electrical engineering end of semester project
1/6
Final Project EE-431
Introduction
This project aims to determine your ability to apply the concepts and methods discussed in class
for a power system design problem. You can develop your own software in your language of
choice, and/or use the software tools utilized in the class (i.e. MATLAB) or you can follow the
procedure by hand calculations.
Objective
● To carry out the design of a power transmission system that runs through urban service
territories.
● To apply your knowledge from class in computing parameters for component models,
perform steady-state analysis.
● To build software scripts and use different software tools towards your design.
● To document your results, calculations, and source code (if applicable) in a report.
Design Project Statement and Data
Design Problem Statement
The design problem consists in expanding a transmission system to serve a 4-bus power system
shown in the map in Fig. 1 and to also determine if the existing transmission system needs to be
upgraded to handle an additional growth (40MW) in the existing load connected to the Bus 3. This
requires to redesign and build new transmission infrastructure, and to perform power flow analysis
studies using Newton-Raphson method.
Transmission System
The transmission system in Figure 1, below, contains both 161 kV transmission lines and
substations that go through urban service territories. The load at each of the buses is provided in
Table 1, and the parameters of the existing lines are shown in Table 2.
2/6
Figure 1. One-line Diagram of the 4-Bus Power System
Substations Buses and Loads
The buses shown in the diagram correspond not only to electrical buses, but to substations:
Buses 1-2 are substations at power sources (i.e. generation plants) at 161 kV.
○ Each power source is rated at 100 MVA, and should be represented by their
equivalent current sources with their reactances in per unit on a 100 MVA-
base as shown below.
Bus # Bus Name Reactance Capacity
1 Generator j0.25 100 MVA
2 Generator j0.20 100 MVA
● Buses 3-4 are urban load substations, assume a voltage magnitude of 1.0 per unit at
buses 3 and 4.
Bus # Load (MW) Load (MVAr)
3 100 25
4 150 50
Table 1. Loads at different buses
3/6
Transmission Lines
Parameters for Existing Lines
The parameters of the existing transmission lines representing by π model where series
reactances and shunt reactances expressed in per unit on a 100MVA base are provided in Table
2, below.
Bus # Bus # R (p.u) XL (p.u) XC (p.u)
1 2 0 0.25 -4
1 3 0 0.1 -4
1 4 0 0.4 -4
2 4 0 0.16 -4
3 4 0 0.2 -4
Table 2. Transmission Line Parameters
Design Phases Overview
The project is structured so that you conduct this project in 4 different phases, as follows:
1. In the first phase of the design, the only requirement is to convert the loads, generation
units, and transmission lines to the corresponding impedance parameters.
This phase consists of transforming all the data to per unit quantities, if not already in per
unit.
The remaining step of the design requires to consider the location of the equivalent current
source of power generators along with the given reactance per each generator.
2. The second phase consists in using the per-unit data of all system components to compute
both Ybus and Zbus.
3. The third phase consists in a power flow study of the system under different load growth
scenarios.
4. The final phase is to prepare a report describing obtained results based on this analysis.
Phase 1
In this phase you are asked to draw the existing system in per unit with all values making design
to serve the load and generation subject to the specifications and design tasks as described
below.
4/6
Design Tasks
a. Calculate per unit values of impedances of all the transmission lines using a suitable
software. You can make your own hand calculation, or use MATLAB. The resistance of
lines is ignored. The line reactances at rated voltage is provided in Table 2.
b. Each power source (generator) should be connected to the Bus 1 and Bus 2 with specified
reactance above.
c. Calculate all the per unit values of the loads on a 100 MVA base, with a voltage base of
161 kV (1 p.u.) as appropriate.
Create a table with all the parameters of the system in per unit.
Phase 2
This phase is a continuation of Phase 1 consists of building the Ybus and Zbus matrices.
Design Tasks
For the parameters determined in Phase 1, perform the following calculations.
d. Use the MATLAB Command other code to compute Ybus and Zbus. You can proceed
with hand calculations if you wish.
e. Compute the bus admittance matrix, Ybus and bus impedance matrix, Zbus with all the
parameters expressed in per unit on the common system base of 100 MVA.
Phase 3
This phase consists in performing different power flow studies for the system set up in the previous
phases. You will consider the following case studies:
● Case 1: Base case system with base loads as specified in Table 1.
● Case 2: Modified system with adding a 40 MW “Data Center” load connected to Bus 3.
Design Tasks
f. Perform power flow analysis based on Newton-Raphson method on Case 1 and verify the
design requirements listed below.
g. Modify the 4-bus power system to supply the new 40 MW load connected to Bus 3 and
repeat Newton-Raphson power flow analysis.
h. Summarize graphically (one plot for each Cases 1 and 2) the power flow results from the
two cases analyzed above, show the bus voltage magnitude and angle, active and
reactive powers.
i. Compare the MVA in the loads, the MVA used in the lines, and the MVA from the
generators in each case.
5/6
Design Criteria and Specifications
Criteria
When carrying out the design tasks above, you must meet the following design criteria:
● R1. Satisfactory system operation: all voltages should be in the range from 0.95 to 1.05
pu, with no overloaded lines.
● R2. Loads: from the power flow results, determine the total load in the system, the losses
across lines and total generation.
Phase 4
This final phase is about documentation of your obtained results considering the below guidelines:
A deadline for report submission is on December 11th, 2020 by 5:00 pm.
Report Requirements and Structure
Your report should be structured as described below.
1. Executive Summary: a maximum 1-2 page summary that includes the main information
of your project.
This should contain everything that I need to know to grade you without having to read
the whole report. Make this a “self contained” document.
Your summary should include at least the following:
a. Summarize the changes required (for example the capacity of transmission lines,
choosing lower or high capacity of cables, etc.) at each case in Phase 3 using a
table.
b. Contrast the analysis methods and results of Phase 3.
c. Use a minimum of 1 figure and a maximum of 2 figures to highlight your most
important finding.
2. Report Structure:
a. Title page
b. Table of contents.
c. System Description
i. A one-line diagram of the system showing the generators, bus, line, and
load connections. Explain your suggestion to achieve a better system
operation if you think there is a need for modifications by adding new 40MW
loads at Bus 3.
ii. Specifications of each line in the system: connection between buses,
voltage, series impedance and shunt capacitance reactance, and MVA and
current ratings.
6/6
d. Design Summary
i. Provide a summary of results from all other design phases here. You
should aim to summarize each phase with a short paragraph and preferably
through 1 or 2 figures. You might prefer that all other details (calculations,
tables, figures) for each design phase to be included in a dedicated
Appendix.
ii. Design Analysis:
1. Compare the analysis results of Case 1 and Case 2 in Phase 3.
2. Use a minimum of 1 figure and a maximum of 2 figures to highlight
your most important finding.
iii. Design Tools (if using software):
1. Software Documentation: Briefly explain, through a
flowchart/discussion, how you were able to do the analysis required
through different software routines or by using different
functions/software and reading data.
e. Conclusions: briefly discuss your findings. Keep this short, 1-2 paragraphs, 1
figure, and highlight your most important finding.
3. Other:
a. Number and title all figures.
b. Number and title all tables.
c. Document all changes made from the base case design in a dedicated Appendix,
be organized!
Final Remarks
Do your own work!
● This project serves as a way to measure your ability to apply the intended learning
outcomes. You must make sure during the course that you will be able to do the work
described here, and thus, you must do all the homework assignments to be able to have
the skills you need.
● This project may have not a unique solution, so there is likely possible way that you
can have the different solution as another student.