4
6 Finishes and Carpentry
6.1 Drywall and paint. Wed 7/20/22 Sat 7/30/22 11 0% 8
6.2 Flooring. Sun 7/31/22 Wed 8/03/22 4 0% 3
6.3 Landscape and patio. Thu 8/04/22 Mon 8/15/22 12 0% 8
6.4 Light fixtures and exterior seating Tue 8/16/22 Fri 8/19/22 4 0% 4
6.5 Cabinetry. Sat 8/20/22 Fri 8/26/22 7 0% 5