Project management assignment

profilejoshna
earnedvaluechart.xls

Sheet1

Earned Value Chart
Date
Be sure to enter your own data and check your formulas.
Month
1 2 3 4 5 6 7 8 9 10 11 12 Total Cost
WBS Categories
1. Initiating 13,000 $ 13,000
2. Planning 6,000 16,000 8,000 1,000 1,000 1,000 1,000 1,000 1,000 $ 36,000
3. Executing - 0 - 0 - 0 $ - 0
3.1 Course design and development - 0 - 0 - 0 $ - 0
3.1.1 Supplier management training 5,000 73,667 73,667 73,667 $ 226,000
3.1.2 Negotiating skills training 5,000 35,500 35,500 35,500 $ 111,500
3.1.3 Project management training 5,000 43,000 43,000 43,000 $ 134,000
3.1.4 Software applications training 5,000 43,000 43,000 43,000 $ 134,000
3.2 Course administration 17,000 53,333 53,333 53,333 $ 177,000
3.3.Course evaluation 3,000 3,000 3,000 7,500 $ 16,500
3.4 Stakeholder communications 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 $ 16,500
4. Monitoring and Controlling 1,000 2,000 2,000 2,000 3,000 3,500 3,000 3,000 2,000 3,000 2,000 1,000 $ 27,500
5. Closing 8,000 3,000 $ 11,000
Subtotal $ 903,000
Reserves - 0 - 0 - 0 90,300 $ 90,300
Total 20,000 19,500 31,500 199,667 200,667 218,167 61,833 61,833 60,833 12,000 11,500 95,800 993,300
$ 689,500
Monthly Planned Value (PV) 20,000 19,500 31,500 199,667 200,667 218,167 61,833 61,833 60,833 12,000 11,500 95,800
Cumulative Planned Value (PV) 20,000 39,500 71,000 270,667 471,333 689,500 751,333 813,167 874,000 886,000 897,500 993,300
Monthly Actual Cost (AC) 20,000 20,000 35,000 210,000 220,000 245,000
Cumulative Actual Cost (AC) 20000 40,000 75,000 285,000 505,000 750,000
Monthly Earned Value (EV) 20,000 20,000 30,000 190,000 200,000 240,000
Cumulative Earned Value (EV) 20,000 40,000 70,000 260,000 460,000 700,000
Project EV as of May 31 700,000
Project PV as of May 31 689,500
Project AC as of May 31 $ 750,000
CV=EV-AC $ (50,000)
SV=EV-PV $ 10,500
CPI=EV/AC 93.33%
SPI=EV/PV 101.52%
Estimate at Completion (EAC) $ 1,071,429
Estimated time to complete 11.82

Sheet1

Cumulative Planned Value (PV)
Cumulative Actual Cost (AC)
Cumulative Earned Value (EV)

Sheet2

BAC
EAC

Sheet3