Technology and information management
R
TIM 125 HW#3
01/31/2019
TIM 125/225: MOT II: Homework #3
Day & Date Completed Assignment Friday (01/25/19) • Start on HW3, Problem 1
Saturday (01/26/19) • Finish up HW3, Problem 1
• Start on HW3, Problem 2
• Finish up HW3, Problem 2
Sunday (01/27/19) • Start on HW3, Problem 3
Tuesday (01/29/19) • Finish up HW3, Problem 3
• Start on HW3, Problem 4
Thursday (01/31/19) • Finish up HW3, Problem 4
• Check work to make sure everything was done correctly and followed through.
Problem 1: Seven-Eleven Japan
1. Define the Real Problem a. Answer the following questions as a group about the 7-11 case study:
• What has Seven-Eleven done in its choice of facility location, inventory
management, transportation, and information infrastructure to develop
capabilities that support its supply chain strategy in Japan?
• Seven-Eleven is attempting to duplicate the supply chain structure that
has succeeded in Japan and the United States with the introduction of CDCs.
What are the pros and cons of this approach? Keep in mind that stores are also
replenished by wholesalers and DSD by manufacturers.
2. Plan a. What information is available for solving the problem?
• Lecture Notes
• Textbook
• Internet
b. What assumptions need to be made to make the solution process manageable?
• I must assume that the documents provided are the correct documents
assigned by the professor.
c. What analysis needs to be performed to resolve the issues defined in Step 1?
• I need to execute my analysis in the form of a text-based report which answer
the questions 3 and 6 from the SCM textbook.
• Problem 1: What has Seven-Eleven done in its choice of facility location,
inventory management, transportation, and information infrastructure to
develop capabilities that support its supply chain strategy in Japan?
o Read the case study for 7-11 Japan in the textbook
o Define the different supply chain strategies listed above
• Problem 2: Seven-Eleven is attempting to duplicate the supply chain structure
that has succeeded in Japan and the United States with the introduction of
CDCs. What are the pros and cons of this approach? Keep in mind that stores
are also replenished by wholesalers and DSD by manufacturers.
o Explain the pros and cons of the CDC approach
3. Execute the Plan PART 1
a. Facility Location
• Convivence stores in Japan have historically been very successful. Even
during hard times, the convenience store was still growing. 7-11 sought
to enter the Japanese market for this very reason. Stores of this type are
so popular that the market has become oversaturated causing many
stores to close and leave. The top 10 stores account for 90% of the sales
and 7-11 is in that top 10.
• Entry into any new market was built around a cluster of 50 to 60 stores
that were to be supported by a distribution center. This clustering
strategy allowed 7-11 to have a high-density presence in an area and
allowed them to operate an efficient distribution system. For example,
the Aichi prefecture began opening stores in 2002, and by 2004 had 108
stores. The clusters of stores in the Aichi prefecture were all fed by the
same distribution center. By 2014, 7-11 owned stores in 42 or 27
prefectures in Japan, approximately 16,000 stores across Japan.
b. Inventory Management
• Through the help of the Graphic order terminal, the POS (point-of-sales)
system store, and the scanner terminal, helped managers have an much
easier time with their inventory management. Managers are able to view
a detailed analysis of the POS data on specific items and then follow up
with placing an order through the graphic order terminal. The
information of the order from the graphic terminal was then relayed to
the store computer of both the appropriate vendor and the seven-eleven
distribution center. The scanner terminal was used to receive products
coming in from a distribution center. Once an order was received the
scanner allowed the managers to easily enter their new supplies into the
system.
c. Transportation
• For transportation, there was two levels to it, one from suppliers to
distribution center and the other from distribution center to the 7-11
stores. Suppliers receive order from all stores, and they sent the order by
truck to distribution center. Each store order was separated so the DC
could easily assign it to the appropriate store truck using the order
information it already had. At the DCs, similar products are directed to a
single temperature-controlled truck and there are 4 different type. he
numbers of stores per truck depended on the sales volume. All deliveries
were made during off-peak hours and were received using the scanner
terminals. There are about 158 DCs in Japan that ensures rapid, reliable
delivery and none these carry any inventory; they just transfer inventory
from supplier trucks to 7-11 distribution trucks.
d. Information Infrastructure
• The managers of each seven-eleven store computer send data through
the POS (point-of sales) system. With the POS system every time a
customer purchased a product data was stored and sent to the
headquarters. Data of register sales, and other data was recorded
through the POS system. The data was then analyzed and updated and
sent back to each seven-eleven store. With this information the
managers of each store were able to better match their store’s supply
with demand. The store computer also gave information on store
inventory, sales, POS data, store equipment and placed orders.
Throughout the year about 70% of the items sold at a seven eleven store
changed according to the POS system.
Part 2 Explain the pros and cons of the CDC approach
CDC Combined Distribution Centers
DSD Direct Store Delivery
Pros • Lower operation costs o Rent or Utility expenditures
for different warehouses reduced.
• Efficient in Operating o Reduces the delivery time
spent at each store. o Reduces the number of
vehicles required for daily delivery service to each store.
• Known to work strategy o US stores currently use this
strategy o Able to put product on the
shelves • 7-11 can depend on other companies to
deliver their goods to the store o 7-11 does not need a
distribution network for products they do not make
• Fresh Products o No inventory is carried at the
DCs. o DCs is just used to transfer
inventory from supplier trucks to Seven-Eleven distribution trucks.
o This will cut down on costs and responsibilities of having to deliver and move goods
• Saved retailer hours o Item data is managed by
vendors and then communicated to retailers which means that retailers do not have to take as long to manage their item data.
Cons • Rush delivery is of high cost o If a mistake occurs in the
miscalculation of supplies additional fees must be paid for rush deliveries.
• Not good if customers are widespread.
o If customers are demanding different items in nearby areas CDCs would be the only distribution center and would only be able to supply what is being carried.
• 7-11 must depend on others to bring them their products
o Since they are not in charge of the delivery of their products they have to wait for other companies to do this
o This means that they cannot dictate when their products arrive
• Keeping track of products o With a DSD products are being
transported from multiple areas meaning that products must be tracked from multiple locations. With CDC all the products are being kept in one place.
4. Check your work
a. We went over our work as a team and talked about if it made sense or not. All of the work that was done was based off of the textbook. We looked over the question and
made sure that we answered all parts of the questions. To verify the popularity of
convenience stores in Japan we as a team took a trip to Tokyo and sampled a number of
the convenience stores available to the Japanese public. 5. Learn and Generalize
a. The case study for 7-11 Japan addressed some of the supply chain strategies that made
their convenience stores expand rapidly around the world. The seven-eleven
distribution system linked the entire supply chain together; its supply chain also has
many CDCs located throughout North America. Seven-Eleven understands the tricks in
supplying and marketing their product. We learned the information infrastructure of
their sales system and inventory management which attributed a significant part of
seven-eleven’s success. Their systems were updated each morning via the network. The
pros of having the CDCs outweighs the cons because it offers fresh product at all of their
convenience stores. Overall, the supply chain strategy of 7-11 in Japan is very responsive
and provides customers with what they need.
Problem 2: Demand Forecasting
1. Define the Real Problem a. 7.1. What role does forecasting play in the supply chain of a build-to-order server
manufacturer such as Dell?
b. 7.2. How could Apple use collaborative forecasting with its suppliers to improve its
supply chain?
c. 7.9. What information do the MSE, MAD, and MAPE provide to a manager? How can the
manager use this information?
d. 7.10. What information do the bias and TS provide to a manager? How can the manager
use this information?
2. Plan a. What information is available for solving the problem?
• Lecture Notes
• Textbook
• Internet
b. What assumptions need to be made to make the solution process manageable?
• Problem Solver
o Student
• Audience:
o CEO or CIO of a company
c. What analysis needs to be performed to resolve the issues defined in Step 1?
• 7.1. What role does forecasting play in the supply chain of a build-to-order
server manufacturer such as Dell?
• 7.2. How could Apple use collaborative forecasting with its suppliers to improve
its supply chain?
• 7.9. What information do the MSE, MAD, and MAPE provide to a manager? How
can the manager use this information?
• 7.10. What information do the bias and TS provide to a manager? How can the
manager use this information?
3. Execute the Plan a. 7.1. What role does forecasting play in the supply chain of a build-to-order
server manufacturer such as Dell?
• Dell obtains PC components in anticipation of customer orders and therefore
they rely on forecasting. Dell uses forecasting to communicate with their
suppliers and match production requirements. This forecast is used to predict
future demand, which determines the quantity of each component needed to
assemble a PC and the plant capacity required to perform the assembly.
b. 7.2. How could Apple use collaborative forecasting with its suppliers to
improve its supply chain?
• Collaborative forecasting requires all supply chain partners to share information
regarding parameters that might affect demand, such as the timing and
magnitude of promotions. Dell could share with their component’s suppliers all
of the promotions, e.g., holiday, back-to-school, etc., they have planned. These
suppliers could, in turn, notify their suppliers of discrete components that a
spike in demand is anticipated. These demand forecasts for end items
determine the demand for components and coupled with knowledge of
fabrication times, allows all members of the supply chain to provide the right
quantity at the right time to their customers.
c. 7.9. What information do the MSE, MAD, and MAPE provide to a manager?
How can the manager use this information?
• Mean Squared Error(MSE) - squared deviation of forecast from demand. It
estimates variance in forecasting error.
• Mean Absolute Deviation(MAD)- Absolute deviation of forecast from demand. It
estimates the standard deviation of the forecast error and gives us the absolute
error allowing us to estimate the expected value. MAD is used to provide
balanced estimation of the mean value.
• Mean Absolute Percentage Error (MAPE)- Absolute of forecast from demand as
percentage of the demand. It gives us the overall percentage of the absolute
error in terms of overall quantity that is forecasted.
• Managers can use this information to forecast accuracy and minimize error.
d. 7.10. What information do the bias and TS provide to a manager? How can the
manager use this information?
• By combining the errors that are detected throughout the entire period of using
the model the bias tells us about any kind of regular tendency for over and
undervaluing data. The fluctuation of the bias should be around 0. Tracking
signal is ratio of Bias to mean absolute deviation that accounts an unbiased
model that includes normal assumptions for predicting demand. Tracking signal
is expected to increase to get high probability. It fluctuates around 0 with an
interval of 6.0. Outside this interval is an alert signal for enlargement of the
regular bias.
4. Check your work a. Is the work correct in every detail?
• Using the book as a source of information, I can safely assume that work I have
written is correct.
b. Are my assumptions reasonable?
• Yes, they are because I used the book as source of information. So, I can assume
that the information I have provided is accurate and correct.
c. In terms of the things I know, do the results make sense?
• Yes, in terms of the things I understood from my research, the results do make a
lot of sense.
5. Learn and Generalize a. From reading the book and working on those discussion problems, I learned that it is
crucial that a forecast is not biased therefore MSE, MAD, MAPE and TS allow us to
minimize error and prevent bias in the forecast. I believe these discussion questions
helped me further understand the usefulness of Forecasting and its key components
MSE, MAD, etc. and their functions in giving the company a competitive advantage.
Problem 3: Tahoe Salt (Chapter 7 continued)
1. Define the Real Problem a. Forecast demand using the:
• Static method (make sure to include the appropriate error analysis)
• Moving Average and Simple Exponential Smoothing Forecasting methods.
2. Plan a. What information is available for solving the problem?
• Lecture Notes
• Textbook
• Internet
b. What assumptions need to be made to make the solution process manageable?
• Problem Solver
o Market Analyst
• Audience:
o CEO or CIO of a company
c. What analysis needs to be performed to resolve the issues defined in Step 1?
• Use previous homework’s static method solution and then include error
analysis into it
• Follow textbook to match solutions
3. Execute the Plan
Copied Static Method Forecasting over from HW 2 but now including error analysis:
t = Period
P = Periods in a cycle
St = estimate of seasonal factor for Period t Dt = actual demand observed in Period t
D’t: De-Seasonalized Data
Ft = forecast of demand for Period t
a. STEP 1 De-seasonalize the Data • Since there are an even number of period, I will have to find the average of two
averages corresponding with periods 1-4 and 2-5.
-
10,000
20,000
30,000
40,000
50,000
1 2 3 4 5 6 7 8 9 10 11 12
D e
m a
n d
Period
Quarterly Demand at Tahoe Salt
b. STEP 2 Regress the Data
• We obtain L = 18,439 and T = 524
• Regressed Equation: Regressed Demand = 18,439 + 524t
• Plugging =18,439+A2*524 into Excel and copying down the “Regressed Data”
coulomb to apply the regression equation to all actual demand points resulted
in the following:
c. STEP 3 Determine the Seasonal Factors
• Formula:
I then apply this formula to Excel by dividing columns D/F to derive to the seasonal factor.
RESULTS:
d. STEP 4 Calculate the Average Seasonal Factors
Savg1 = (S1+S5+S9)/3 = 0.47
Savg2 = (S2+S6+S10)/3 = 0.68
Savg3 = (S3+S7+S11)/3 =1.17
Savg4 = (S4+S8+S12)/3 = 1.66
e. STEP 5 Forecasting
• Finally, I forecast by multiplying the regressed factor and the seasonal factor
f. STEP 6 Error Analysis
• Error = Forecast – Demand
• Absolute deviation
• Mean squared error (MSE)
• Mean absolute deviation (MAD)
• Mean absolute percentage error (MAPE)
• Tracking signal (TS)
g. Adaptive Forecasting Moving Average:
• Using these formulas in excel we are able to calculate the Level, Forecast,
Error, Absolute Error, MSE, MAD, %Error, MAPE, and TS.
h. Adaptive Forecasting Simple Exponential Smoothing:
• The forecasting team next uses a simple exponential smoothing
approach, with a = 0.1, to forecast demand. This method is also tested on
the 12 quarters of historical data. Using Equation 7.11, the team
estimates the initial level for Period 0 to be the average demand for
Periods 1 through 12 (see worksheet Figure 7-8). The initial level is the
average of the demand entries in cells B3 to B14 in Figure 7-8 and results
in L0 = 22,083
• Using the given formulas in excel, the figure below was created:
4. Check your work a. Error Analysis
b. Are my assumptions reasonable?
• Yes, they are because using the book and using my lecture notes for the
problem, I was able to get all the information that I needed it. So, I can assume
that the information I have provided is accurate and correct.
c. In terms of the things I know, do the results make sense?
• Yes, in terms of the things I understood from the book, the results do make a lot
of sense.
5. Learn and Generalize a. The different ways to forecast demand allow us to see which one has larger
error. Error analysis allows us to see whether the quality of the forecast is good. I
believe with more practice I will be able to do this with ease.
Problem 4: Demand Forecasting for ABC Corporation
1. Define the Real Problem a. Consider monthly demand for the ABC Corporation, as shown in Table 7-3. Forecast the
monthly demand for Year 6 using the static method for forecasting. Evaluate the bias,
TS, MAD, MAPE, and MSE. Evaluate the quality of the forecast.
2. Plan a. What information is available for solving the problem?
• Lecture Notes
• Textbook
b. What assumptions need to be made to make the solution process manageable?
• Problem Solver
o Market Analyst
• Audience:
o CEO or CIO of a company
c. What analysis needs to be performed to resolve the issues defined in Step 1?
• Forecast the demand
• Evaluate the bias, TS, MAD, MAPE, and MSE.
• Evaluate the quality of the forecast.
3. Execute the Plan
Comment: The Break in the graph represent where the year ends.
Since we are doing an analysis on a yearly basis, periodicity (p) is 12. We must find the time at
which de-seasonalized demand starts.
Year Months Period Demand Dt De-Sea Demand
January 1 2,000
February 2 3,000
March 3 3,000
April 4 3,000
May 5 4,000
June 6 6,000
July 7 7,000 6,542
August 8 6,000 6,625
September 9 10,000 6,667
October 10 12,000 6,750
November 11 14,000 6,875
December 12 8,000 7,000
January 13 3,000 6,917
February 14 4,000 6,833
March 15 3,000 7,000
April 16 5,000 7,083
May 17 5,000 7,167
June 18 8,000 7,333
July 19 3,000 7,375
August 20 8,000 7,375
September 21 12,000 7,500
October 22 12,000 7,500
November 23 16,000 7,375
December 24 10,000 7,250
January 25 2,000 7,333
February 26 5,000 7,583
March 27 5,000 7,792
April 28 3,000 8,042
May 29 4,000 8,250
June 30 6,000 8,250
July 31 7,000 8,292
August 32 10,000 8,375
September 33 15,000 8,292
October 34 15,000 8,208
November 35 18,000 8,208
December 36 8,000 8,292
January 37 5,000 8,458
February 38 4,000 8,750
March 39 4,000 8,958
April 40 2,000 9,042
May 41 5,000 9,167
June 42 7,000 9,417
July 43 10,000 9,583
August 44 14,000 9,500
September 45 16,000 9,375
October 46 16,000 9,333
November 47 20,000 9,417
December 48 12,000 9,458
January 49 5,000 9,333
February 50 2,000 9,083
March 51 3,000 9,083
April 52 2,000 9,417
May 53 7,000 9,667
June 54 6,000 9,583
July 55 8,000
August 56 10,000
September 57 20,000
October 58 20,000
November 59 22,000
December 60 8,000 5
1
2
3
4
We obtain L = 5997.26 and T = 70.25
Regressed Equation: Regressed Demand = 5997.26 + 70.25t
Plugging = 5997.26 +A2*70.25 into Excel and copying down the “Regressed Data” coulomb to
apply the regression equation to all actual demand points resulted in the following:
Year Months Period Demand Dt De-Sea Demand
January 1 2,000
February 2 3,000
March 3 3,000
April 4 3,000
May 5 4,000
June 6 6,000
July 7 7,000 6,542
August 8 6,000 6,625
September 9 10,000 6,667
October 10 12,000 6,750
November 11 14,000 6,875
December 12 8,000 7,000
January 13 3,000 6,917
February 14 4,000 6,833
March 15 3,000 7,000
April 16 5,000 7,083
May 17 5,000 7,167
June 18 8,000 7,333
July 19 3,000 7,375
August 20 8,000 7,375
September 21 12,000 7,500
October 22 12,000 7,500
November 23 16,000 7,375
December 24 10,000 7,250
January 25 2,000 7,333
February 26 5,000 7,583
March 27 5,000 7,792
April 28 3,000 8,042
May 29 4,000 8,250
June 30 6,000 8,250
July 31 7,000 8,292
August 32 10,000 8,375
September 33 15,000 8,292
October 34 15,000 8,208
November 35 18,000 8,208
December 36 8,000 8,292
January 37 5,000 8,458
February 38 4,000 8,750
March 39 4,000 8,958
April 40 2,000 9,042
May 41 5,000 9,167
June 42 7,000 9,417
July 43 10,000 9,583
August 44 14,000 9,500
September 45 16,000 9,375
October 46 16,000 9,333
November 47 20,000 9,417
December 48 12,000 9,458
January 49 5,000 9,333
February 50 2,000 9,083
March 51 3,000 9,083
April 52 2,000 9,417
May 53 7,000 9,667
June 54 6,000 9,583
July 55 8,000
August 56 10,000
September 57 20,000
October 58 20,000
November 59 22,000
December 60 8,000 5
1
2
3
4
Year Months Period Demand Dt De-Sea Demand Regressed De-Sea Demand
January 1 2,000 6,068
February 2 3,000 6,138
March 3 3,000 6,208
April 4 3,000 6,278
May 5 4,000 6,349
June 6 6,000 6,419
July 7 7,000 6,542 6,489
August 8 6,000 6,625 6,559
September 9 10,000 6,667 6,630
October 10 12,000 6,750 6,700
November 11 14,000 6,875 6,770
December 12 8,000 7,000 6,840
January 13 3,000 6,917 6,911
February 14 4,000 6,833 6,981
March 15 3,000 7,000 7,051
April 16 5,000 7,083 7,121
May 17 5,000 7,167 7,192
June 18 8,000 7,333 7,262
July 19 3,000 7,375 7,332
August 20 8,000 7,375 7,402
September 21 12,000 7,500 7,473
October 22 12,000 7,500 7,543
November 23 16,000 7,375 7,613
December 24 10,000 7,250 7,683
January 25 2,000 7,333 7,754
February 26 5,000 7,583 7,824
March 27 5,000 7,792 7,894
April 28 3,000 8,042 7,964
May 29 4,000 8,250 8,035
June 30 6,000 8,250 8,105
July 31 7,000 8,292 8,175
August 32 10,000 8,375 8,245
September 33 15,000 8,292 8,316
October 34 15,000 8,208 8,386
November 35 18,000 8,208 8,456
December 36 8,000 8,292 8,526
January 37 5,000 8,458 8,597
February 38 4,000 8,750 8,667
March 39 4,000 8,958 8,737
April 40 2,000 9,042 8,807
May 41 5,000 9,167 8,878
June 42 7,000 9,417 8,948
July 43 10,000 9,583 9,018
August 44 14,000 9,500 9,088
September 45 16,000 9,375 9,159
October 46 16,000 9,333 9,229
November 47 20,000 9,417 9,299
December 48 12,000 9,458 9,369
January 49 5,000 9,333 9,440
February 50 2,000 9,083 9,510
March 51 3,000 9,083 9,580
April 52 2,000 9,417 9,650
May 53 7,000 9,667 9,721
June 54 6,000 9,583 9,791
July 55 8,000 9,861
August 56 10,000 9,931
September 57 20,000 10,002
October 58 20,000 10,072
November 59 22,000 10,142
December 60 8,000 10,212 5
1
2
3
4
Year Months Period Demand Dt De-Sea Demand Regressed De-Sea Demand
January 1 2,000 6,068
February 2 3,000 6,138
March 3 3,000 6,208
April 4 3,000 6,278
May 5 4,000 6,349
June 6 6,000 6,419
July 7 7,000 6,542 6,489
August 8 6,000 6,625 6,559
September 9 10,000 6,667 6,630
October 10 12,000 6,750 6,700
November 11 14,000 6,875 6,770
December 12 8,000 7,000 6,840
January 13 3,000 6,917 6,911
February 14 4,000 6,833 6,981
March 15 3,000 7,000 7,051
April 16 5,000 7,083 7,121
May 17 5,000 7,167 7,192
June 18 8,000 7,333 7,262
July 19 3,000 7,375 7,332
August 20 8,000 7,375 7,402
September 21 12,000 7,500 7,473
October 22 12,000 7,500 7,543
November 23 16,000 7,375 7,613
December 24 10,000 7,250 7,683
January 25 2,000 7,333 7,754
February 26 5,000 7,583 7,824
March 27 5,000 7,792 7,894
April 28 3,000 8,042 7,964
May 29 4,000 8,250 8,035
June 30 6,000 8,250 8,105
July 31 7,000 8,292 8,175
August 32 10,000 8,375 8,245
September 33 15,000 8,292 8,316
October 34 15,000 8,208 8,386
November 35 18,000 8,208 8,456
December 36 8,000 8,292 8,526
January 37 5,000 8,458 8,597
February 38 4,000 8,750 8,667
March 39 4,000 8,958 8,737
April 40 2,000 9,042 8,807
May 41 5,000 9,167 8,878
June 42 7,000 9,417 8,948
July 43 10,000 9,583 9,018
August 44 14,000 9,500 9,088
September 45 16,000 9,375 9,159
October 46 16,000 9,333 9,229
November 47 20,000 9,417 9,299
December 48 12,000 9,458 9,369
January 49 5,000 9,333 9,440
February 50 2,000 9,083 9,510
March 51 3,000 9,083 9,580
April 52 2,000 9,417 9,650
May 53 7,000 9,667 9,721
June 54 6,000 9,583 9,791
July 55 8,000 9,861
August 56 10,000 9,931
September 57 20,000 10,002
October 58 20,000 10,072
November 59 22,000 10,142
December 60 8,000 10,212 5
1
2
3
4
Seasonal Factor is then calculated by dividing the Demand by the RDD.
Year Months Period Demand Dt De-Sea Demand Regressed De-Sea Demand Seasonal Factor Avg Seasonal Factor
January 1 2,000 6,068 0.33 0.43
February 2 3,000 6,138 0.49 0.47
March 3 3,000 6,208 0.48 0.46
April 4 3,000 6,278 0.48 0.40
May 5 4,000 6,349 0.63 0.62
June 6 6,000 6,419 0.93 0.83
July 7 7,000 6,542 6,489 1.08 0.85
August 8 6,000 6,625 6,559 0.91 1.15
September 9 10,000 6,667 6,630 1.51 1.73
October 10 12,000 6,750 6,700 1.79 1.78
November 11 14,000 6,875 6,770 2.07 2.12
December 12 8,000 7,000 6,840 1.17 1.09
January 13 3,000 6,917 6,911 0.43
February 14 4,000 6,833 6,981 0.57
March 15 3,000 7,000 7,051 0.43
April 16 5,000 7,083 7,121 0.70
May 17 5,000 7,167 7,192 0.70
June 18 8,000 7,333 7,262 1.10
July 19 3,000 7,375 7,332 0.41
August 20 8,000 7,375 7,402 1.08
September 21 12,000 7,500 7,473 1.61
October 22 12,000 7,500 7,543 1.59
November 23 16,000 7,375 7,613 2.10
December 24 10,000 7,250 7,683 1.30
January 25 2,000 7,333 7,754 0.26
February 26 5,000 7,583 7,824 0.64
March 27 5,000 7,792 7,894 0.63
April 28 3,000 8,042 7,964 0.38
May 29 4,000 8,250 8,035 0.50
June 30 6,000 8,250 8,105 0.74
July 31 7,000 8,292 8,175 0.86
August 32 10,000 8,375 8,245 1.21
September 33 15,000 8,292 8,316 1.80
October 34 15,000 8,208 8,386 1.79
November 35 18,000 8,208 8,456 2.13
December 36 8,000 8,292 8,526 0.94
January 37 5,000 8,458 8,597 0.58
February 38 4,000 8,750 8,667 0.46
March 39 4,000 8,958 8,737 0.46
April 40 2,000 9,042 8,807 0.23
May 41 5,000 9,167 8,878 0.56
June 42 7,000 9,417 8,948 0.78
July 43 10,000 9,583 9,018 1.11
August 44 14,000 9,500 9,088 1.54
September 45 16,000 9,375 9,159 1.75
October 46 16,000 9,333 9,229 1.73
November 47 20,000 9,417 9,299 2.15
December 48 12,000 9,458 9,369 1.28
January 49 5,000 9,333 9,440 0.53
February 50 2,000 9,083 9,510 0.21
March 51 3,000 9,083 9,580 0.31
April 52 2,000 9,417 9,650 0.21
May 53 7,000 9,667 9,721 0.72
June 54 6,000 9,583 9,791 0.61
July 55 8,000 9,861 0.81
August 56 10,000 9,931 1.01
September 57 20,000 10,002 2.00
October 58 20,000 10,072 1.99
November 59 22,000 10,142 2.17
December 60 8,000 10,212 0.785
1
2
3
4
We then calculate the average seasonal factor for 12 periods. We take the seasonal factor for
each of the 12 months and average them.
Year Months Period Demand Dt De-Sea Demand Regressed De-Sea Demand Seasonal Factor Avg Seasonal Factor
January 1 2,000 6,068 0.33 0.43
February 2 3,000 6,138 0.49 0.47
March 3 3,000 6,208 0.48 0.46
April 4 3,000 6,278 0.48 0.40
May 5 4,000 6,349 0.63 0.62
June 6 6,000 6,419 0.93 0.83
July 7 7,000 6,542 6,489 1.08 0.85
August 8 6,000 6,625 6,559 0.91 1.15
September 9 10,000 6,667 6,630 1.51 1.73
October 10 12,000 6,750 6,700 1.79 1.78
November 11 14,000 6,875 6,770 2.07 2.12
December 12 8,000 7,000 6,840 1.17 1.09
January 13 3,000 6,917 6,911 0.43
February 14 4,000 6,833 6,981 0.57
March 15 3,000 7,000 7,051 0.43
April 16 5,000 7,083 7,121 0.70
May 17 5,000 7,167 7,192 0.70
June 18 8,000 7,333 7,262 1.10
July 19 3,000 7,375 7,332 0.41
August 20 8,000 7,375 7,402 1.08
September 21 12,000 7,500 7,473 1.61
October 22 12,000 7,500 7,543 1.59
November 23 16,000 7,375 7,613 2.10
December 24 10,000 7,250 7,683 1.30
January 25 2,000 7,333 7,754 0.26
February 26 5,000 7,583 7,824 0.64
March 27 5,000 7,792 7,894 0.63
April 28 3,000 8,042 7,964 0.38
May 29 4,000 8,250 8,035 0.50
June 30 6,000 8,250 8,105 0.74
July 31 7,000 8,292 8,175 0.86
August 32 10,000 8,375 8,245 1.21
September 33 15,000 8,292 8,316 1.80
October 34 15,000 8,208 8,386 1.79
November 35 18,000 8,208 8,456 2.13
December 36 8,000 8,292 8,526 0.94
January 37 5,000 8,458 8,597 0.58
February 38 4,000 8,750 8,667 0.46
March 39 4,000 8,958 8,737 0.46
April 40 2,000 9,042 8,807 0.23
May 41 5,000 9,167 8,878 0.56
June 42 7,000 9,417 8,948 0.78
July 43 10,000 9,583 9,018 1.11
August 44 14,000 9,500 9,088 1.54
September 45 16,000 9,375 9,159 1.75
October 46 16,000 9,333 9,229 1.73
November 47 20,000 9,417 9,299 2.15
December 48 12,000 9,458 9,369 1.28
January 49 5,000 9,333 9,440 0.53
February 50 2,000 9,083 9,510 0.21
March 51 3,000 9,083 9,580 0.31
April 52 2,000 9,417 9,650 0.21
May 53 7,000 9,667 9,721 0.72
June 54 6,000 9,583 9,791 0.61
July 55 8,000 9,861 0.81
August 56 10,000 9,931 1.01
September 57 20,000 10,002 2.00
October 58 20,000 10,072 1.99
November 59 22,000 10,142 2.17
December 60 8,000 10,212 0.785
1
2
3
4
Year Months Period Demand Dt De-Sea Demand Regressed De-Sea Demand Seasonal Factor Avg Seasonal Factor
January 1 2,000 6,068 0.33 0.43
February 2 3,000 6,138 0.49 0.47
March 3 3,000 6,208 0.48 0.46
April 4 3,000 6,278 0.48 0.40
May 5 4,000 6,349 0.63 0.62
June 6 6,000 6,419 0.93 0.83
July 7 7,000 6,542 6,489 1.08 0.85
August 8 6,000 6,625 6,559 0.91 1.15
September 9 10,000 6,667 6,630 1.51 1.73
October 10 12,000 6,750 6,700 1.79 1.78
November 11 14,000 6,875 6,770 2.07 2.12
December 12 8,000 7,000 6,840 1.17 1.09
January 13 3,000 6,917 6,911 0.43
February 14 4,000 6,833 6,981 0.57
March 15 3,000 7,000 7,051 0.43
April 16 5,000 7,083 7,121 0.70
May 17 5,000 7,167 7,192 0.70
June 18 8,000 7,333 7,262 1.10
July 19 3,000 7,375 7,332 0.41
August 20 8,000 7,375 7,402 1.08
September 21 12,000 7,500 7,473 1.61
October 22 12,000 7,500 7,543 1.59
November 23 16,000 7,375 7,613 2.10
December 24 10,000 7,250 7,683 1.30
January 25 2,000 7,333 7,754 0.26
February 26 5,000 7,583 7,824 0.64
March 27 5,000 7,792 7,894 0.63
April 28 3,000 8,042 7,964 0.38
May 29 4,000 8,250 8,035 0.50
June 30 6,000 8,250 8,105 0.74
July 31 7,000 8,292 8,175 0.86
August 32 10,000 8,375 8,245 1.21
September 33 15,000 8,292 8,316 1.80
October 34 15,000 8,208 8,386 1.79
November 35 18,000 8,208 8,456 2.13
December 36 8,000 8,292 8,526 0.94
January 37 5,000 8,458 8,597 0.58
February 38 4,000 8,750 8,667 0.46
March 39 4,000 8,958 8,737 0.46
April 40 2,000 9,042 8,807 0.23
May 41 5,000 9,167 8,878 0.56
June 42 7,000 9,417 8,948 0.78
July 43 10,000 9,583 9,018 1.11
August 44 14,000 9,500 9,088 1.54
September 45 16,000 9,375 9,159 1.75
October 46 16,000 9,333 9,229 1.73
November 47 20,000 9,417 9,299 2.15
December 48 12,000 9,458 9,369 1.28
January 49 5,000 9,333 9,440 0.53
February 50 2,000 9,083 9,510 0.21
March 51 3,000 9,083 9,580 0.31
April 52 2,000 9,417 9,650 0.21
May 53 7,000 9,667 9,721 0.72
June 54 6,000 9,583 9,791 0.61
July 55 8,000 9,861 0.81
August 56 10,000 9,931 1.01
September 57 20,000 10,002 2.00
October 58 20,000 10,072 1.99
November 59 22,000 10,142 2.17
December 60 8,000 10,212 0.785
1
2
3
4
Now we forecast the demand by taking the equation
Deseasonalized Demand = 5997.26 + 70.25t, and multiplying it by the average seasonal factor
for each period.
F61 = (5997.26 + 70.25 x 61)0.43 = 4387
F62 = (5997.26 + 70.25 x 62 )0.47 = 4913
F63 = (5997.26 + 70.25 x 63)0.46 = 4822
F64 = (5997.26 + 70.25 x 64)0.40 = 4178
a. STEP 6 Error Analysis
• Error = Forecast – Demand
• Absolute deviation
• Mean squared error (MSE)
• Mean absolute deviation (MAD)
• Mean absolute percentage error (MAPE)
• Tracking signal (TS)
The Results are all given in the table below!!
Now we can evaluate the Forecast
We can see from the tracking signals that 3 of the periods are outside the interval of [-6,6],
meaning an underestimation in demand. The MAPE provides evidence that the forecast error is
acceptable due to relatively low percentages which displays the minimal differences between
the forecasted and actual demand data. The amount of errors does not seem to be high which
means that the forecast was good.
Year Months Period Demand Dt De-Sea Demand Regres. De-Sea Demand Seasonal Factor Avg Seasonal Factor Forecast Error Abs Error MSE MAD % Error MAPE TS
January 1 2,000 6,068 0.33 0.43 2588 588 588 346,233 588 29 29 1
February 2 3,000 6,138 0.49 0.47 2913 -87 87 176,935 338 3 16 1.48
March 3 3,000 6,208 0.48 0.46 2872 -128 128 123,424 268 4 12 1.39
April 4 3,000 6,278 0.48 0.40 2500 -500 500 155,074 326 17 13 -0.39
May 5 4,000 6,349 0.63 0.62 3944 -56 56 124,678 272 1 11 -0.67
June 6 6,000 6,419 0.93 0.83 5356 -644 644 173,097 334 11 11 -2.48
July 7 7,000 6,542 6,489 1.08 0.85 5534 -1466 1466 455,274 496 21 12 -4.63
August 8 6,000 6,625 6,559 0.91 1.15 7551 1551 1551 698,909 628 26 14 -1.18
September 9 10,000 6,667 6,630 1.51 1.73 11489 1489 1489 867,517 723 15 14 1.03
October 10 12,000 6,750 6,700 1.79 1.78 11913 -87 87 781,531 660 1 13 1.00
November 11 14,000 6,875 6,770 2.07 2.12 14377 377 377 723,411 634 3 12 1.63
December 12 8,000 7,000 6,840 1.17 1.09 7488 -512 512 684,968 624 6 11 0.84
January 13 3,000 6,917 6,911 0.43 2948 -52 52 632,486 580 2 11 0.81
February 14 4,000 6,833 6,981 0.57 3313 -687 687 621,054 587 17 11 -0.37
March 15 3,000 7,000 7,051 0.43 3262 262 262 584,224 566 9 11 0.08
April 16 5,000 7,083 7,121 0.70 2836 -2164 2164 840,484 666 43 13 -3.18
May 17 5,000 7,167 7,192 0.70 4468 -532 532 807,684 658 11 13 -4.03
June 18 8,000 7,333 7,262 1.10 6059 -1941 1941 972,113 729 24 13 -6.30
July 19 3,000 7,375 7,332 0.41 6253 3253 3253 1,477,982 862 108 18 -1.55
August 20 8,000 7,375 7,402 1.08 8521 521 521 1,417,655 845 7 18 -0.97
September 21 12,000 7,500 7,473 1.61 12950 950 950 1,393,092 850 8 17 0.16
October 22 12,000 7,500 7,543 1.59 13411 1411 1411 1,420,317 875 12 17 1.76
November 23 16,000 7,375 7,613 2.10 16167 167 167 1,359,782 845 1 16 2.03
December 24 10,000 7,250 7,683 1.30 8411 -1589 1589 1,408,345 876 16 16 0.14
January 25 2,000 7,333 7,754 0.26 3308 1308 1308 1,420,411 893 65 18 1.60
February 26 5,000 7,583 7,824 0.64 3713 -1287 1287 1,429,517 908 26 19 0.16
March 27 5,000 7,792 7,894 0.63 3652 -1348 1348 1,443,881 924 27 19 -1.30
April 28 3,000 8,042 7,964 0.38 3171 171 171 1,393,363 898 6 19 -1.15
May 29 4,000 8,250 8,035 0.50 4992 992 992 1,379,242 901 25 19 -0.05
June 30 6,000 8,250 8,105 0.74 6762 762 762 1,352,642 896 13 19 0.80
July 31 7,000 8,292 8,175 0.86 6972 -28 28 1,309,033 868 0 18 0.80
August 32 10,000 8,375 8,245 1.21 9491 -509 509 1,276,209 857 5 18 0.22
September 33 15,000 8,292 8,316 1.80 14411 -589 589 1,248,065 849 4 17 -0.48
October 34 15,000 8,208 8,386 1.79 14910 -90 90 1,211,594 826 1 17 -0.60
November 35 18,000 8,208 8,456 2.13 17958 -42 42 1,177,029 804 0 16 -0.67
December 36 8,000 8,292 8,526 0.94 9334 1334 1334 1,193,744 819 17 16 0.97
January 37 5,000 8,458 8,597 0.58 3667 -1333 1333 1,209,484 833 27 16 -0.64
February 38 4,000 8,750 8,667 0.46 4113 113 113 1,177,990 814 3 16 -0.52
March 39 4,000 8,958 8,737 0.46 4042 42 42 1,147,830 794 1 16 -0.48
April 40 2,000 9,042 8,807 0.23 3507 1507 1507 1,175,911 812 75 17 1.39
May 41 5,000 9,167 8,878 0.56 5516 516 516 1,153,716 805 10 17 2.04
June 42 7,000 9,417 8,948 0.78 7466 466 466 1,131,412 796 7 17 2.65
July 43 10,000 9,583 9,018 1.11 7691 -2309 2309 1,229,068 832 23 17 -0.24
August 44 14,000 9,500 9,088 1.54 10462 -3538 3538 1,485,651 893 25 17 -4.19
September 45 16,000 9,375 9,159 1.75 15871 -129 129 1,453,004 876 1 17 -4.42
October 46 16,000 9,333 9,229 1.73 16409 409 409 1,425,057 866 3 16 -3.99
November 47 20,000 9,417 9,299 2.15 19748 -252 252 1,396,090 853 1 16 -4.35
December 48 12,000 9,458 9,369 1.28 10257 -1743 1743 1,430,330 872 15 16 -6.26
January 49 5,000 9,333 9,440 0.53 4027 -973 973 1,420,464 874 19 16 -7.36
February 50 2,000 9,083 9,510 0.21 4513 2513 2513 1,518,335 906 126 18 -4.32
March 51 3,000 9,083 9,580 0.31 4432 1432 1432 1,528,765 917 48 19 -2.71
April 52 2,000 9,417 9,650 0.21 3843 1843 1843 1,564,664 934 92 20 -0.69
May 53 7,000 9,667 9,721 0.72 6039 -961 961 1,552,552 935 14 20 -1.71
June 54 6,000 9,583 9,791 0.61 8169 2169 2169 1,610,934 958 36 21 0.59
July 55 8,000 9,861 0.81 8410 410 410 1,584,703 948 5 20 1.03
August 56 10,000 9,931 1.01 11432 1432 1432 1,593,035 957 14 20 2.52
September 57 20,000 10,002 2.00 17332 -2668 2668 1,689,937 987 13 20 -0.26
October 58 20,000 10,072 1.99 17908 -2092 2092 1,736,250 1,006 10 20 -2.34
November 59 22,000 10,142 2.17 21538 -462 462 1,710,439 996 2 20 -2.82
December 60 8,000 10,212 0.78 11179 3179 3179 1,850,406 1,033 40 20 0.365
1
2
3
4
4. Check your work a. Is the work correct in every detail?
• Using text and using my lecture notes for the data. I can safely assume that
work I have written is correct.
b. Are my assumptions reasonable?
• I can assume that the information I have provided is accurate and correct.
c. In terms of the things I know, do the results make sense?
• Yes, in terms of the things I understood from my research, the results do make a
lot of sense.
5. Learn and Generalize a. This was a tedious task as it required a lot of number punching, however I have
further strengthened my skill in demand forecasting as I am now able to perform
an error analysis.