Project Execution
Recovered_Sheet1
Summary
| Application | Requested | Previous | Delta | Issues/Risks/Decisions | ||||||||
| AP | $21,026 | $0.00 | -$21,026 | 100% AP decoms dependent on purchase of final eight SAVES @ ~ $1M (UFR). | ||||||||
| BDRE | $108,558 | $0.00 | -$108,558 | Review of this application with customers resulted in a coonversion requirement @ $108.6K + Capital expense (UFR). | ||||||||
| DSE | $126,297 | $100,639.25 | -$25,658 | System under delay for stress testing and code defect remediation. Delay may cause slip past morotorium. | ||||||||
| HOBIC | N/A | $0.00 | $0 | System transferred . No langer a NIS Y2K responsibility. | ||||||||
| MM | $17,675 | $0.00 | -$17,675 | System undergoing migration from M/F host. Y2K Compliance integral part of migration coding. | ||||||||
| NAP | $17,675 | $0.00 | -$17,675 | Decomission dependent on NEMAS acceptance of NAP as front-end processor or utilization of TCP/IP. | ||||||||
| NIC | $122,206 | $105,571.50 | -$16,634 | On Schedule, Under Requested Budget. Certain actuals not posted to date. | ||||||||
| SAVE | $604,179 | $112,773.75 | -$491,405 | In order to meet Y2K Compliance by EOY, SAVE dependent on purchace of eight additional SAVEs @ $1M (UFR). | ||||||||
| TOTAL= | $1,017,615 | $318,984.50 | ||||||||||
| 98 Allocation | $382,000 | $382,000.00 | ||||||||||
| Delta | -$635,615 | $63,015.50 | ||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
| BCWS | $4,655 | $11,780 | $23,332 | $26,173 | $154,454 | $198,992 | $281,197 | $331,507 | $387,998 | $462,708 | $996,077 | $1,017,615 |
| ACWP | $4,655 | $11,780 | $23,920 | $27,330 | $158,826 | $209,292 | $240,259 |
Summary
| Jan | Jan |
| Feb | Feb |
| Mar | Mar |
| Apr | Apr |
| May | May |
| Jun | Jun |
| Jul | Jul |
| Aug | Aug |
| Sep | Sep |
| Oct | Oct |
| Nov | Nov |
| Dec | Dec |
BCWS
ACWP
Cumulative Cost for NIS Y2K (7/14/98)
4655
4655
11780
11780
23332
23919.6
26172.5
27330.1
154454.197142857
158825.63952381
198992.387619048
209292.249047619
281197.435238095
240259.106190476
331507.459047619
387998.459047619
462708.363809524
996076.720952381
1017614.86380952
Roll-Up
| BCWS 6/6/98 | 1998 | |||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 122.5 | 187.5 | 304 | 74.75 | 1148 | 881 | 1206 | 622 | 790 | 732 | 332 | 205 | 6,605 |
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | 4,655 | 7,125.00 | 11,552.00 | 2,840.50 | 43,624.00 | 33,478.00 | 45,828.00 | 23,636.00 | 30,020.00 | 27,816.00 | 12,616.00 | 7,790.00 | 250,981 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 0 | 0 | 0 | 0 | 120 | 176 | 212 | 253 | 294 | 248 | 183 | 174 | 1,660 |
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 6,722.86 | 9,860.19 | 11,877.05 | 14,174.02 | 16,471.00 | 13,893.90 | 10,252.36 | 9,748.14 | 93,000 | |
| Grade | Hours | 0 | 0 | 0 | 0 | 0 | 0 | 70 | 125 | 100 | 290 | 65 | 0 | 650 |
| Rate | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 7,000.00 | 12,500.00 | 10,000.00 | 29,000.00 | 6,500.00 | - 0 | 65,000 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | 120 | 176 | 282 | 378 | 394 | 538 | 248 | 174 | 2,310 |
| $ | - 0 | - 0 | - 0 | - 0 | 6,723 | 9,860 | 18,877 | 26,674 | 26,471 | 42,894 | 16,752 | 9,748 | 158,000 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | 0 | 0 | 0 | 0 | 0 | 1200 | 15000 | 0 | 0 | 1000 | 501000 | 1000 | 519,200 |
| Software | $ | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - 0 |
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | 0 | 0 | 0 | 0 | 77934.84 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 77,935 |
| Travel | $ | 0 | 0 | 0 | 0 | 0 | 0 | 2500 | 0 | 0 | 3000 | 3000 | 3000 | 11,500 |
| $ | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - 0 | |
| Total 1998 | $ | 4,655 | 7,125 | 11,552 | 2,841 | 128,282 | 44,538 | 82,205 | 50,310 | 56,491 | 74,710 | 533,368 | 21,538 | 1,017,615 |
| ACWP 6/2/98 | 1998 | |||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 122.5 | 187.5 | 174 | 89.75 | 784.5 | 963.5 | 638 | 0 | 0 | 0 | 0 | 0 | 2,960 |
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | 4,655 | 7,125.00 | 6,612.00 | 3,410.50 | 29,811.00 | 36,613.00 | 24,244.00 | - 0 | - 0 | - 0 | - 0 | - 0 | 112,471 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 0 | 0 | 0 | 0 | 160 | 160 | 120 | 0 | 0 | 0 | 0 | 0 | 440 |
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 8,963.81 | 8,963.81 | 6,722.86 | - 0 | - 0 | - 0 | - 0 | - 0 | 24,650 | |
| Grade | Hours | 0 | 0 | 130 | 0 | 82.5 | 115 | 0 | 0 | 0 | 0 | 0 | 0 | 328 |
| Rate | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | ||
| $ | - 0 | - 0 | 5,527.60 | - 0 | 3,507.90 | 4,889.80 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 13,925 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | 130 | - 0 | 243 | 275 | 120 | - 0 | - 0 | - 0 | - 0 | - 0 | 768 |
| $ | - 0 | - 0 | 5,528 | - 0 | 12,472 | 13,854 | 6,723 | - 0 | - 0 | - 0 | - 0 | - 0 | 38,576 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - 0 |
| Software | $ | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - 0 |
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | 0 | 0 | 0 | 0 | 89212.83 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 89,213 |
| Travel | $ | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - 0 |
| $ | - 0 | |||||||||||||
| Total 1998 | $ | 4,655 | 7,125 | 12,140 | 3,411 | 131,496 | 50,467 | 30,967 | - 0 | - 0 | - 0 | - 0 | - 0 | 240,259 |
1998 Y2K Budget Revision
&L&D&C&P&R&T
AP
| Budget Description: Update | App Mgr Name | Larry Lafreniere | ||||||||||||
| Application Name: Adjunct Processor (AP) | Project Coord Name | Jeff Tyler | ||||||||||||
| Phase: Decom Assessment | VP Name | Patrice Carroll | ||||||||||||
| Work Request # | Director Name | Bob Laird | ||||||||||||
| Work Request Name | Authorized Dep'ts | 2895 | ||||||||||||
| Project # | Date | 6/7/98 | ||||||||||||
| Company # | ||||||||||||||
| SHL Project Code # | ||||||||||||||
| 1998 | ||||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 32 | 32 | 32 | 96 | |||||||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 1,216.00 | 1,216.00 | 1,216.00 | 3,648 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 16 | 16 | 16 | 16 | 16 | 16 | 96 | ||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 896.38 | 896.38 | 896.38 | 896.38 | 896.38 | 896.38 | 5,378 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 16 | 16 | 16 | 16 | 16 | 16 | 96 |
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 896 | 896 | 896 | 896 | 896 | 5,378 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | 1000 | 1000 | 1000 | 3,000 | |||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | - 0 | ||||||||||||
| Travel | $ | 3000 | 3000 | 3000 | 9,000 | |||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 896 | 896 | 6,112 | 6,112 | 6,112 | 21,026 |
| ACWP | 1998 | |||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | - 0 | ||||||||||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | - 0 | ||||||||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | - 0 | ||||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |||
| BCWS | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 1,793 | 2,689 | 8,802 | 14,914 | 21,026 | ||
| BCWP | 0 | 0 | 0 | 0 | 0 | 0 | ||||||||
| ACWP | 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
AP
| Jan | Jan | Jan |
| Feb | Feb | Feb |
| Mar | Mar | Mar |
| Apr | Apr | Apr |
| May | May | May |
| Jun | Jun | Jun |
| Jul | Jul | Jul |
| Aug | Aug | Aug |
| Sep | Sep | Sep |
| Oct | Oct | Oct |
| Nov | Nov | Nov |
| Dec | Dec | Dec |
BCWS
BCWP
ACWP
Cumulative Costs for AP Y2K Decommission
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
896.380952381
1792.7619047619
2689.1428571429
8801.5238095238
14913.9047619048
21026.2857142857
BDRR
| Budget Description: Update | App Mgr Name | Larry LaFreniere | ||||||||||||
| Application Name:Billing Detail Record Reporting (BDRR) | Project Coord Name | Jeff Tyler | ||||||||||||
| Phase: Conversion Assessment | VP Name | Patrice Carroll | ||||||||||||
| Work Request # | Director Name | Bob Laird | ||||||||||||
| Work Request Name | Authorized Dep'ts | 2895 | ||||||||||||
| Project # | Date | 6/6/98 | ||||||||||||
| Company # | ||||||||||||||
| Project Code # | ||||||||||||||
| 1998 | ||||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 215 | 255 | 340 | 315 | 70 | 10 | 1,205 | ||||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 8,170.00 | 9,690.00 | 12,920.00 | 11,970.00 | 2,660.00 | 380.00 | 45,790 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 50 | 85 | 80 | 85 | 20 | 15 | 335 | ||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 2,801.19 | 4,762.02 | 4,481.90 | 4,762.02 | 1,120.48 | 840.36 | 18,768 | |
| Grade | Hours | 70 | 125 | 100 | 130 | 15 | 0 | 440 | ||||||
| Rate | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 7,000.00 | 12,500.00 | 10,000.00 | 13,000.00 | 1,500.00 | - 0 | 44,000 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 120 | 210 | 180 | 215 | 35 | 15 | 775 |
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 9,801 | 17,262 | 14,482 | 17,762 | 2,620 | 840 | 62,768 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | - 0 | ||||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 17,971 | 26,952 | 27,402 | 29,732 | 5,280 | 1,220 | 108,558 |
| ACWP | 1998 | |||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | - 0 | ||||||||||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | - 0 | ||||||||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | - 0 | ||||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |||
| BCWS | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 17,971 | 44,923 | 72,325 | 102,057 | 107,338 | 108,558 | ||
| BCWP | 0 | 0 | 0 | 0 | 0 | 0 | ||||||||
| ACWP | 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
Jeff Tyler:
Est cost of shipping and hanling of stratus boxes for turn-in credit.
Jeff Tyler:
Est cost of shipping and hanling of stratus boxes for turn-in credit.
Jeff Tyler:
Est cost of shipping and hanling of stratus boxes for turn-in credit.
Jeff Tyler:
Est. cost of trips to two sites for unexpected problems.
Jeff Tyler:
Est. cost of trips to two sites for unexpected problems.
Jeff Tyler:
Est. cost of trips to two sites for unexpected problems.
BDRR
| Jan | Jan | Jan |
| Feb | Feb | Feb |
| Mar | Mar | Mar |
| Apr | Apr | Apr |
| May | May | May |
| Jun | Jun | Jun |
| Jul | Jul | Jul |
| Aug | Aug | Aug |
| Sep | Sep | Sep |
| Oct | Oct | Oct |
| Nov | Nov | Nov |
| Dec | Dec | Dec |
BCWS
BCWP
ACWP
Cumulative Cost Of BDR Y2K Conversion
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
17971.1904761905
44923.2142857143
72325.119047619
102057.142857143
107337.619047619
108557.976190476
DSE
| Budget Description: 1998 Y2K Update | App Mgr Name | Larry Lafreniere | ||||||||||||
| Application Name: ISP\NIS\DSE | Project Coord Name | Jeff Tyler | ||||||||||||
| Phase: Conversion Analysis | VP Name | Patrice Carroll | ||||||||||||
| Work Request # | 120743 | Director Name | Open | |||||||||||
| Work Request Name | Authorized Dep'ts | 2895 | ||||||||||||
| Project # | Date | 5/7/98 | ||||||||||||
| Company # | ||||||||||||||
| SHL Project Code # | ||||||||||||||
| 1998 | ||||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 29 | 37.75 | 220.5 | 23 | 413 | 66 | 76 | 187 | 270 | 205 | 50 | 23 | 1,600 |
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | 1,102 | 1,434.50 | 8,379.00 | 874.00 | 15,694.00 | 2,508.00 | 2,888.00 | 7,106.00 | 10,260.00 | 7,790.00 | 1,900.00 | 874.00 | 60,810 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 40 | 48 | 38 | 40 | 70 | 35 | 35 | 11 | 317 | ||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 2,240.95 | 2,689.14 | 2,128.90 | 2,240.95 | 3,921.67 | 1,960.83 | 1,960.83 | 616.26 | 17,760 | |
| Grade | Hours | 160 | 50 | 210 | ||||||||||
| Rate | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 16,000.00 | 5,000.00 | - 0 | 21,000 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | 40 | 48 | 38 | 40 | 70 | 195 | 85 | 11 | 527 |
| $ | - 0 | - 0 | - 0 | - 0 | 2,241 | 2,689 | 2,129 | 2,241 | 3,922 | 17,961 | 6,961 | 616 | 38,760 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | 26,727.88 | 26,728 | |||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | 1,102 | 1,435 | 8,379 | 874 | 44,663 | 5,197 | 5,017 | 9,347 | 14,182 | 25,751 | 8,861 | 1,490 | 126,297 |
| Ass/Req | Analysis | Stress Test Delay (DP&D) | Coding | Test | FVO | Roll-Out | ||||||||
| 93.00% | 79.00% | 74.00% | 58.00% | 9.00% | 8.00% | |||||||||
| 1,024.86 | 2,158.12 | 8,358.58 | 8,865.50 | 12,885.15 | 13,300.92 | |||||||||
| 1998 | ||||||||||||||
| ACWP | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | |
| Internal (MCI Staff) | Hours | 29 | 37.75 | 90.5 | 23 | 15 | 10 | 60.5 | 266 | |||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | 1,102 | 1,434.50 | 3,439.00 | 874.00 | 570.00 | 380.00 | 2,299.00 | - 0 | - 0 | - 0 | - 0 | - 0 | 10,099 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 40 | 43 | 30 | 113 | |||||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 2,240.95 | 2,409.02 | 1,680.71 | - 0 | - 0 | - 0 | - 0 | - 0 | 6,331 | |
| Grade | Hours | 130 | 130 | |||||||||||
| Rate | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | ||
| $ | - 0 | - 0 | 5,527.60 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 5,528 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | 130 | - 0 | 40 | 43 | 30 | - 0 | - 0 | - 0 | - 0 | - 0 | 243 |
| $ | - 0 | - 0 | 5,528 | - 0 | 2,241 | 2,409 | 1,681 | - 0 | - 0 | - 0 | - 0 | - 0 | 11,858 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | 27,763.06 | 27,763 | |||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | 1,102 | 1,435 | 8,967 | 874 | 30,574 | 2,789 | 3,980 | - 0 | - 0 | - 0 | - 0 | - 0 | 49,720 |
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |||
| BCWS | 1102 | 2,537 | 10,916 | 11,790 | 56,452 | 61,649 | 66,666 | 76,013 | 90,195 | 115,946 | 124,807 | 126,297 | ||
| BCWP | 1,025 | 3,183 | 11,542 | 20,407 | 33,292 | 35,052 | ||||||||
| ACWP | 1102 | 2,537 | 11,503 | 12,377 | 42,951 | 45,740 |
&L&D&C&A&R&T
DSE
| Jan | Jan | Jan |
| Feb | Feb | Feb |
| Mar | Mar | Mar |
| Apr | Apr | Apr |
| May | May | May |
| Jun | Jun | Jun |
| Jul | Jul | Jul |
| Aug | Aug | Aug |
| Sep | Sep | Sep |
| Oct | Oct | Oct |
| Nov | Nov | Nov |
| Dec | Dec | Dec |
BCWS
BCWP
ACWP
Cumulative Costs for DSE Y2K (7/14/98)
1102
1024.86
1102
2536.5
3182.975
2536.5
10915.5
11541.55
11503.1
11789.5
20407.045
12377.1
56452.3323809524
33292.1949142857
42951.1123809524
61649.4752380952
35051.5662571429
45740.1361904762
66666.38
76013.3323809524
90194.999047619
115945.832380952
124806.665714286
126296.927619048
MM
| Budget Description: 1998 Y2K Update | App Mgr Name | Larry LaFreniere | ||||||||||||
| Application Name: Match Merge (MM) | Project Coord Name | Jeff Tyler | ||||||||||||
| Phase: Decom Assessment | VP Name | Patrice Carroll | ||||||||||||
| Work Request # | Director Name | Bob Laird | ||||||||||||
| Work Request Name | Authorized Dep'ts | 2895 | ||||||||||||
| Project # | Date | 6/6/98 | ||||||||||||
| Company # | ||||||||||||||
| SHL Project Code # | ||||||||||||||
| 1998 | ||||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 50 | 50 | 50 | 50 | 50 | 50 | 300 | ||||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 1,900.00 | 1,900.00 | 1,900.00 | 1,900.00 | 1,900.00 | 1,900.00 | 11,400 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 16 | 16 | 16 | 16 | 16 | 16 | 16 | 112 | |||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | 896.38 | 896.38 | 896.38 | 896.38 | 896.38 | 896.38 | 896.38 | 6,275 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | - 0 | 16 | 16 | 16 | 16 | 16 | 16 | 16 | 112 |
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 896 | 896 | 896 | 896 | 896 | 896 | 6,275 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | - 0 | ||||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 2,796 | 2,796 | 2,796 | 2,796 | 2,796 | 2,796 | 17,675 |
| ACWP | 1998 | |||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | - 0 | ||||||||||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | - 0 | ||||||||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | - 0 | ||||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |||
| BCWS | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 3,693 | 6,489 | 9,286 | 12,082 | 14,878 | 17,675 | ||
| BCWP | 0 | 0 | 0 | 0 | 0 | 0 | ||||||||
| ACWP | 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
Jeff Tyler:
Lack of tester will require product testing in ICCA with a contracted teser.
Jeff Tyler:
Lack of tester will require product testing in ICCA with a contracted teser.
MM
| Jan | Jan | Jan |
| Feb | Feb | Feb |
| Mar | Mar | Mar |
| Apr | Apr | Apr |
| May | May | May |
| Jun | Jun | Jun |
| Jul | Jul | Jul |
| Aug | Aug | Aug |
| Sep | Sep | Sep |
| Oct | Oct | Oct |
| Nov | Nov | Nov |
| Dec | Dec | Dec |
BCWS
BCWP
ACWP
Cumulative Cost Of Match Merge Y2K Conversion
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
896.380952381
0
0
3692.7619047619
6489.1428571429
9285.5238095238
12081.9047619048
14878.2857142857
17674.6666666667
NAP
| Budget Description: 1998 Y2K Update | App Mgr Name | Larry LaFreniere | ||||||||||||
| Application Name: NIC Adjunct Processor (NAP) | Project Coord Name | Jeff Tyler | ||||||||||||
| Phase: Decom Assessment | VP Name | Patrice Carroll | ||||||||||||
| Work Request # | Director Name | Bob Laird | ||||||||||||
| Work Request Name | Authorized Dep'ts | 2895 | ||||||||||||
| Project # | Date | 6/6/98 | ||||||||||||
| Company # | ||||||||||||||
| Project Code # | ||||||||||||||
| 1998 | ||||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 50 | 50 | 50 | 50 | 50 | 50 | 300 | ||||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 1,900.00 | 1,900.00 | 1,900.00 | 1,900.00 | 1,900.00 | 1,900.00 | 11,400 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 16 | 16 | 16 | 16 | 16 | 16 | 16 | 112 | |||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | 896.38 | 896.38 | 896.38 | 896.38 | 896.38 | 896.38 | 896.38 | 6,275 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | - 0 | 16 | 16 | 16 | 16 | 16 | 16 | 16 | 112 |
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 896 | 896 | 896 | 896 | 896 | 896 | 6,275 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | - 0 | ||||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 2,796 | 2,796 | 2,796 | 2,796 | 2,796 | 2,796 | 17,675 |
| ACWP | 1998 | |||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | - 0 | ||||||||||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | - 0 | ||||||||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | - 0 | ||||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |||
| BCWS | - 0 | - 0 | - 0 | - 0 | - 0 | 896 | 3,693 | 6,489 | 9,286 | 12,082 | 14,878 | 17,675 | ||
| BCWP | 0 | 0 | 0 | 0 | 0 | 0 | ||||||||
| ACWP | 0 | - 0 | - 0 | - 0 | - 0 | - 0 |
NAP
| Jan | Jan | Jan |
| Feb | Feb | Feb |
| Mar | Mar | Mar |
| Apr | Apr | Apr |
| May | May | May |
| Jun | Jun | Jun |
| Jul | Jul | Jul |
| Aug | Aug | Aug |
| Sep | Sep | Sep |
| Oct | Oct | Oct |
| Nov | Nov | Nov |
| Dec | Dec | Dec |
BCWS
BCWP
ACWP
Cumulative Cost Of NAP Y2K Claimed Compliance
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
896.380952381
0
0
3692.7619047619
6489.1428571429
9285.5238095238
12081.9047619048
14878.2857142857
17674.6666666667
NIC
| Budget Description: 1998 Y2K Update | App Mgr Name | Larry LaFreniere | ||||||||||||
| Application Name:Network Information Concentrator (NIC) | Project Coord Name | Jeff Tyler | ||||||||||||
| Phase: Conversion Analysis | VP Name | Patrice Carroll | ||||||||||||
| Work Request # | 120742 | Director Name | Bob Laird | |||||||||||
| Work Request Name | Authorized Dep'ts | 2895 | ||||||||||||
| Project # | Date | 6/6/98 | ||||||||||||
| Company # | ||||||||||||||
| SHL Project Code # | ||||||||||||||
| 1998 | ||||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 38 | 41.5 | 44 | 29.5 | 413 | 413 | 413 | 40 | 40 | 40 | 40 | 0 | 1,552 |
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | 1,444 | 1,577.00 | 1,672.00 | 1,121.00 | 15,694.00 | 15,694.00 | 15,694.00 | 1,520.00 | 1,520.00 | 1,520.00 | 1,520.00 | - 0 | 58,976 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 40 | 48 | 38 | 40 | 48 | 40 | 40 | 50 | 344 | ||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 2,240.95 | 2,689.14 | 2,128.90 | 2,240.95 | 2,689.14 | 2,240.95 | 2,240.95 | 2,801.19 | 19,272 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | 40 | 48 | 38 | 40 | 48 | 40 | 40 | 50 | 344 |
| $ | - 0 | - 0 | - 0 | - 0 | 2,241 | 2,689 | 2,129 | 2,241 | 2,689 | 2,241 | 2,241 | 2,801 | 19,272 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | 15000 | 15,000 | |||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | 27,457.32 | 27,457 | |||||||||||
| Travel | $ | 1500 | 1,500 | |||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | 1,444 | 1,577 | 1,672 | 1,121 | 45,392 | 18,383 | 34,323 | 3,761 | 4,209 | 3,761 | 3,761 | 2,801 | 122,206 |
| Ass/Req | Analysis | Coding | Test | FVO | Roll-Out | |||||||||
| 90.00% | 81.00% | 88.00% | 77.00% | 56.00% | 17.00% | |||||||||
| 1,299.60 | 2,576.97 | 2,770.96 | 3,634.13 | 29,053.80 | 32,178.94 | |||||||||
| ACWP | 1998 | |||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 38 | 41.5 | 44 | 44.5 | 89.25 | 147 | 64 | 468 | |||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | 1,444 | 1,577.00 | 1,672.00 | 1,691.00 | 3,391.50 | 5,586.00 | 2,432.00 | - 0 | - 0 | - 0 | - 0 | - 0 | 17,794 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 60 | 57 | 45 | 162 | |||||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 3,361.43 | 3,193.36 | 2,521.07 | - 0 | - 0 | - 0 | - 0 | - 0 | 9,076 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | 60 | 57 | 45 | - 0 | - 0 | - 0 | - 0 | - 0 | 162 |
| $ | - 0 | - 0 | - 0 | - 0 | 3,361 | 3,193 | 2,521 | - 0 | - 0 | - 0 | - 0 | - 0 | 9,076 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | 28,538.09 | 28,538 | |||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | 1,444 | 1,577 | 1,672 | 1,691 | 35,291 | 8,779 | 4,953 | - 0 | - 0 | - 0 | - 0 | - 0 | 55,407 |
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |||
| BCWS | 1,444 | 3,021 | 4,693 | 5,814 | 51,206 | 69,589 | 103,912 | 107,673 | 111,882 | 115,643 | 119,404 | 122,206 | ||
| BCWP | 1,300 | 3,877 | 5,348 | 6,405 | 32,688 | 61,233 | ||||||||
| ACWP | 1,444 | 3,021 | 4,693 | 6,384 | 41,675 | 50,454 |
&L&D&C&A&R&T
NIC
| Jan | Jan | Jan |
| Feb | Feb | Feb |
| Mar | Mar | Mar |
| Apr | Apr | Apr |
| May | May | May |
| Jun | Jun | Jun |
| Jul | Jul | Jul |
| Aug | Aug | Aug |
| Sep | Sep | Sep |
| Oct | Oct | Oct |
| Nov | Nov | Nov |
| Dec | Dec | Dec |
BCWS
BCWP
ACWP
Cumulative Costs for NIC Y2K (7/14/98)
1444
1299.6
1444
3021
3876.57
3021
4693
5347.93
4693
5814
6405.09
6384
51206.2723809524
32687.9325333333
41675.0185714286
69589.4152380952
61232.739352381
50454.3757142857
103912.32
107673.272380952
111882.415238095
115643.367619048
119404.32
122205.51047619
SAVE
| Budget Description: 1998 Y2K Update | App Mgr Name | Larry LaFreniere | ||||||||||||
| Application Name:Storage And Verification Element (SAVE) | Project Coord Name | Jeff Tyler | ||||||||||||
| Phase: Conversion Design & Planning | VP Name | Patrice Carroll | ||||||||||||
| Work Request # | 120741 | Director Name | Bob Laird | |||||||||||
| Work Request Name | Authorized Dep'ts | 2895 | ||||||||||||
| Project # | Date | 6/6//1998 | ||||||||||||
| Company # | ||||||||||||||
| Project Code # | ||||||||||||||
| 1998 | ||||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 55.5 | 108.25 | 39.5 | 22.25 | 322 | 402 | 402 | 40 | 40 | 40 | 40 | 40 | 1,552 |
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | 2,109 | 4,113.50 | 1,501.00 | 845.50 | 12,236.00 | 15,276.00 | 15,276.00 | 1,520.00 | 1,520.00 | 1,520.00 | 1,520.00 | 1,520.00 | 58,957 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 40 | 48 | 38 | 40 | 48 | 40 | 40 | 50 | 344 | ||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 2,240.95 | 2,689.14 | 2,128.90 | 2,240.95 | 2,689.14 | 2,240.95 | 2,240.95 | 2,801.19 | 19,272 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | 40 | 48 | 38 | 40 | 48 | 40 | 40 | 50 | 344 |
| $ | - 0 | - 0 | - 0 | - 0 | 2,241 | 2,689 | 2,129 | 2,241 | 2,689 | 2,241 | 2,241 | 2,801 | 19,272 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | 1200 | 500,000 | 501,200 | ||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | 23,749.64 | 23,750 | |||||||||||
| Travel | $ | 1000 | 1,000 | |||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | 2,109 | 4,114 | 1,501 | 846 | 38,227 | 19,165 | 18,405 | 3,761 | 4,209 | 3,761 | 503,761 | 4,321 | 604,179 |
| Ass/Req | Analysis | Design | Coding | Test | FVO | Roll-Out | ||||||||
| 100.0% | 87.0% | 78.0% | 79.0% | 71.0% | 11.0% | |||||||||
| 2,109.00 | 5,687.75 | 1,170.78 | 667.95 | 27,140.88 | 2,108.17 | |||||||||
| ACWP | 1998 | |||||||||||||
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total | ||
| Internal (MCI Staff) | Hours | 55.5 | 108.25 | 39.5 | 22.25 | 680.25 | 806.5 | 513.5 | 2,226 | |||||
| Rate | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | 38 | ||
| $ | 2,109 | 4,113.50 | 1,501.00 | 845.50 | 25,849.50 | 30,647.00 | 19,513.00 | - 0 | - 0 | - 0 | - 0 | - 0 | 84,579 | |
| External (Contractors) | ||||||||||||||
| Grade | Hours | 60 | 60 | 45 | 165 | |||||||||
| Rate | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | 56 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 3,361.43 | 3,361.43 | 2,521.07 | - 0 | - 0 | - 0 | - 0 | - 0 | 9,244 | |
| Grade | Hours | 82.5 | 115 | 198 | ||||||||||
| Rate | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | 43 | ||
| $ | - 0 | - 0 | - 0 | - 0 | 3,507.90 | 4,889.80 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 8,398 | |
| Grade | Hours | - 0 | ||||||||||||
| Rate | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |||
| $ | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | |
| Total Contractor | Hours | - 0 | - 0 | - 0 | - 0 | 143 | 175 | 45 | - 0 | - 0 | - 0 | - 0 | - 0 | 363 |
| $ | - 0 | - 0 | - 0 | - 0 | 6,869 | 8,251 | 2,521 | - 0 | - 0 | - 0 | - 0 | - 0 | 17,642 | |
| Capital (Detail Items) | ||||||||||||||
| Hardware | $ | - 0 | ||||||||||||
| Software | $ | - 0 | ||||||||||||
| Other Costs (Detail Items) | ||||||||||||||
| Team/Factory Costs | $ | 32,911.68 | 32,912 | |||||||||||
| Travel | $ | - 0 | ||||||||||||
| $ | - 0 | |||||||||||||
| Total 1998 | $ | 2,109 | 4,114 | 1,501 | 846 | 65,631 | 38,898 | 22,034 | - 0 | - 0 | - 0 | - 0 | - 0 | 135,132 |
| Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |||
| BCWS | 2,109 | 6,223 | 7,724 | 8,569 | 46,796 | 65,961 | 84,366 | 88,127 | 92,336 | 96,097 | 599,858 | 604,179 | ||
| BCWP | 0 | 5,688 | 6,859 | 7,526 | 34,667 | 36,776 | ||||||||
| ACWP | 2109 | 6,223 | 7,724 | 8,569 | 74,200 | 113,098 |
Jeff Tyler: The NAP box in Perryman needs to have an OS upgrade to VOS 12.4. This is necessary for Y2K compliance, and to stay current with the kit revision level (build 08). We have been requested to fund Sheldons trip to Perryman for this activity. The costs should not exceed $1200, and this should be billable to the Y2K funds.
The maintenance is necessary before May 29, and is requested for a Sunday afternoon due to the behavior patterns of the NAP.
Jeff Tyler:
Estimated cost of memory repacement for NIC testing box canibalized to support Lab in Y2K testing.
&L&D&C&A&R&T
SAVE
BCWS
BCWP
ACWP
Cumulative Cost of SAVE Y2K (7/14/98)
Risk Assessment
| ID | Risk Event | Probability | Impact | Response | Priority | Resonsibility |
| NIS Adjunct Processor (AP) Y2K Project | ||||||
| 1 | Decom by 12/31/98 | Med | Hi | 1 | Edie Smith | |
| 2 | Use as Tape Drive for NIC | Hi | Low | 2 | Jeff Tyler | |
| 3 | Get Exemption | HI | Low | 3 | Jeff Tyler | |
| NIS Billing Detail Record Reporting (BDRR) Y2K Project | ||||||
| 1 | Not decom'd | HI | HI | (a) Get exmption (b) Xfer to DSS (c) Claim Compliance (d) Convert | 1 | |
| 2 | Get exmption | HI | Low | 5 | Jeff Tyler | |
| 3 | Transfer to DSS | Low | HI | 3 | Bob Laird | |
| 4 | Claim Compliance | Low-Med | HI | 4 | Jeff Tyler | |
| 5 | Convert | HI | Med | Ramp up staffing ASAP | 2 | Larry Lafreniere |
| NIS Data Server for EVS (DSE) Y2K Project | ||||||
| 1 | Coding Slip | Med | Hi | Request Exemption | 2 | Jeff Tyler |
| 2 | No test capability | Hi | Hi | ICCA product test | 1 | John Anderson |
| 3 | No PM | Med | Hi | Job Req. | 3 | John Anderson |
| NIS Match Merge (MM) Y2K Project | ||||||
| 1 | Not decom'd | HI | HI | Exemption | 2 | Jeff Tyler |
| 2 | Host migration delays | HI | HI | Requires Assesment | 1 | John Libermann |
| 3 | Get exmption | HI | Low | 3 | Jeff Tyler | |
| NIS NIC Adjunct Processor (NAP) Y2K Project | ||||||
| 1 | Not decom'd by 12/31/98 | Med | Low | (a) Submit exception. (b) Xfer to NEMAS as front end processor. (c) See if TEFAC can replace it. (d) Institute TCP/IP with NEMAS. (e) Resort to Claimed Compliance. | 1 | Bob Laird |
| 2 | Receive exmption | Med-HI | Low | 2 | Jeff Tyler | |
| 3 | Transfer to NEMAS | Low | HI | If not then goto TEFAC | 3 | Bob Laird |
| 4 | TEFEC to replace need for NAP | Med-Low | HI | If not then goto TCP/IP | 4 | Kim Greer |
| 5 | Institute TCP/IP with NEMAS | Med-HI | Med | If not then goto Claimed Compliance | 5 | Dave Weis |
| 6 | Go Claimed Compliance | Low | Med | If not then retire | 6 | Jeff Tyler |
| 7 | Retire | Low | Low | Escalate Business Case | 7 | Bob Laird |
| NIS Storage And Verification Element (SAVE) Y2K Project | ||||||
| 1 | Not Compliant by 12/31/98 | HI | HI | Purchase remaining eight SAVE boxes | 1 | Bob Laird |
| 2 | RolLowut by Moratorium | Med | Med | Apply for exemption | 2 | Jeff Tyler |
Jeff Tyler:
Estimated cost of O/S upgrade
Jeff Tyler:
Includes $6K in change controls not planned for