Project management assignment

profilejoshna
earned_value.xlsx

EV data

Earned Value Calculations for Project Name
Prepared by: Date:
Note: Change the entries to meet your project needs. This data is from Figure 7-4 of Schwalbe's text Information Technology Project Management, Fourth Edition.
Also make sure the formulas work properly based on the data you enter.
To Date Planned Actual
Activity Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec PV % Complete % Complete RV EV
Plan and staff project 4,000 4,000 8,000 100 100 100% 8,000
Analyze requirements 6,000 6,000 12,000 100 100 100% 12,000
Develop ERDs 4,000 4,000 8,000 100 100 100% 8,000
Design database tables 6,000 4,000 10,000 100 100 100% 10,000
Design forms, reports, and queries 8,000 4,000 8,000 75 50 67% 5,333
Construct working prototype 10,000 - 0 - 0
Test/evaluate prototype 2,000 6,000 - 0 - 0
Incorporate user feedback 4,000 6,000 4,000 - 0 - 0
Test system 4,000 4,000 2,000 - 0 - 0
Document system 3,000 1,000 - 0 - 0
Train users 4,000 - 0 - 0
Monthly Planned Value (PV) 4,000 10,000 10,000 10,000 12,000 16,000 10,000 6,000 8,000 4,000 5,000 5,000 43,333
Cumulative Planned Value (PV) 4,000 14,000 24,000 34,000 46,000 62,000 72,000 78,000 86,000 90,000 95,000 100,000
Monthly Actual Cost (AC) 4,000 11,000 11,000 12,000 15,000
Cumulative Actual Cost (AC) 4,000 15,000 26,000 38,000 53,000
Monthly Earned Value (EV) 4,000 10,000 10,000 10,000 9,333
Cumulative Earned Value (EV) 4,000 14,000 24,000 34,000 43,333
Project EV as of May 31 43,333
Project PV as of May 31 46,000
Project AC as of May 31 $ 53,000
CV=EV-AC $ (9,667)
SV=EV-PV $ (2,667)
CPI=EV/AC 81.761%
SPI=EV/PV 94.203%
Estimate at Completion (EAC) $ 122,308 (original plan of $100,000 divided by CPI)
Estimated time to complete 12.74 (original plan of 12 months divided by SPI)

EV chart

Chart1

4000 4000 4000
14000 15000 14000
24000 26000 24000
34000 38000 34000
46000 53000 44000
62000
72000
78000
86000
90000
95000
100000
BCWS or Cumulative Plan
ACWP or Cumulative Actual
BCWP or Cumulative EV
Month
$

Chart4

3 4 3
8 8 8
19 18 19
32 29 31
47 41 41.5
63 56 48.645
91 83 73.045
145
206
233
246
254
BCWS or Cumulative Plan
ACWP or Cumulative Actual
BCWP or Cumulative EV
Month
$

Sheet1

Activity Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Plan % Complete EV
Plan and staff project 4,000 4,000 8,000 100 8,000
Analyze requirements 6,000 6,000 12,000 100 12,000
Develop ERDs 4,000 4,000 8,000 100 8,000
Design database tables 6,000 4,000 10,000 100 10,000
Design forms, reports, and queries 8,000 4,000 12,000 50 6,000
Construct working prototype 10,000 10,000 - 0 - 0
Test/evaluate prototype 2,000 6,000 8,000 - 0 - 0
Incorporate user feedback 4,000 6,000 4,000 14,000 - 0 - 0
Test system 4,000 4,000 2,000 10,000 - 0 - 0
Document system 3,000 1,000 4,000 - 0 - 0
Train users 4,000 4,000 - 0 - 0
Monthly Plan 4,000 10,000 10,000 10,000 12,000 16,000 10,000 6,000 8,000 4,000 5,000 5,000 100,000 44,000
BCWS or Cumulative Plan 4,000 14,000 24,000 34,000 46,000 62,000 72,000 78,000 86,000 90,000 95,000 100,000
Monthly Actual 4,000 11,000 11,000 12,000 15,000
ACWP or Cumulative Actual 4,000 15,000 26,000 38,000 53,000
Monthly EV 4,000 10,000 10,000 10,000 10,000
BCWP or Cumulative EV 4,000 14,000 24,000 34,000 44,000
Project BCWP as of May 31 44,000
Project BCWS as of May 31 46,000
Project ACWP as of May 31 $ 53,000
CV=BCWP-ACWP $ (9,000)
SV=BCWP-BCWS $ (2,000)
CPI=BCWP/ACWP 83%
SVI=BCWP/BCWS 96%
Estimated cost at completion $ 120,455 (original plan of $100,000 divided by CPI of 83%)
Estimated time to complete 12.55 (original plan of 12 months divided by SVI of 96%)
Above for Figure 6-2
Chart below for Figure 6-3

Sheet1

0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0
0
0
0
0
BCWS or Cumulative Plan
ACWP or Cumulative Actual
BCWP or Cumulative EV
Month
$

Sheet2

Sheet3

-

20,000

40,000

60,000

80,000

100,000

120,000

123456789101112

Month

$

Planned Value (PV)

Budget at Completion (BAC)

Actual Cost (AC)

Earned Value (EV)

Estimate at Completion (EAC)