Subject: five tx power plants to go commercial this month
texas power plants to add 2 , 775 mw this month
five power plants with 2 , 775 mw of new generating capacity are
being tested in the ercot and all should be operating commercially
before the end of this month . the 500 mw unit 2 at fpl ' s lamar
county plant is expected to be commercial soon . calpine ' s 545 mw
expansion of its pasadena plant in harris county is running but has
not yet gone commercial . lg & e power services ' 400 mw gregory power
partners plant in san patricio county and american national power ' s
500 mw midlothian plant in ellis county are set to go commercial
within days . the 830 mw tenaska frontier plant in grimes county has
been testing since may and is also set to go .