District4WarehouseMove
Cannon_F_M3_A2
August 24th,2018
Please see my comments below to see the items that need to be addressed in the write-up (report).
District4WarehouseMove
(a) Project plan with precedence relationship is given below:
|
ID |
Task |
Estimated Duration |
Pred1ecessor |
|
1 |
Start of the project |
4 |
|
|
2 |
Documents of the project |
8 |
1 |
|
3 |
Status Meetings/Reports |
2 |
2 |
|
4 |
Initial Meetings Planning |
4 |
3 |
|
5 |
Permits of Electricity |
11 |
4 |
|
6 |
Permits of Plumbing |
11 |
4 |
|
7 |
Permits of Buildings |
15 |
5 |
|
8 |
Framing |
55 |
5 |
|
9 |
Electrical |
11 |
6 |
|
10 |
Plumbing |
11 |
7 |
|
11 |
Drywall |
2 |
8 |
|
12 |
Work Finnish |
30 |
9,10,11,12 |
|
13 |
Workbenches |
19 |
12 |
|
14 |
Packing Equipment |
16 |
13 |
|
15 |
Move |
2 |
14 |
|
16 |
Closure Procurement |
2 |
15 |
|
17 |
Closure Project |
9 |
16 |
(b) Project network diagram (Activity on Node) diagram is following
(c) Alternative paths and Critical path are as listed below
For the whole project to be completed, it will take up to 122 days.
References (What is it you are referencing when there is no write-up?)
Mind Tool, Inc. (2013) Project Management Phases and Processes. Retrieved October 26, 2013 from
Piscopo, M. (2013) Performance Report. Retrieved October 26, 2013 from http://www.projectmanagementdocs.com/project-documents/performance-report.html
Project Closure (n.d.) Retrieved October 26, 2013 from https://wiki.state.ma.us/confluence/download/attachments/69894234/Closure+Training.pdf
Comments:
The project plan was not correctly developed and the appropriate work breakdown structure (WBS) was not properly completed.
The predecessor column was not correctly completed and set included additional aspects that set it apart from the ordinary.
Critical paths activities were not correctly identified with additional insights.
The risks that would impact the project schedule were not correctly identified with appropriate information/action to mitigate those risks.
The paper was not adequately organized with a good introduction and conclusion. There was no writing to assess spelling/grammar error. APA elements were not appropriately addressed.