1

TBC 1 2 3 4 5 6 7 8 9 10
Task 1 30 10 15 5
Task 2 70 10 10 10 20 10 10
Task 3 40 5 5 25 5
Task 4 30 5 5 20
Total 170 10 25 15 10 25 15 35 10 5 20
Cumulative
ACT 1 2 3 4 5 6
Task 1 34 10 16 8
Task 2 68 10 10 12 24 12
Task 3 10 5 5
Task 4 0
Total 112 10 26 18 12 29 17
Cumulative
1 2 3 4 5 6
Task 1 30% 80% 100%
Task 2 10% 25% 35% 55% 65%
Task 3 10% 20%
Task 4

Refer to the table below. What is the cumulative budgeted cost at the end of Week 6?

Below is a table of actual costs. What is the cumulative actual cost at the end of Week 6? Determine whether there was a cost overrun or underrun. What is causing it?

Below is a table of of the cumulative percentages of work completed by the end of week 6. What is the cumulative earned value at the end of week 6? Is is good? What is the CPI at the end of week 6? What is the CV? Calculate the FCAC using the first two methods described in the chapter. In addition, describe a third FCAC you could use.