Project Selection and Initiation

After having been recently laid off from his job of 35 years as a Sales Manager at Hightower Global Solutions, Tony DiBello got a call from

his former boss Peter McKenzie asking him to return to the organization to help get a new initiative off the ground.

The Project

Based on McKenzie's brief description over the phone, DiBello understood that the project was to develop a "sales training intranet" (code

named HighLEARN) for Hightower's 350 geographically dispersed sales associates. A Fortune 500 firm specializing in financial services

technology and outsourcing solutions, Hightower had more than 100 complex products and services to offer its diverse client base of banks,

mutual fund complexes and insurance companies. In addition, Hightower's executive leadership was pursuing an aggressive acquisition

strategy, buying small companies and further expanding the product portfolio. As a result, both new and experienced sales associates were

struggling to get up to speed on all of the Hightower offerings, and sales leadership was concerned that they were missing opportunities to

pitch new products to clients. McKenzie, the Head of Hightower's Sales organization, had become an evangelist for what he called "Blended

Learning"—combining traditional classroom training with online learning opportunities—and he was determined to develop a highly

interactive "portal" to help improve sales performance. He envisioned a custom intranet where Hightower sales associates across the globe

could log on to get comprehensive product information and presentations, access webinars and videos with product specialists, and share tips

and feedback through blogs, forums and social features.

McKenzie's enthusiasm for the intranet project was infectious. Even Carol Bailey, Hightower's CEO, had come to believe that connecting

people in this way was critical to ensuring Hightower's success and sustainability in the global market. Due to the breadth and diversity of the

company's product offerings—and the rate at which they were acquiring new products—there was immense pressure on everyone in the sales

organization to become experts on as many products and services as possible in order to meet aggressive sales targets.

To support the CEO's strategic agenda, the following project elements, team members, and constraints were provided.

Project Budget and Roll-out Date

Project Budget $1.5 million

Project Scheduled to Start June 1, 2017

HighLEARN Roll-out January 1, 2018

Project Team Members

Name Role

Ricardo Contin Director of Learning and Development

Steve Quan Hightower IT Operations Specialist

Shannon Valley Hightower IT Systems and Security

Monica Ianucci Content Specialist

Jonathan Brant Content Specialist

Initial Project Risks

1 Website does not meet user requirements or functionality.

2 Shannon Valley and Steve Quan are not available to contribute to the project until July 15, 2017.

3 Marketing department has not endorsed the approach; believes they should go with Microsoft® SharePoint® system.

4 Security of intranet/portal: no external access beyond firewall.

QSO 640: Project Management Copyright &copy; 2014, %year% MindEdge Inc. All rights reserved. Duplication prohibited. <br>PMP, PMI-ACP, PMI-RMP, PMBOK, and the PMI

Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

Project Activity Duration

Portal Development

User Interface Design Complete and Tested 2 days

Style Sheets for Portal 3 weeks

Theme Design for Website 8 weeks

Portal Administration Complete and Accepted 2 days

Administrative Page Groups 10 weeks

Administrative Access Control Design 7 weeks

Content Management & Coding Complete and Tested 2 days

Content Display from Repository 28 days

Content Upload and Functionality 8 weeks

Configure/Code Indexing and Functionality 13 weeks

Infrastructure and Security

Architecture Approved for Implementation 1 day

Servers for Development, Staging, and Production 13 weeks

Configure Firewalls 4 weeks

Integrate Infrastructure and Security Systems 8 weeks

Log-in/Registration System Complete and Tested 3 days

Create Log-in/User Profiles 4 weeks

Content Creation and Editing

Product Content Modules Completed and Accepted 5 days

Interviews with Subject Matter Experts (SMEs) and Sales Representatives 2 weeks

Product Sales Summaries 4 weeks

Sales Case Studies for Content Modules 7 weeks

Edit/Film SME Videos 1 week

Upload Presentations, Demos, and Webinars for Content Modules 2 weeks

Documentation

Development and Document Coding Standards and Procedures 15 weeks

Develop Test Acceptance Plans and Procedures 15 weeks

HighLEARN Database Test and Acceptance 1 week

HighLEARN Roll-out

Hightower Global Solutions Organizational Chart

QSO 640: Project Management Copyright &copy; 2014, %year% MindEdge Inc. All rights reserved. Duplication prohibited. <br>PMP, PMI-ACP, PMI-RMP, PMBOK, and the PMI

Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

Hightower Global Solutions Staffing List

IT Systems and Security

Cyber Security

Harold Williams

Dennis Callahan

Beth Stroller

Systems Engineering

Juan Felipe

Susan Xiao

Cheryl Bolden

Business Operations

John Petrel

Steven Johnson

Steve Quan

Learning and Development

Human Resources

Christina Alston

Elizabeth Carol

Judy Wilson

Terrence Holober

Frederick Concern

Kimberly Contos

Nicholas Bergh

QSO 640: Project Management Copyright &copy; 2014, %year% MindEdge Inc. All rights reserved. Duplication prohibited. <br>PMP, PMI-ACP, PMI-RMP, PMBOK, and the PMI

Registered Education Provider logo are registered marks of the Project Management Institute, Inc.

Training Department Tyler Burns

Dianne Harrison

Content Development

Jonathan Brant

Monica Ianucci

Henry Stephenson

Sales, Marketing, and Budgeting

Domestic Sales James Youngster

William Feller

International Sales Tracy Woodster

Andrew Levitt

Marketing/Advertising Sasha Fiercer

Jason Holdmeer

Acquisitions and Product Portfolios

Product Management Meagan Golden

Melvin Simpson

Acquisitions Management Nicole Smith

Evelyn Lovelace

Strategic Management Richard Mattingly

Teresa Berry-Van Helbing

Please use the information above to complete your final Graded Case Study. Return to your learning environment to submit your work.

QSO 640: Project Management Copyright &copy; 2014, %year% MindEdge Inc. All rights reserved. Duplication prohibited. <br>PMP, PMI-ACP, PMI-RMP, PMBOK, and the PMI

Registered Education Provider logo are registered marks of the Project Management Institute, Inc.