- W(0) 60 Wall Street – Free of JPMC’s Employees and Technology

- W(1) New Technology Infrastructure Operating Environment W(Delivered to JPMC’s Technology Teams) W(Consolidated 8th and 9th Floor Data Centers)

- W(1.1) Infrastructure Server Installation Plan

· W(1.2) Circuit Cutover Plan

· W(1.3) Market Data W(TIBCO) Test Plan

· W(1.4) Operational Test Plan

· W(1.5) Floor Plan

· W(1.6) Power and Cooling Requirements Document

· W(2) 12th Floor Data Center W(Empty) W(Delivered to Deutsche Bank)

· W(2.1) 12th Floor Data Center W(Facilities Equipment Removed)

· W(2.1.1) Communications Cabinet Removal Plan

· W(2.1.2) HVAC Shutdown Plan

· W(2.1.3) PDU Shutdown Plan

· W(2.1.4) Cable Removal Plan

· W(2.1.5) Furniture Removal Plan

· W(2.1.6) Raised Floor Retrofit Plan

- W(2.2) 12th Floor Data Center W(Technology Infrastructure Removed)

· W(2.2.1) Infrastructure Server Removal Plan

· W(2.2.2) Market Data W(TIBCO) Relocation Plan

· W(2.2.3) PBX Removal Plan

· W(2.2.4) Carrier Removal/Relocation Plan

· W(2.2.5) Network Equipment Removal Plan

· W(2.2.6) Circuit Removal Plan

· W(2.2.7) Final Verification Plan

- W(3) Low Rise, Tenant Floors 1 – 18 W(Delivered to Deutsche Bank) W(Typical For All Tenant Floors, 1 - 47)

· W(3.1) Floor Free Of Tenants

· W(3.1.1) Tenant Migration Plan

· W(3.1.2) Tenant Contingency Plan

· W(3.1.3) New Location Test Plan

· W(3.1.4) Personal Belongings Relocation Plan

· W(3.1.5) Floor “Lock Down” Schedule

· W(3.2) Floor “Broom Clean”

· W(3.2.1) Cable Cross Connect Removal Plan

· W(3.2.2) Riser Cable Removal Plan

· W(3.2.3) Furniture Removal Plan

· W(3.2.4) Debris Removal Schedule

· W(3.3) Floor Free Of Technology

· W(3.3.1) Logical Network Shutdown Plan

· W(3.3.2) Network Equipment Removal Plan

· W(3.3.3) Market Data Equipment Removal Plan

· W(3.3.4) Workstation Equipment Removal Plan

· W(3.3.5) Copier and FAX Machine Removal Plan

· W(3.3.6) Telephone Removal Plan

· W(3.3.7) Direct Circuit Removal Plan