project recommendations
ID Task Mode
Task Name Duration Start Finish Predecessors
1 Project 90 days Thu 9/1/22 Wed 1/4/23 2 IT Project Manager Input 7 days? Thu 9/1/22 Fri 9/9/22 3 Project Flow Diagram 17 days Fri 9/9/22 Sat 10/1/22 4 Software designer Input 7 days Thu 9/1/22 Fri 9/9/22 5 Project Flow Diagram 17 days Fri 9/9/22 Sat 10/1/22 6 Networking specialist Input 7 days Thu 9/1/22 Fri 9/9/22 7 Project Flow Diagram 17 days Fri 9/9/22 Sat 10/1/22 8 Data Analyst Input 7 days Thu 9/1/22 Fri 9/9/22 9 Project Flow Diagram 17 days Fri 9/9/22 Sat 10/1/22 10 Data Manager Input 7 days Thu 9/1/22 Fri 9/9/22 11 Project Flow Diagram 17 days Fri 9/9/22 Sat 10/1/22 12 Cybersecurity Input 7 days? Thu 9/1/22 Fri 9/9/22 13 Project Flow Diagram 14 Initiate Process 7 days Thu 9/1/22 Fri 9/9/22 15 Planning Process 17 days Sat 9/10/22 Sat 10/1/22 16 Compile Project Flow Diagram 2 days Sun 10/2/22 Mon 10/3/22 17 Executing Process 43 days Mon 10/3/22Wed 11/30/22 18 Monitoring and Controlling
Process 11 days Thu 12/1/22 Thu
12/15/22 19 Closing Process 14 days Fri 12/16/22 Wed 1/4/23
M T W T F S S M T W T F Aug 21, '22 Aug 28, '22
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Sep 4, '22 Sep 11, '22 Sep 18, '22 Sep 25, '22 Oct 2, '22 Oct 9, '22
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Oct 16, '22 Oct 23, '22 Oct 30, '22 Nov 6, '22 Nov 13, '22 Nov 20, '22
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Nov 27, '22 Dec 4, '22 Dec 11, '22 Dec 18, '22 Dec 25, '22 Jan 1, '23
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4