question

profiledenittawhite
fin5130.12.xlsx

Sheet1

10.7 Chapter 10
A Uneven Cash Flow Stream
Time CF
0 -15000000
1 5000000
2 10000000
3 20000000
$16,108,951.52 $12,836,213.37 $10,059,587.41
Accept NPV>0
B
Time CF
0 -15000000
1 20000000
2 10000000
3 6000000
$18,300,939.42 $15,954,169.80 $13,897,838.42
Accept NPV>0
b. IRR
A 43.97% >5% >10% >15% Accept
B 82.03% >5% >10% >15% Accept
10.8
Annuity
NPV NPV
PV of cash flows $17,508.71 $408.71 Accept
PV of cash flows $25,748.11 $3,318.11 Accept
IRR
14.00%
Truck 14.00%
MIRR
Future value of annuity ($33,711.53)
MIRR 14.54% >14% Accept
Pulley
MIRR
Future value of annuity $49,575.78
MIRR 17.19% >14% Accept
10.10'
Project S
pv of cash flows $10,814.33 $814.33 npv
Project L
pv of cash flows $26,675.34 $1,675.34 npv Accept
IRR
Project S 15.24% Accept
Project L 14.67%
MIRR Project S
Future value of annuity ($19,058.54)
MIRR 13.77% Accept
MIRR Project L
Future value of annuity ($47,011.07)
MIRR 13.46%
Profitability Index
PI PV of cash flows/Initial investment
Project S 1.08 Accept
Project L 1.07
Project L to be selected on the basis of NPV
10.12
a.
Purchase price 900000
Installation cost 165000
1065000
Annuity
PV of cash flows $1,201,578.34
Less: Initial $136,578.34 npv accept
Irr 19.22% irr irr>cost of capital accept
Reduce the cash flows by the amount of environmental costs c.
r NPVA NPVB
10 $478.83 $372.37
12 $366.13 $308.39
18 $94.46 $150.42
22 ($43.14) $67.26
A -400 $478.83
-528
-219
-150
1100
820
990
-325
b. 20.65% A
25.84% B
d. MIRR B
Future value of an annuity $1,992.31
MIRR 17.35%
MIRR A
14.91%
Select B at a cost of capital of 10%
e. Crossover rate
Year A CF B CF Difference
0 -400 -650 250
-528 210 -738
-219 210 -429
-150 210 -360
1100 210 890
820 210 610
990 210 780
-325 210 -535
Crossover rate 14.76% below the crossover rate, choose A
above the crossover rate, choose Bz
10.16.
Equivalent Annual Annuity Plane A
Present Value of Cash Flows $108.14 million shorter life NPV $8.14
EAA $2.26 million
Plane B
Equivalent Annual Annuity
NPV
$9.26 millions longer life
EAA $1.64 millions
Select A
10.21
A B
Year Annual CF
0 -25000000
1 5000000
2 10000000
3 15000000
4 20000000
Payback A 2.6666666667 years
Year Annual CF 1.5 years Payback B B
0 -25000000
1 20000000
2 10000000
3 8000000
4 6000000
Discounted Payback B
Period Annual CF Discount Rate Discount CF
0 -25000000 0 0
1 20000000 0.9090909091 18181818.1818182
2 10000000 0.826446281 8264462.80991735
3 8000000 0.7513148009 6010518.40721262
4 6000000 0.6830134554 4098080.73219042
Discounted Payback Payback
1.825 years 26446280.9917355 6818181.81818182
A
Period Annual CF Discount Rate Discount CF
0 -25000000 0 0
1 5000000 0.9090909091 4545454.54545454
2 10000000 0.826446281 8264462.80991735
3 15000000 0.7513148009 11269722.0135237
4 20000000 0.6830134554 13660269.1073014
24079639.3688956
920360.631104436
Disc Payback 3.067375 years