work-10

profileDongrim
figure10.1to10.5.pdf

Task Predecessor

Homeowner Acquire lawn materials

Remove debris Teens and youth group

Teens 2

1,2 Prepare soil Plont lawn seed

3 3 Teens

Plant shrubs 2 Teens 5

Correct

Finish Start

Network diagram with milestones at the start and finish.

This network has two Concurent paths.

Incorrect

Start Finish

The most common network diagram mistake is removing all concurrent tasks for the same resource. Resource constraints may prevent tasks 4 and 5 from being pertormed at the same time, but that

shouldnt change the network. The network represents only task sequence constraints.

FIGURE Network diagram 10.1 developed from a predecessor table.

Milestones Are Useful Markers

In setting up the sequence of events,

many project managers find it useful

to mark significant events in the life of a project. These markers-called milestones-are often used in work breakdown structures and network diagrams (see Eigure 10.2). Milestones have zern duration, so adding them to

affect the schedule at Back to page i a Tnere are iaree sreat reasons to

Complete salmon data collection.

During an environmental impact study, the project uses data from a federal agency. Task 4.1 will not be able to start until at least July 14, the day the federal report is released.

FIGURE 10.2 Milestones can show external dependencies. Finish-to-start The most common task relationships on the network are finish-to-start. The first task must finish before the next one can start.

MTWT|F |M| T |w T| F

Task A must finish before Task B can start.

Start-to-start The successor task can start as soon as the predecessor task starts. The example shows a painting company, painting all the

rooms on one floor of an office building. After the first room is prepared, both the prep crew and the paint crew can be working at the same time.

Overlapping the tasks reduces the total duration of the project.

MTwT |F |M|T |wlT|E| Prep

Paint B

Task A must start before Task B can start.

Finish-to-finish The successor task can finish only when the prede cessor task is finished. The example shows the last two tasks of a design phase. Planning for the construction phase can begin before the final design approval, but it cannot finish until design is complete.

MTwT| F |M|T|wlT| F Design approval

A

Planning for the next phase B

Task A must finish before Task B can finish.

FIGURE10.3 Task relationships.

CONCEPr PLANNING STEP THREE: STIMATE WORK PACKAGES

In order to determine the cost and duration of an entire project, it's

CONCEP PLANNING STEP THREE: ESTIMATE WORK PACKAGES

In order to determine the cost and duration of an entire project, it's necessary to builda cost and schedule estimate for each work package; this is

called bottom.up estimating. A lot of

information is generated in the estimating process, so it is critical to record it in a systematic manner. (Table 10.1 shows the work package estimates for the home landscape project. Tables 10.2 to 10.5 illustrate some of the variables that affect work package estimates.)

The schedule estimate for a task measures the time from initiation to completion. This estimate is usuallyy referred to as duration of a task. When building a schedule estimate, it's important to include all the time the task will span. For instance, it may take only 1 day to order materials, but if it takes 10 days for delivery, the total duration of the task will be 11 days. Similarly, while a certain decision might take only 2 hours to make, it might be more realistic to estimate duration at 5 days if the decision maker is likely to be busy at that time.

Cost estimates come from four sources:

1. Labor estimates. These project how much human effort will be put into a task. If three people work 8 hours a day for 3 days, the total labor estimate will be 72 hours. On

11.

10.1 Home Landscape TABLE Project Work Package Estimates

ID Task Name

Duration Labor Resource Hours Names

Design home

5 days 80 hrs.

1 Homeovwner [0.5], Teens [1.5 landscape

2 Put in lawn

3 Acquire 2 days lawn

64 Homeowner, hrs. Teens [3]1

materials

Install sprinkler system

4

5 Identify 1 day sprinkler locationns

Fixed Contractor, fee,8 Homeowner hrs.

Dig trenches

6 2 days Fixed Contractor fee

7 Install pipe and hardware

3 days Fixed Contractor fee

1 day 8 Cover sprinkler system

Fixed Contractor fee

9 Plant grass

10 Remove 4 days debris

Teens [31, Youth Group

256 hrs.

Teens [3] Rototiller

4 days 11 Prepare soil

12 Plant lawn seed

96

hrs.

1 day 16 Teens [2] hrs.

1 day 12 Plant lawn seed

16 Teens [2] hrs.

13 Plant shrubs

14 Build fence

6 days 96 Teens [2] hrs.

15 Acquire 2 days 16 Homeowner fence hrs. material

16 Install fence

1 day 17 Mark fence line

32 Homeowner, hrs. Teens [3]

5 days 18 Install posts

80 Teens (21 hrs.

6 days Teens [3]1 19 Install |fencing and gates

144 hrs.

20 Paint/stain |3 days fence and

gates

72 Teens [31 hrs.

On task 1, both the homeowner and the teens are working 4 hours per day.

Fixed.price bids. Fixed.estimate

costs can replace the three

previous cost sources. For example, a vendor or subcontractor might make a fixed.

price bid that includes labor, equipment, and materials. Fixed.

price bids mean that the vendor takes responsibility for costs; should there be overruns, the cost to the project will not change. (The landscape project in Table 10.1

1.

TABLE 10.2 Work Package Estimate: Example 1

Task description: During an environmental study, a power

company counts salmon during a 40-

day salmon run.

Assumption: The federal agency Overseeing the power company dictates the length of the study.

Materials: None

Duration: 40 days

Labor and Equipment Table

Type Average Use

Total

1@ 10 hrs./day

Salmon 400 hrs. specialist

2@ 10 hrs./day

800 hrs. Field technician Truck 1 all day 40 days |Increasing the number of people on this task does not change the duration but it could increase the accuracy of

the study. Is it really necessary to concentrate on costs when trying to build a realistic schedule? It is, because each cost represents a resource constraint. Costs such as hiring subcontractors and purchasing materials will constrain the schedule. Later on, the schedule will be adjusted to account for these resource constraints (this is the fifth step of planning), but before adjusting the schedule we need to identify all the resource requirements, one work

package at a time.

TABLE 10.3 Work Package Estimates: Example 2

Task description: During a training project, software is upgraded on 20 workstations in a training room.

Assumption: The average time to install the software is 2 hours per workstation. Testing is 1 hour per workstation. Only one person can work on one workstation at a time.

First Estimate

Duration:5 days

Materials: 20 copies of the new software

Labor and Equipment Table

Type Average Total Use

40 hrs. Computer technician

1@8 hrs./day

Tester (user or 1@4 technician)

20 hrs. hrs./day

Software test

kit 1 per tester 1 test

kit The training manager does not want the training room out of use for a whole week. In fact, he wants the upgrade done overa weekend so the training room doesn't lose any

availability. Revised Estimate

Duration: 2 days

Materials: 20 copies of the new software

Labor and Equipment Table

Type Average Total Use

Computer 2@ 10 40 hrs.

How Productivity Relates to Duration

When estimating the number of people needed for a task, you will need to consider their productivity. Adding people to simple tasks always reduces the duration. Productivity is said to be constant when the total labor hours do not change as the number of people assigned to the task changes. (The productivity of the technicians in Table 10.3 was constant, and so was the "Remove debris" task in Table 10.1)

However, in the case of tasks involving knowledge workers, adding more workers does not always result in greater productivity and shorter duration for a task. For example, if two engineers are working ona complex problem, adding three more may actually slow the task and produce no recognizable change in product quality. The result is a measurable decrease in productivity because the cost for labor increases while the product stays the same. (The first revised estimate in Table 10.5 is another example of this factor.)

TABLE 10.4 Work Package Estimates: Example 3

Task description: A government agency is mapping a forest. Aerial photography of the entire area is the first step in creating the maps.

Assumption: An aerial photography subcontractor rents airplanes

(complete with pilots and photographers). The agency has one Scientist ride with every airplane. Thhe

TABLE 10.4 Work Package Estimates: Example 3

Task description: A government agency is mapping a forest. Aerial

photography of the entire area is the first step in creating the maps.

Assumption: An aerial photography subcontractor rents airplanes

(complete with pilots and photographers). The agency has one Scientist ride with every airplane. The forest is broken into 60 squares. They can photograph one square per day. During the flight, a ground technician stays in radio contact with the scientist to answer mapping questions. First Estimate

Duration: 60 days Materials: None

Labor and Equipment Table

Type Average Total Use

1@8 |hrs./day

Scientist (in 480 hrs. plane)

480 hrs. 1@8 hrs./day

Airplane

480 hrs. 1@8 hrs./day

Ground

technician The forest area traditionally has so much cloudy weather that the agency estimates there will be only one clear

day out of every three, but the photography needs to take place

during the three months of summer

when there is no snow.

TABLE 10.5 Work Package Estimates: Example 4

Task description: A systems analyst is working on three projects at the same time. One of her project managers asks her to estimate the design of aa

subsystem. Assumption: She will continue to work on all three projects simultaneously. First Estimate

Duration: 40

days Materials: None

Labor and Equipment Table

Type Systems analyst

Total Average Use

1@ 2.5 hrs./day

100

Her project manager needs the design performed much faster and suggests he could get another analyst to work with her part.time.

Revised Estimate

Duration: 30 days

Materials: None

Labor and Equipment Table

Average Use Total

2@ 2.5 hrs./day

Type Systems analyst

150

Adding people to a design task can speed up some of the work, but much of it will be done together so it results in an increase in the total labor cost. It is possible the resulting design will be better, but that is another

assumption.

be better, but that is another assumption. Then the project manager asks her what it would take to get it done the fastest. She responds, "Talk to my other project managers and arrange to get me completely off those projects for a few weeks so I can concentrate 100 percent on yours."

Revised Estimate

Duration: 10

days Materials: None

Labor and Equipment Table

Type Average Use Total 1@ 8 hrs./dayy

80 Systems analyst Not only is she able to spend more time per day on this task but she knows that if she is able to concentrate on it 100 percent she will be more productive.

Another point to consider when measuring productivity is that people who spend all their time on one project are usually more productive than people who spread their time across multiple projects (again, see Table 10.5). The analyst estimates that the most productive way for her to work- requiring the fewest hours and fewest days-is to be able to devote 100 percent of her attention to one project.

When calculating hours for your part.

time project workers, it is usually unnecessary to figure out exactly what hour of which day they'll be working on your project. By assigning a

unnecessary to figure out exactly what hour of which day they'll be working on your project. By assigning a resource.level assumption, such as

"two hours per day," to all their tasks, you proportionally increase the estimates for the duration of the task. This approach allows each individual team member to decide for himself or herself when to actually work on the task. It doesn't matter whether they get started on it as soon as it's scheduled or work on it the last day. All you need to do to prepare a detailed plan is to

give them a start time anda completion time.

As you can see, there is much to be considered when estimating the costs and duration of work packages. Chapter 12 discusses the subject further, with many more tips and

techniques.

PLANNING STEP FOUR: CALCULATE AN INITIAL SCHEDULE

Calculating a schedule may be one of the most well known, but unappreciated, of all project management techniques. It can be

particularly tedious and time.

consuming when done by hand for large projects. Yet it is the key to establishing realistic schedules and meeting them. (The tedium involved is a compelling reason to use project

management software.) Ac dicco onrlior tho initinl