Subject: conoco / tw at monument - - - level " a " + / - 30 % cost estimate
design volume = 60 mmcf / d at 700 psig
the following is a summary of facility requirements and the associated cots to tie conoco to tw - 10 " suction side of the monument compressor station .
facilities a - release costs ( $ )
10 x 8 " tee & side valve 30 , 000
efm , das , rtu , chromatograh 130 , 000
and h 2 o analyzer and buildings .
8 " - ultrasonic measurements 40 , 000
flow control valve with pressure override 135 , 000
and isolation valve
overhead 15 % 50 , 250
contingency 10 % 33 , 500
total $ 418 , 750