Earned Value Management (EVM)

profileMkrenisky84
earned-value-management1.xlsx

Report

[Project Title] [Company Name / Logo]
Earned Value Analysis Report
Earned Value Management Template
Prepared By: [Manager's Name] © 2012-2017 Vertex42 LLC
Date: [Report Date]
[42]
For Period: Week 7
Summary:
[Use this space to write a brief summary or to record specific observations or notes]
Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS)
WBS
Vertex42: Work Breakdown Structure (WBS)
Task Name TBC
Vertex42: Total Budgeted Cost (TBC)
1 2 3 4 5 6 7 8 9 10 11 12 ← You can change the labels for the periods (e.g. Week 1/2/3, Jan/Feb/Mar, etc.)
1.1 Task 1 3500 1000 500 2000 ← Enter or edit values in the light-blue cells.
1.2 Task 2 4200 500 800 900 2000
1.3 Task 3 4500 700 2000 1000 800
1.4 Task 4 3300 200 600 1000 1500
1.5 Task 5 3000 700 500 1000 800
1.6 Task 6 6700 700 2000 1000 2000 1000
0
0
0
0
0
0
Insert new rows above this one ← To add more tasks, insert rows above this one. You can or delete this row after you are done adding tasks.
Total Budgeted Cost 25200 1000 1000 3700 3500 4700 2800 1000 1500 2000 1000 2000 1000
Cumulative Planned Value (PV) 1000 2000 5700 9200 13900 16700 17700 19200 21200 22200 24200 25200
Actual Cost and Earned Value
Cumulative Actual Cost (AC) 800 1950 4550 6550 10800 13600 14500 ← Enter the Actual Costs as calculated from the AC worksheet.
Cumulative Earned Value (EV) 525 2800 5885 7820 9725 15170 20770 ← Enter the Earned Value as calculated from the EV worksheet.
Project Performance Metrics
Cost Variance (CV = EV - AC) -275 850 1335 1270 -1075 1570 6270 - - - - -
Schedule Variance (SV = EV - PV) -475 800 185 -1380 -4175 -1530 3070 - - - - -
Cost Performance Index (CPI = EV/AC) 0.66 1.44 1.29 1.19 0.90 1.12 1.43 - - - - -
Schedule Performance Index (SPI = EV/PV) 0.53 1.40 1.03 0.85 0.70 0.91 1.17 - - - - -
Estimated Cost at Completion (EAC) 38400 17550 19483 21107 27986 22592 17593 - - - - -

&8&K01+049https://www.vertex42.com/ExcelTemplates/earned-value-management.html &8&K01+049EVM Template © 2012 Vertex42 LLC

Planned Value (PV) 1 2 3 4 5 6 7 8 9 10 11 12 1000 2000 5700 9200 13900 16700 17700 19200 21200 22200 24200 25200 Earned Value (EV) 1 2 3 4 5 6 7 8 9 10 11 12 525 2800 5885 7820 9725 15170 20770 Actual Cost (AC) 1 2 3 4 5 6 7 8 9 10 11 12 800 1950 4550 6550 10800 13600 14500

Period

Planned Value (PV) 1 2 3 4 5 6 7 8 9 10 11 12 1000 2000 5700 9200 13900 16700 17700 19200 21200 22200 24200 25200 Earned Value (EV) 1 2 3 4 5 6 7 8 9 10 11 12 525 2800 5885 7820 9725 15170 20770 Actual Cost (AC) 1 2 3 4 5 6 7 8 9 10 11 12 800 1950 4550 6550 10800 13600 14500

Period

https://www.vertex42.com/ExcelTemplates/earned-value-management.html

EV

Earned Value Worksheet
This worksheet is used to help calculate the Earned Value (EV) or Budgeted Cost of Work Performed (BCWP). Earned Value Management Template
Make sure that the WBS, Task Name, and TBC are identical to the table in the Report worksheet. © 2012-2017 Vertex42 LLC
Enter the % Complete for each task to calculate the cumulative earned value.
Cumulative Earned Value (EV)
WBS Task Name TBC Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8 Wk 9 Wk 10 Wk 11 Wk 12
1.1 Task 1 3500 15% 50% 100% 100% 100% 100% 100%
1.2 Task 2 4200 25% 30% 60% 75% 90% 100%
1.3 Task 3 4500 25% 40% 50% 100% 100%
1.4 Task 4 3300 25% 80% 90%
1.5 Task 5 3000 25% 75%
1.6 Task 6 6700 50%
- - 0
- - 0
- - 0
- - 0
- - 0
- - 0
Insert new rows above this one
Cumulative EV 525 2800 5885 7820 9725 15170 20770 0 0 0 0 0
https://www.vertex42.com/ExcelTemplates/earned-value-management.html

AC

Actual Cost Worksheet
Use this worksheet to help calculate the Actual Cost (AC) of Work Performed (ACWP) by entering the costs incurred each period. Earned Value Management Template
Make sure that the WBS, Task Name, and TBC are identical to the table in the Report worksheet. © 2012-2017 Vertex42 LLC
Transfer the Cumulative Actual Cost to the Report worksheet.
Actual Cost (AC) of Work Performed
WBS Task Name Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8 Wk 9 Wk 10 Wk 11 Wk 12
1.1 Task 1 800 250 1500
1.2 Task 2 900 700 1200 1700
1.3 Task 3 300 300 1250 1500
1.4 Task 4 100 500 900 700 400
1.5 Task 5 400 600 500
1.6 Task 6
- -
- -
- -
- -
- -
- -
Insert new rows above this one
Total Actual Cost 800 1150 2600 2000 4250 2800 900 0 0 0 0 0
Cumulative Actual Cost (AC) 800 1950 4550 6550 10800 13600 14500 14500 14500 14500 14500 14500
https://www.vertex42.com/ExcelTemplates/earned-value-management.html

©

Earned Value Management (EVM) Template
By Vertex42.com
https://www.vertex42.com/ExcelTemplates/critical-path-method.html
© 2012-2017 Vertex42 LLC
This spreadsheet, including all worksheets and associated content is a copyrighted work under the United States and other copyright laws.
Do not submit copies or modifications of this template to any website or online template gallery.
Please review the following license agreement to learn how you may or may not use this template. Thank you.
https://www.vertex42.com/licensing/EULA_privateuse.html
Do not delete this worksheet.
https://www.vertex42.com/ExcelTemplates/critical-path-method.html https://www.vertex42.com/licensing/EULA_privateuse.html