Project Name Online Inventory Development Project
Project Duration 86
Project Start Date 4-Jan-21
Project End Date 31-Mar-21
Task Start Date End Date 4-Jan-21 5-Jan-21 6-Jan-21 7-Jan-21 8-Jan-21 9-Jan-21 10-Jan-21 11-Jan-21 12-Jan-21 13-Jan-21 14-Jan-21 15-Jan-21 16-Jan-21 17-Jan-21 18-Jan-21 19-Jan-21 20-Jan-21 21-Jan-21 22-Jan-21 23-Jan-21 24-Jan-21 25-Jan-21 26-Jan-21 27-Jan-21 28-Jan-21 29-Jan-21 30-Jan-21 31-Jan-21 1-Feb-21 2-Feb-21 3-Feb-21 4-Feb-21 5-Feb-21 6-Feb-21 7-Feb-21 8-Feb-21 9-Feb-21 10-Feb-21 11-Feb-21 12-Feb-21 13-Feb-21 14-Feb-21 15-Feb-21 16-Feb-21 17-Feb-21 18-Feb-21 19-Feb-21 20-Feb-21 21-Feb-21 22-Feb-21 23-Feb-21 24-Feb-21 25-Feb-21 26-Feb-21 27-Feb-21 28-Feb-21 1-Mar-21 2-Mar-21 3-Mar-21 4-Mar-21 5-Mar-21 6-Mar-21 7-Mar-21 8-Mar-21 9-Mar-21 10-Mar-21 11-Mar-21 12-Mar-21 13-Mar-21 14-Mar-21 15-Mar-21 16-Mar-21 17-Mar-21 18-Mar-21 19-Mar-21 20-Mar-21 21-Mar-21 22-Mar-21 23-Mar-21 24-Mar-21 25-Mar-21 26-Mar-21 27-Mar-21 28-Mar-21 29-Mar-21 30-Mar-21 31-Mar-21
Planning
system Request 4-Jan-21 15-Jan-21 X X X X X X X X X X X X
Feasibility analaysis 5-Jan-21 13-Jan-21 X X X X X X X X X
Analysis Phase
Gantt Chart 14-Jan-21 20-Jan-21 X X X X X X X
Requiremensts Definitions 15-Jan-21 28-Jan-21 X X X X X X X X X X X X X X
Data Flow Diagram 20-Jan-21 29-Jan-21 X X X X X X X X X X
Use Cases 20-Jan-21 29-Jan-21 X X X X X X X X X X
Design Phase
Acquisition Strategy 1-Feb-21 9-Feb-21 X X X X X X X X X
Entity-relationship Design 5-Feb-21 12-Feb-21 X X X X X X X X
Protoypes/mockup 15-Feb-21 19-Feb-21 X X X X X
Inputs/Output 17-Feb-21 22-Feb-21 X X X X X X
Architecture Design 16-Feb-21 26-Feb-21 X X X X X X X X X X X
Hardware and Software Specification 22-Feb-21 4-Mar-21 X X X X X X X X X X X
Implementation Phase
Testing 4-Mar-21 23-Mar-21 X X X X X X X X X X X X X X X X X X X X
Documentation 22-Mar-21 26-Mar-21 X X X X X
Migration and conversion 24-Mar-21 31-Mar-21 X X X X X X X X