exam.docx

Which quality technique was developed to demonstrate what businessmen called the "80-20 Rule" - meaning that 80% of problems originate from 20% of various causes?

Select one:

a.

A flowchart

b.

A Gantt chart

c.

A control chart

d.

A Pareto chart

Clear my choice

Question 2

Not yet answered

Points out of 1.0

Flag question

Question text

When we are designing and documenting complex processes, we often create a(n) ________ to help ensure that we are designing a quality product.

Select one:

a.

A work breakdown schedule

b.

A Pareto diagram

c.

A flowchart

d.

A Gantt chart

Clear my choice

Question 3

Not yet answered

Points out of 1.0

Flag question

Question text

The best project managers allot about twice as much time to _____ than do less-skilled project managers.

Select one:

a.

Project communication

b.

Keeping project plans/documents updated

c.

The user acceptance testing phase

d.

The planning phase

Clear my choice

Question 4

Not yet answered

Points out of 1.0

Flag question

Question text

Who should be invited to a project close-out meeting?

Select one:

a.

The project team members

b.

The project champion

c.

The project stakeholders

d.

All of the above

e.

Only A and B

Clear my choice

Question 5

Not yet answered

Points out of 1.0

Flag question

Question text

Resource leveling:

Select one:

a.

Creates a smoother distribution of work usage

b.

Resolves resource conflicts by delaying tasks

c.

Is a network analysis technique

d.

All of the above

e.

Only A and C

Clear my choice

Question 6

Answer saved

Points out of 1.0

Flag question

Question text

Which of the following is the value of completed project work, as of a given point in time?

Select one:

a.

Actual value

b.

Earned value

c.

Planned value

d.

None of the above

Clear my choice

Question 7

Answer saved

Points out of 1.0

Flag question

Question text

The purpose of a _________ is to keep stakeholders informed, to document when and how they want to receive information (what format), and to identify who will be sending 'what' information to 'whom'.

Select one:

a.

Communications register

b.

Knowledge matrix

c.

Communications management plan

d.

Information distribution plan

Clear my choice

Question 8

Answer saved

Points out of 1.0

Flag question

Question text

The most common reason for closing a project is project _______.

Select one:

a.

Disjunction

b.

Extinction

c.

Integration

d.

Obsolescence

Clear my choice

Question 9

Answer saved

Points out of 1.0

Flag question

Question text

A graphical rendering of some process that shows the flow of, and relationships among, process steps is known as:

Select one:

a.

An Ishikawa diagram

b.

A fishbone diagram

c.

A flowchart

d.

A hierarchical chart

Clear my choice

Question 10

Answer saved

Points out of 1.0

Flag question

Question text

When someone is motivated to do something for their own enjoyment or sense of accomplishment, we call this:

Select one:

a.

Extrinsic motivation

b.

Intrinsic motivation

c.

The hygiene theory of motivation

d.

Esteem-driven motivation

Clear my choice

Question 11

Answer saved

Points out of 1.0

Flag question

Question text

High project management maturity results in ________ direct costs of project management.

Select one:

a.

Noticeably higher

b.

Somewhat higher

c.

Lower

d.

About the same

Clear my choice

Question 12

Not yet answered

Points out of 1.0

Flag question

Question text

The following diagram helps pinpoint:

Select one:

a.

Analysis of a project's current status

b.

The causes and effects of a problem

c.

Work breakdown for change control

d.

A problem check sheet

Clear my choice

Question 13

Answer saved

Points out of 1.0

Flag question

Question text

At some point, 'real or live' data will have to be used in the final stage of project testing.

Select one:

a.

True

b.

False

Clear my choice

Question 14

Answer saved

Points out of 1.0

Flag question

Question text

The following is an example of a(n):

Select one:

a.

Work histogram

b.

Pareto chart

c.

Ishikawa diagram

d.

Gantt chart

Clear my choice

Question 15

Not yet answered

Points out of 1.0

Flag question

Question text

When a project manager calculates how well a project is doing by comparing actual values against the baseline that was set back in the planning phase, we call this:

Select one:

a.

Earned value management

b.

Budget management

c.

Cost-benefit management

d.

Scope management

Clear my choice

Question 16

Not yet answered

Points out of 1.0

Flag question

Question text

Which of the following is not a best practice for project managers?

Select one:

a.

Managing issues and risks

b.

Managing procurement

c.

Eliminating stakeholder competition

d.

Meeting the budget baselines for the project

Clear my choice

Question 17

Not yet answered

Points out of 1.0

Flag question

Question text

Some risks have a positive impact on the project.

Select one:

a.

True

b.

False

Clear my choice

Question 18

Not yet answered

Points out of 1.0

Flag question

Question text

Ignoring a project's stakeholders can:

Select one:

a.

Allow the project manager to focus on project execution

b.

Streamline the project's progress

c.

Help the project team focus without outside interference or influence

d.

All of the above

e.

None of the above

Clear my choice

Question 19

Not yet answered

Points out of 1.0

Flag question

Question text

The main point of a project change request is:

Select one:

a.

To re-establish the project baseline

b.

To ensure the sponsor/stakeholders approve the change

c.

To avoid unplanned scope creep

d.

All of the above

Clear my choice

Question 20

Not yet answered

Points out of 1.0

Flag question

Question text

Which of the following would the project manager want to capture at a "lessons learned" meeting?

Select one:

a.

What worked well

b.

What surprises the project team encountered

c.

Whether the project achieved its goals

d.

All of the above

e.

Only A and C

Clear my choice

Question 21

Not yet answered

Points out of 1.0

Flag question

Question text

The testing report is a vital communication tool in the project execution and monitoring/controlling phases.

Select one:

a.

True

b.

False

Clear my choice

Question 22

Not yet answered

Points out of 1.0

Flag question

Question text

The following image is known as a(n):

Select one:

a.

Budget completion graph

b.

Earned value chart

c.

Cost variance graph

d.

None of the above

Clear my choice

Question 23

Not yet answered

Points out of 1.0

Flag question

Question text

Which statement is true?

Select one:

a.

Most of the traits of the best project managers can be learned.

b.

Most organizations find it easy to practice good project management practices.

c.

Companies with high maturity levels spend more money on project management.

d.

A project "gauge" is the name for criteria that's used to determine the degree to which an outcome is achieved.

Clear my choice

Question 24

Not yet answered

Points out of 1.0

Flag question

Question text

When quality is planned, designed, and built in, as opposed to looking for defects during inspection, we call this:

Select one:

a.

Quality proactivity

b.

Prevention over inspection

c.

Defect prevention

d.

Proactive prevention

Clear my choice

Question 25

Answer saved

Points out of 1.0

Flag question

Question text

__________ is a project technique that integrates time, scope and cost data to perform performance measurement.

Select one:

a.

Forecasting

b.

Earned value management

c.

Baseline control

d.

Budget management

Clear my choice

Question 26

Not yet answered

Points out of 1.0

Flag question

Question text

The primary reason that the testing phase is compromised is:

Select one:

a.

Insufficient funds left in the budget

b.

Insufficient hours left on the project (lack of time)

c.

Poor quality control

d.

All of the above

e.

Only A and B

Clear my choice

Question 27

Not yet answered

Points out of 1.0

Flag question

Question text

Quality should always be determined by:

Select one:

a.

The project manager

b.

The person actually creating the project deliverables

c.

The end user

d.

The project sponsor

Clear my choice

Question 28

Not yet answered

Points out of 1.0

Flag question

Question text

Which of the following is not a true statement?

Select one:

a.

The project manager should include tasks in the WBS for project closing activities.

b.

The closing activities should have resource(s) assigned to them.

c.

The project manager handles all closing activities.

d.

These are all true statements

Clear my choice

Question 29

Not yet answered

Points out of 1.0

Flag question

Question text

Maria's project has expended $10,000 actual cost to date. The earned value = $12,000. What is its cost variance?

Select one:

a.

$2,000

b.

($2,000)

c.

83%

d.

1.2

Clear my choice

Question 30

Not yet answered

Points out of 1.0

Flag question

Question text

Which of the following is an output of the executing phase of the project management lifecycle?

Select one:

a.

The risk probability matrix

b.

The communications plan

c.

Project management plan updates

d.

The work breakdown structure

Clear my choice

Question 31

Not yet answered

Points out of 1.0

Flag question

Question text

What quality technique uses a collection of data points to display values for two variables in a graphic image, as collected from a set of data (such as defects, causes, etc.)?

Select one:

a.

A scatter diagram

b.

A correlation analysis

c.

A parallel analysis

d.

A quality matrix

Clear my choice

Question 32

Not yet answered

Points out of 1.0

Flag question

Question text

Which statement is true?

Select one:

a.

In general, the executing phase is the longest of the project management lifecycle phases.

b.

Sometimes a project manager needs to break organizational rules in order to complete a project successfully.

c.

An "issue" is a matter that could impede the success the project.

d.

All of the above are true.

Clear my choice

Question 33

Not yet answered

Points out of 1.0

Flag question

Question text

An alpha project manager is one who:

Select one:

a.

Has the most seniority among the project managers in an organization

b.

Is experienced enough to be responsible for program and portfolio management

c.

Is considered to be in the top 2% of project managers in terms of performance

d.

Is consistently the most aggressive project manager in terms of handling stakeholders

Clear my choice

Question 34

Not yet answered

Points out of 1.0

Flag question

Question text

We learned that the best project managers send ________ e-mails per day and spend ____ time in meetings than typical project managers.

Select one:

a.

more, more

b.

fewer, more

c.

fewer, less

d.

more, less

Clear my choice

Question 35

Not yet answered

Points out of 1.0

Flag question

Question text

Which of the following is NOT a trait of the Manager X motivation theory?

Select one:

a.

Managers must control workers

b.

Workers seek responsibility

c.

Workers seek security

d.

Employees try to avoid work

Clear my choice

Question 36

Not yet answered

Points out of 1.0

Flag question

Question text

Maturity models are a way of benchmarking organizational processes used in many different industries.

Select one:

a.

True

b.

False

Clear my choice

Question 37

Not yet answered

Points out of 1.0

Flag question

Question text

Areas of focus in the monitoring and controlling phase include:

Select one:

a.

Scope management

b.

Time Management

c.

Quality management

d.

All of the above

e.

Only A and B

Clear my choice

Question 38

Not yet answered

Points out of 1.0

Flag question

Question text

The following image is an example of a(n):

Select one:

a.

Risk register

b.

Communications log

c.

Issues log

d.

Status matrix

Clear my choice

Question 39

Not yet answered

Points out of 1.0

Flag question

Question text

The primary technique that a project manager would use for the monitoring and control phase are:

Select one:

a.

Decision-making

b.

Expert judgement

c.

Data analysis

d.

Meetings

e.

All of the above

Clear my choice

Question 40

Not yet answered

Points out of 1.0

Flag question

Question text

When testing a finished software system, we can be assured that if it works in testing, it will work in production.

Select one:

a.

True

b.

False

Clear my choice

Question 41

Not yet answered

Points out of 1.0

Flag question

Question text

The best or "alpha" project managers do not enjoy their work more than their counterparts, but they generally get paid more.

Select one:

a.

True

b.

False

Clear my choice

Question 42

Not yet answered

Points out of 1.0

Flag question

Question text

______ is an uncertainty that may arise during the course of a project that will have a negative impact on the project's outcome.

Select one:

a.

Variance

b.

Conflict

c.

Risk

d.

An opportunity

Clear my choice

Question 43

Not yet answered

Points out of 1.0

Flag question

Question text

A framework adopted by an organization in order to improve processes by becoming increasingly organized is known as:

Select one:

a.

Six Sigma

b.

A maturity model

c.

Systemic improvement

d.

Systemic enhancement

Clear my choice

Question 44

Not yet answered

Points out of 1.0

Flag question

Question text

When we identify, evaluate, and manage changes throughout a project's life cycle we are carrying out:

Select one:

a.

The monitoring and controlling phase

b.

Change measurement and reinforcement

c.

Integrated change control

d.

Configuration management

Clear my choice

Question 45

Not yet answered

Points out of 1.0

Flag question

Question text

Which stakeholders should be involved in the planning phase to identify, analyze, prioritize and (hopefully) mitigate all possible risks?

Select one:

a.

The project team and primary sponsor

b.

The project manager and primary sponsor

c.

The project team and project manager

d.

As many stakeholders as possible

Clear my choice

Question 46

Not yet answered

Points out of 1.0

Flag question

Question text

The following is an example of a(n):

Select one:

a.

Project schedule

b.

Responsibility assignment matrix

c.

Project communication plan

d.

Risk matrix

Clear my choice

Question 47

Not yet answered

Points out of 1.0

Flag question

Question text

If a project closed successfully (on time, budget, and within scope) a "lessons learned" meeting isn't always necessary.

Select one:

a.

True

b.

False

Clear my choice

Question 48

Not yet answered

Points out of 1.0

Flag question

Question text

Which of the following is not a method of conflict management?

Select one:

a.

Confrontation

b.

Forcing

c.

Smoothing

d.

Escalation

Clear my choice

Question 49

Not yet answered

Points out of 1.0

Flag question

Question text

According to Maslow, once a "need" has been filled, it ceases being something that motivates an individual.

Select one:

a.

True

b.

False

Clear my choice

Question 50

Not yet answered

Points out of 1.0

Flag question

Question text

A project manager should have a good understanding of the various quality techniques that are available, so that they are able to select those techniques most suited to the project.

Select one:

a.

True

b.

False

Clear my choice

Question 51

Not yet answered

Points out of 1.0

Flag question

Question text

Which of Maslow's tiers of needs applies to a person who wants to be part of a team or have close-knit coworkers?

Select one:

a.

Communal needs

b.

Esteem needs

c.

Cohesive needs

d.

Social needs

Clear my choice

Question 52

Not yet answered

Points out of 1.0

Flag question

Question text

When addressing quality control, a Pareto chart might be used to determine:

Select one:

a.

The most common sources of defects,

b.

The highest-occurring types of defects

c.

The most frequent causes for user/customer complaints

d.

All of the above

Clear my choice

Question 53

Not yet answered

Points out of 1.0

Flag question

Question text

When trying to determine the level of commitment a project stakeholder will show your project, the best way to communicate with that individual is:

Select one:

a.

Through email or other written communication

b.

By meeting with the stakeholder

c.

By having a phone conversation

d.

The use of quick-response text messages.

Clear my choice

Question 54

Not yet answered

Points out of 1.0

Flag question

Question text

Project scope management is primarily focused on:

Select one:

a.

Analyzing scope

b.

Validating scope

c.

Controlling scope

d.

All of the above

e.

Only B and C

Clear my choice

Question 55

Not yet answered

Points out of 1.0

Flag question

Question text

A chart that captures, by resource, the specific amount of time that the particular resource is scheduled to be worked over a predetermined time period is known as a:

Select one:

a.

Gantt chart

b.

Risk responsibility chart

c.

Resource histogram

d.

Responsibility assignment matrix

Clear my choice

Question 56

Not yet answered

Points out of 1.0

Flag question

Question text

Which of the following is not a quality control technique?

Select one:

a.

A cause and effect diagram

b.

A scatter diagram

c.

An issue register

d.

A flowchart

Clear my choice

Question 57

Not yet answered

Points out of 1.0

Flag question

Question text

In the workplace, the lowest tier on Maslow's pyramid may correlate to _______, according to an outside article we read.

Select one:

a.

Having a full-time job.

b.

Having a job that provides you with enough money to pay living expenses, and buy food and clothing.

c.

Having a job that pays well enough that you may save money, in addition to paying for living expenses, food, and clothing.

d.

Having a job that is in in a safe area of town.

Clear my choice

Question 58

Not yet answered

Points out of 1.0

Flag question

Question text

Newly-formed teams go through a predictive set of stages during their lifetime. The team formation stage with the highest accomplishments is called the ______ stage.

Select one:

a.

Forming

b.

Storming

c.

Norming

d.

Performing

Clear my choice

Question 59

Answer saved

Points out of 1.0

Flag question

Question text

Negative numbers for the project's cost variance and schedule variance means that the project is ahead of its planned progress.

Select one:

a.

True

b.

False

Clear my choice

Question 60

Not yet answered

Points out of 1.0

Flag question

Question text

The following image shows outputs of the ______ phase of the project lifecycle.

Select one:

a.

Monitoring and controlling

b.

Planning

c.

Executing

d.

None of the above