Project Schedule Changes
ID WBS Task
Mode
Task Name Duration Start Finish
0 0 District4WarehouseMove 109 days? Wed 4/19/17Mon 9/18/17 1 1 Project Kick-off 3 days Wed 4/19/17Fri 4/21/17
2 1.1 Book location for meeting 1 day Wed 4/19/17Wed 4/19/17
3 1.2 Invite stakeholders 1 day Thu 4/20/17 Thu 4/20/17
4 1.3 Prepare presentation 1 day Fri 4/21/17 Fri 4/21/17
5 1.4 Conduct the meeting 1 day Fri 4/21/17 Fri 4/21/17
6 2 Project Documents 7 days Mon 4/24/17Tue 5/2/17
7 2.1 Develop Charter/Scope 2 days Mon 4/24/17Tue 4/25/17
8 2.2 Develop WBS 7 days Mon 4/24/17Tue 5/2/17
9 2.3 Develop Project Plan 2 days Mon 4/24/17Tue 4/25/17
10 2.4 Develop Communication Plan2 days Wed 4/26/17Thu 4/27/17
11 3 Status Reports/Meetings 3 days Wed 4/26/17Fri 4/28/17
12 3.1 Develop Status Report 1 day Wed 4/26/17Wed 4/26/17
13 3.2 Set schedule for team meetings1 day Fri 4/28/17 Fri 4/28/17
14 3.4 Set schedule for stakeholder meetings1 day Thu 4/27/17 Thu 4/27/17
15 4 Initial Planning Meetings with Vendors3 days Fri 4/28/17 Tue 5/2/17
16 4.1 Meet with Framing/Drywall 1 day Mon 5/1/17 Mon 5/1/17
17 4.2 Meet with Electrical 1 day Fri 4/28/17 Fri 4/28/17
18 4.3 Meet with Plumbing 1 day Mon 5/1/17 Mon 5/1/17
19 4.4 Meet with Finish Work 1 day Mon 5/1/17 Mon 5/1/17
20 4.5 Meet with Student Workers 1 day Tue 5/2/17 Tue 5/2/17
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
W T F S S M T W T F S S M T W T F
Apr 9, '17 Apr 16, '17 Apr 23, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 1
ID WBS Task
Mode
Task Name Duration Start Finish
21 5 Electrical Permits 10 days Wed 5/3/17 Tue 5/16/17
22 5.1 Obtain Electrical Permits 10 days Wed 5/3/17 Tue 5/16/17
23 6 Plumbing Permits 10 days Wed 5/17/17Tue 5/30/17
24 6.1 Obtain Plumbing Permits 10 days Wed 5/17/17Tue 5/30/17
25 7 Building Permits 14 days Wed 5/31/17Mon 6/19/17
26 7.1 Obtain Building Permits 14 days Wed 5/31/17Mon 6/19/17
27 8 Framing 53 days Wed 5/3/17 Fri 7/14/17
28 8.1 Framing-Order Supplies 3 days Wed 6/14/17Fri 6/16/17
29 8.2 Framing-Build 15 days Mon 6/19/17Fri 7/7/17
30 8.3 Framing-Inspect 5 days Mon 7/10/17Fri 7/14/17
31 8.4 Framing-Project Sign-off 1 day Wed 5/3/17 Wed 5/3/17
32 9 Electrical 10 days Thu 5/4/17 Wed 5/17/17
33 9.1 Electrical-Order Supplies 3 days Thu 5/4/17 Mon 5/8/17
34 9.2 Electrical-Install 10 days Thu 5/4/17 Wed 5/17/17
35 9.3 Electrical-Inspect 5 days Tue 5/9/17 Mon 5/15/17
36 9.4 Electrical-Project Sign-off 1 day Tue 5/16/17 Tue 5/16/17
37 10 Plumbing 10 days Wed 5/17/17Tue 5/30/17
38 10.1 Plumbing-Order Supplies 3 days Wed 5/17/17Fri 5/19/17
39 10.2 Plumbing-Install 10 days Wed 5/17/17Tue 5/30/17
40 10.3 Plumbing-Inspect 5 days Mon 5/22/17Fri 5/26/17
41 10.4 Plumbing-Project Sign-off 1 day Mon 5/29/17Mon 5/29/17
0%
0%
0%
0%
0%
0%
0%
0%
W T F S S M T W T F S S M T W T F
Apr 9, '17 Apr 16, '17 Apr 23, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 2
ID WBS Task
Mode
Task Name Duration Start Finish
42 11 Drywall 19 days Tue 5/30/17 Fri 6/23/17
43 11.1 Drywall-Order Supplies 6 days Tue 5/30/17 Tue 6/6/17
44 11.2 Drywall-Install 17 days Wed 5/31/17Thu 6/22/17
45 11.3 Drywall-Inspect 7 days Tue 5/30/17 Wed 6/7/17
46 11.4 Drywall-Project Sign-off 3 days Wed 6/21/17Fri 6/23/17
47 12 Finish Work 29 days Thu 6/22/17 Tue 8/1/17
48 12.1 Finish-Order Supplies 5 days Thu 6/22/17 Wed 6/28/17
49 12.2 Finish-Install 17 days Tue 6/27/17 Wed 7/19/17
50 12.3 Finish-Inspect 7 days Tue 7/18/17 Wed 7/26/17
51 12.4 Finish-Project Sign-off 6 days Tue 7/25/17 Tue 8/1/17
52 13 Workbenches 18 days Wed 7/26/17Fri 8/18/17
53 13.1 Workbenches-Order Supplies5 days Wed 7/26/17Tue 8/1/17
54 13.2 Workbenches-Build 17 days Wed 7/26/17Thu 8/17/17
55 13.3 Workbenches-Quality inspection6 days Fri 7/28/17 Fri 8/4/17
56 13.4 Workbenches-Project Sign-off3 days Wed 8/16/17Fri 8/18/17
57 14 Equipment Packing 15 days Tue 8/1/17 Mon 8/21/17
58 14.1 Pack production equipment 2 days Tue 8/1/17 Wed 8/2/17
59 14.2 Pack non-production equipment2 days Thu 8/17/17 Fri 8/18/17
60 14.3 Project Sign-off 1 day Mon 8/21/17Mon 8/21/17
61 15 Move 13 days Tue 8/22/17 Thu 9/7/17
62 15.1 Move production equipment3 days Tue 8/22/17 Thu 8/24/17
W T F S S M T W T F S S M T W T F
Apr 9, '17 Apr 16, '17 Apr 23, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 3
ID WBS Task
Mode
Task Name Duration Start Finish
63 15.2 Move non-production equipment3 days Fri 8/25/17 Tue 8/29/17
64 15.3 Project Sign-off 1 day Wed 8/30/17Wed 8/30/17
65 16 Procurement Closure 1 day Thu 8/31/17 Thu 8/31/17
66 16.1 Review contract work 3 days Fri 9/1/17 Tue 9/5/17
67 16.2 Release contractors 1 day Wed 9/6/17 Wed 9/6/17
68 16.3 Pay contractors 1 day Thu 9/7/17 Thu 9/7/17
69 17 Project Closure 8 days? Thu 9/7/17 Mon 9/18/17
70 16.1 Prepare presentation 1 day? Thu 9/7/17 Thu 9/7/17
71 17.1 Final report 3 days Fri 9/8/17 Tue 9/12/17
72 17.2 Archive documentation 3 days Wed 9/13/17Fri 9/15/17
73 17.3 Lessons Learned 1 day Mon 9/18/17Mon 9/18/17
W T F S S M T W T F S S M T W T F
Apr 9, '17 Apr 16, '17 Apr 23, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 4
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Apr 23, '17 Apr 30, '17 May 7, '17 May 14, '17 May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 5
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Apr 23, '17 Apr 30, '17 May 7, '17 May 14, '17 May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 6
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Apr 23, '17 Apr 30, '17 May 7, '17 May 14, '17 May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 7
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Apr 23, '17 Apr 30, '17 May 7, '17 May 14, '17 May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 8
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Jun 11, '17 Jun 18, '17 Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 9
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Jun 11, '17 Jun 18, '17 Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 10
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Jun 11, '17 Jun 18, '17 Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 11
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Jun 11, '17 Jun 18, '17 Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 12
0% F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 13
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 14
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 15
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 16