Subject: re : private firm schedule
thanks for the schedule update
- - - - - original message - - - - -
from : kirkpatrick , eric
sent : monday , april 23 , 2001 10 : 52 am
to : mack , iris ; dhar , amitava ; brent , richard ; salmon , scott ; chaney , craig ;
mumford , mike ; detiveaux , kim ; cruver , brian
subject : private firm schedule
all :
this is the rough schedule we came up with at today ' s video conference :
submit rfp to d & b , experian , and amadeus 2 days 25 apr mumford
receive back rfps 1 . 5 weeks 4 may mumford
complete evaluation , selection & authorization 1 week 11 may mumford / mack
contract complete and signed 2 weeks 25 may mumford
data to iris & amitava 3 weeks 15 june mumford
model development complete 4 weeks 15 july mack
* integration of model and data feeds into cts 6 weeks 30 august kirkpatrick
prior to integration into cts any prices would have to be manually uploaded
into cts via spreadsheet .
the rfp will include a request for a smaller data calibration set that we may
select to purchase immediately .
we can revisit this schedule at our wednesday video conference .
eric kirkpatrick