9. You are creating a customer database for the Modesto Nuts minor league
baseball team. Draw a project network given the information below. Complete
the forward and backward pass, compute activity slack, and identify the
critical path.
How long will this project take? How sensitive is the network schedule?
Calculate the free slack and total slack for all noncritical activities.
Time
ID Description Predecessor (days)
A Systems design None 2
B Subsystem A design A 1
C Subsystem B design A 1
D Subsystem C design A 1
E Program A B 2
F Program B C 2
G Program C D 2
H Subsystem A test E 1
I Subsystem B test F 1
J Subsystem C test G 1
K Integration H, I,J 2