Stakeholder
1
- W(0) 60 Wall Street – Free of JPMC’s Employees and Technology
- W(1) New Technology Infrastructure Operating Environment W(Delivered to JPMC’s Technology Teams) W(Consolidated 8th and 9th Floor Data Centers)
- W(1.1) Infrastructure Server Installation Plan
· W(1.2) Circuit Cutover Plan
· W(1.3) Market Data W(TIBCO) Test Plan
· W(1.4) Operational Test Plan
· W(1.5) Floor Plan
· W(1.6) Power and Cooling Requirements Document
· W(2) 12th Floor Data Center W(Empty) W(Delivered to Deutsche Bank)
· W(2.1) 12th Floor Data Center W(Facilities Equipment Removed)
· W(2.1.1) Communications Cabinet Removal Plan
· W(2.1.2) HVAC Shutdown Plan
· W(2.1.3) PDU Shutdown Plan
· W(2.1.4) Cable Removal Plan
· W(2.1.5) Furniture Removal Plan
· W(2.1.6) Raised Floor Retrofit Plan
- W(2.2) 12th Floor Data Center W(Technology Infrastructure Removed)
· W(2.2.1) Infrastructure Server Removal Plan
· W(2.2.2) Market Data W(TIBCO) Relocation Plan
· W(2.2.3) PBX Removal Plan
· W(2.2.4) Carrier Removal/Relocation Plan
· W(2.2.5) Network Equipment Removal Plan
· W(2.2.6) Circuit Removal Plan
· W(2.2.7) Final Verification Plan
- W(3) Low Rise, Tenant Floors 1 – 18 W(Delivered to Deutsche Bank) W(Typical For All Tenant Floors, 1 - 47)
· W(3.1) Floor Free Of Tenants
· W(3.1.1) Tenant Migration Plan
· W(3.1.2) Tenant Contingency Plan
· W(3.1.3) New Location Test Plan
· W(3.1.4) Personal Belongings Relocation Plan
· W(3.1.5) Floor “Lock Down” Schedule
· W(3.2) Floor “Broom Clean”
· W(3.2.1) Cable Cross Connect Removal Plan
· W(3.2.2) Riser Cable Removal Plan
· W(3.2.3) Furniture Removal Plan
· W(3.2.4) Debris Removal Schedule
· W(3.3) Floor Free Of Technology
· W(3.3.1) Logical Network Shutdown Plan
· W(3.3.2) Network Equipment Removal Plan
· W(3.3.3) Market Data Equipment Removal Plan
· W(3.3.4) Workstation Equipment Removal Plan
· W(3.3.5) Copier and FAX Machine Removal Plan
· W(3.3.6) Telephone Removal Plan
· W(3.3.7) Direct Circuit Removal Plan