facility project

profileJones 123
FacilityProjectNumbers.xls

Sheet1

Component # of Units Total SF Cost Required Area Total Cost
Public Spaces
Vestibule 1 area 250 SF $30,000.00
Lobby/Lounge 1 area 2,500 SF $300,000.00
Control/Cashier 1 area 200 SF $24,000.00
Vending 1 area 100 SF $10,000.00
Concessions 1 area 300 SF $36,000.00
Juice Bar 1 area 200 SF $40,000.00
Juice Bar Storage 1 area 200 SF $24,000.00
Pro Shop 1 area 600 SF $84,000.00
Pro Shop Storage 1 area 200 SF $24,000.00
Men's Restroom 1 room 250 SF $30,000.00
Women's Restroom 1 room 250 SF $30,000.00
Babysitting 1 room 550 SF $66,000.00
Babysitting Storage 1 room 50 SF $6,000.00
Babysitting Toilet 1 room 50 SF $6,000.00
Game Room 1 room 1,000 SF $120,000.00
COMPONENT TOTAL - PUBLIC SPACES
Building Support
Mechanical Space 1 room 3,500 SF $350,000.00
Electrical 1 room 500 SF $50,000.00
Janitor 1 room 100 SF $10,000.00
Elevator 1 room 100 SF $60,000.00
Elevator Machine 1 room 100 SF $10,000.00
COMPONENT TOTAL - BUILDING SUPPORT
Aquatics Facility
A - 6-Lane x 25 Meter Pool pool 7,500 SF $1,500,000.00
B - 8-Lane x 25 Meter Pool pool 9,000 SF $1,800,000.00
C - 25 Yard x 25 Meter Pool pool 11,500 SF $2,250,000.00
D - Leisure Pool leisure pool 10,000 SF $2,000,000.00
E - Leisure Pool leisure pool 12,600 SF $2,400,000.00
F - Leisure Pool leisure pool 13,000 SF $2,500,000.00
G - 50 Meter Pool competitive 20,200 SF $4,000,000.00
H - 50 Meter Pool with diving Tank competitive 32,500 SF $6,500,000.00
TOTAL COMPONENT - AQUATICS FACILITY
Fitness Area (Weights/Cardio)
A - Small Fitness Center 76 stations 4,500 SF $550,000.00
B - Medium Fitness Center 122 stations 7,300 SF $1,450,000.00
C - Large Fitness Center 194 stations 11,500 SF $2,800,000.00
COMPONENT TOTAL - FITNESS AREA
Aerobics/Dance
A - Multipurpose Room room 1,600 SF $200,000.00
B - Multipurpose Room room 2,800 SF $350,000.00
C - Multipurpose Room room 4,500 SF $550,000.00
COMPONENT TOTAL - AEROBICS/DANCE
Gymnasium
A - One Court Gym gym 9,700 SF $1,200,000.00
B - One Court Gym with Track gym and track 13,500 SF $1,600,000.00
C - Two Court Gym gym 16,500 SF $2,000,000.00
D - Two Court Gym with Track gym and track 21,500 SF $2,500,000.00
E - Three Court Gym gym 23,000 SF $3,000,000.00
F - Three court Gym with Track gym and track 29,000 SF $3,600,000.00
G - Four Court Gym gym 30,000 SF $3,900,000.00
H - Four Court Gym with Track gym and track 37,000 SF $4,600,000.00
TOTAL COMPONENT - GYMNASIUM
Performance Area
A - Performance Center (1000 Seats) court and seating 16,800 SF $2,300,000.00
B - Performance Center (3000 Seats) court and seating 27,000 SF $3,900,000.00
C - Performance Center (3500 Seats) court and seating 44,000 SF $6,800,000.00
COMPONENT TOTAL - PERFORMANCE AREA
Activity Zone
Climbing Wall wall 900 SF $450,000.00
Racquetball Courts court 800 SF $120,000.00
COMPONENT TOTAL - ACTIVITY ZONE
Classrooms
A - Classroom (25 persons_ room 800 SF $100,000.00
B - Classroom (58 persons) room 1,380 SF $175,000.00
C - Classroom (80 persons) room 1,800 SF $200,000.00
D - Classroom (115 persons) room 2,000 SF $220,000.00
E - Classroom (141 persons) room 3,200 SF $350,000.00
Chair and table storage room 500 SF $50,000.00
COMPONENT TOTAL - CLASSROOMS
User Support
A - Locker Room area 3,400 SF $525,000.00
B - Locker Room area 5,600 SF $850,000.00
Facilty Change Room room 140 SF $20,000.00
Control Desk / Issue area 1,200 SF $150,000.00
COMPONENT TOTAL - USER SUPPORT
Administration
A - Offices area 2,300 SF $300,000.00
B - Offices area 3,900 SF $500,000.00
C - Offices area 6,000 SF $750,000.00
COMPONENT TOTAL
Construction Cost of Gross Building Area
A - Component Total (The total of all the rooms you have selected)
B - Building Sitework (5% of the Component Total)
C - Design Contingency (5% of the Component Total)
TOTAL CONSTRUCTION COSTS
Soft Costs
D - Furniture, Fixtures and Equipment (5% of the Total Construction Costs)
E - Professional fees, expenses & misc. (10% of the Total Construction Costs)
F - Other project-related costs (5% of the Total Construction Costs)
G - Project Contingency (5% of the Total Construction Costs)
TOTAL SOFT COSTS
TOTAL PROJECT COST (Add Total Construction and Total Soft Costs together)