| WBS ID |
Task Name |
Work Estimate (days) |
Lead |
Start Date |
End Date |
% Complete |
| 1 |
Overall Project |
60 |
Chris Johnson (Project Manager) |
1st May 2023 |
29th June 2023 |
100% |
| 1.1 |
Project Management |
15 |
Chris Johnson (Project Manager) |
1st May 2023 |
21st May 2023 |
80% |
| 1.1.1 |
Manage Project |
15 |
Chris Johnson (Project Manager) |
22nd May 2023 |
11th June 2023 |
50% |
| 1.2 |
System Requirements |
10 |
- |
12th June 2023 |
21st June 2023 |
100% |
| 1.2.1 |
Gather Business Requirements |
5 |
- |
12th June 2023 |
16th June 2023 |
100% |
| 1.2.2 |
Design Business Process Flows |
2 |
Ryan Neff (Functional Lead) |
17th June 2023 |
18th June 2023 |
60% |
| 1.2.3 |
Finalize Technical Requirements |
3 |
Ryan Neff (Functional Lead) |
19th June 2023 |
21st June 2023 |
40% |
| 1.2.4 |
Create Operational Requirements |
2 |
Rick Burke (Infrastructure Lead) |
19th June 2023 |
20th June 2023 |
75% |
| 1.2.5 |
Identify Technical Infrastructure Needs |
3 |
Ryan Neff (Functional Lead), Stacy Lyle (Functional Analyst), Rick Burke (Infrastructure Lead) |
19th June 2023 |
21st June 2023 |
30% |
| 1.3 |
Software Requirements |
20 |
Rick Burke (Infrastructure Lead) |
22nd June 2023 |
29th June 2023 |
10% |
| 1.3.1 |
Create Functional Requirements |
15 |
- |
22nd June 2023 |
10th July 2023 |
10% |
| 1.3.1.1 |
Capture Customer Profile |
2 |
- |
22nd June 2023 |
23rd June 2023 |
60% |
| 1.3.1.2 |
View and Search Product Catalog |
3 |
- |
24th June 2023 |
26th June 2023 |
72% |
| 1.3.1.3 |
Updating and Calculating Shopping Cart |
2 |
Ryan Neff (Functional Lead) |
27th June 2023 |
28th June 2023 |
10% |
| 1.3.1.4 |
Taking Payments |
4 |
Ryan Neff (Functional Lead) |
27th June 2023 |
30th June 2023 |
23% |
| 1.3.1.5 |
Submit Order |
3 |
Ryan Neff (Functional Lead) |
1st July 2023 |
3rd July 2023 |
0% |
| 1.3.1.6 |
Check Order History & Order Status |
2 |
Stacy Lyle (Functional Analyst) |
4th July 2023 |
5th July 2023 |
0% |
| 1.3.2 |
Create Data Requirements |
2 |
Ryan Neff (Functional Lead) |
6th July 2023 |
7th July 2023 |
0% |
| 1.3.3 |
Create ERP Interface Requirements |
7 |
Ryan Neff (Functional Lead) |
8th July 2023 |
11th July 2023 |
0% |
| 1.3.4 |
Create User Interface Requirements |
4 |
- |
8th July 2023 |
9th July 2023 |
90% |