project management

profileLiban
FinalProjectPhaseIII.docx

Running head: WORK BREAKDOWN STRUCTURE 1

WORK BREAKDOWN STRUCTURE 6

Work Breakdown Structure

Project phases

Project initiation

The current project initiation phase will include the implementation of the plan and design of the cloud computing project. An evaluation of the timelines, cost, and goals for the project will also be defined during these phases. The project manager and the team will evaluate the profitability of the project and decide whether the project is viable or not.

Project planning

A project plan will be developed in this phase of the project after receiving the green light to go ahead with the project. The project plan will include risk management strategies, management of suppliers, and communication with stakeholders. The project plan will act as guidance for the project manager and the team. On how to obtain the necessary resources for the project, including the financing and materials required. 

Project Execution

This is the phase where all the work will happen in the project. It will begin with the selection of a service provider for the cloud services, cloud platform, security strategy, and security risk strategy. The core configuration of the data model and customer field will be an essential step towards achieving the goal of the project. The project team will also oversee the creation of staff accounts and profiles during this stage as the location-specific configuration takes place. The incidence workflow, workplace designation, service cloud agent scripts, and business rules will be configured. 

Project monitoring and control

The system should be tested after the configuration and migration, and this will involve the IT manager Future Link as the finalization of the project nears. The project team will also monitor their progress as they calculate key performance indicators as the project closure nears.

Project closure  

The team will hand over the successful project to the CEO of future Link during this phase. 

TASK

TASK DESCRIPTION

PREDECESSOR

START DATE

END DATE

OWNER

COST

STATUS

1

Design Concept and plan definition

01/03/2020

20/03/20202

Project manager

Delivered

2

Cloud platform

1

20/03/2020

01/04/2020

CEO and IT manager

Delivered

3

Selection of Cloud Service provide

1,2

01/04/2020

07/05/2020

Project Manager

Pending

4

Security Strategy and security risk strategy

1,2

01/04/2020

07/05/2020

Project manager

Pending

5

Core configuration

3,4

10/05/2020

1/09/2020

Project manager

Pending

6

Location specific configuration

5

01/09/2020

10/09/2020

Project manager

Pending

7

Testing

6

10/09/2020

30/09/2020

Project manager

Pending

8

Enablement

7

01/10/2020

20/10/2020

Project manager

Pending

9

Staff training and education

8

01/11/2020

30/11/2020

Project manager

Pending

10

Deployment

4,5,6,7,8

31/12/2020

Project manager

Pending

References

Work Breakdown Structure. (2003). Office of Management, Budget and Evaluation. U.S. Department of Energy.

Mukul Burghate. (2018). Work Breakdown Structure: Simplifying Project Management. International Journal of Commerce and Management Studies (IJCAMS) Vol.3, No.2,