| Name | Duration | | | Predecessors | Resources | Notes |
| Mobile app plan | 34 days | | 3/17/16 |
| Project set-up | 7 days | 2/1/16 | 2/9/16 |
| Define project processes | 2 days | 2/1/16 | 2/2/16 | | project manager, product owner |
| Set up working environment | 4 days | 2/3/16 | 2/8/16 | 3 | technical administrator |
| Determine initial sprint velocity | 1 day | 2/9/16 | 2/9/16 | 4 | lead developer |
| Project setup complete | 0 days | 2/9/16 | 2/9/16 | 5 |
| Sprint 1 UI | 6 days | 2/10/16 | 2/17/16 | 2 |
| Sprint 1 plan | 0.5 days | 2/10/16 | 2/10/16 |
| Select sprint 1 user stories | 0.25 days | 2/10/16 | 2/10/16 | | product owner |
| Assign user stories | 0.25 days | 2/10/16 | 2/10/16 | 9 | product owner, lead developer |
| Sprint 1 plan complete | 0 days | 2/10/16 | 2/10/16 | 10 |
| User Interface | 5 days | 2/10/16 | 2/16/16 |
| Design User Interface | 2 days | 2/10/16 | 2/11/16 | | UX developer |
| Build User Interface | 2 days | 2/12/16 | 2/15/16 | 13 | UX developer |
| Test User Interface | 1 day | 2/16/16 | 2/16/16 | 14 | test engineer |
| UAT of UI | 1 day | 2/17/16 | 2/17/16 | 12 | test engineer, product owner |
| Correct Issues From UAT UI | 1 day | 2/26/16 | 2/26/16 | 25 | UX developer |
| Sprint 2 reports | 15 days |
| Sprint 2 plan | 0.5 days | 2/18/16 | 2/18/16 |
| Select sprint 2 user stories | 0.25 days | 2/18/16 | 2/18/16 | | lead developer |
| Assign user stories | 0.25 days | 2/18/16 | 2/18/16 | 19 | lead developer |
| Sprint 1.1 plan complete | 0 days | 2/18/16 | 2/18/16 | 20 |
| Client Specified Reports | 7 days | 2/18/16 | 2/26/16 |
| Design Reports | 2 days | 2/18/16 | 2/19/16 | | reporting developer |
| Build Reports | 2 days | 2/22/16 | 2/23/16 | 23 | reporting developer |
| Test Reports | 2 days | 2/24/16 | 2/25/16 | 24 | test engineer |
| UAT of Reports | 1 day | 2/29/16 | 2/29/16 | 22 | test engineer, product owner |
| Correct Issues From UAT of Reports | 1 day | 3/8/16 | 3/8/16 | | reporting developer |
| Sprint 3 Platform | 7 days | 3/1/16 | 3/9/16 | 17 |
| Sprint 3 plan | 0.5 days | 3/1/16 | 3/1/16 |
| Select sprint 3 user stories | 0.25 days | 3/1/16 | 3/1/16 | | lead developer |
| Assign user stories | 0.25 days | 3/1/16 | 3/1/16 | 30 | lead developer |
| Sprint 3 plan complete | 0 days | 3/1/16 | 3/1/16 | 31 |
| Cross Platform Support | 6 days | 3/1/16 | 3/8/16 |
| Design Cross Platform Support | 2 days | 3/1/16 | 3/2/16 | | technical administrator |
| Build Cross Platform Support | 2 days | 3/3/16 | 3/4/16 | 34 | technical administrator |
| Test Cross Platform Support | 1 day | 3/7/16 | 3/7/16 | 35 | technical administrator |
| UAT of CPS | 1 day | 3/9/16 | 3/9/16 | 33 | technical administrator, test engineer |
| Project End | 2 days | 3/16/16 | 3/17/16 | 44 |
| Obtain Final Client Signoff | 1 day | 3/16/16 | 3/16/16 | | project manager, product owner |
| Provide Project Report Out | 0.5 days | 3/17/16 | 3/17/16 | 48 | project manager, product owner |
| Project End Celebration | 0.5 days | 3/17/16 | 3/17/16 | 49 | project manager, product owner |