Project Schedule Changes
ID
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Apr 9, '17 Apr 16, '17 Apr 23, '17 Apr 30, '17 May 7, '17 May 14, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 1
ID
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Apr 9, '17 Apr 16, '17 Apr 23, '17 Apr 30, '17 May 7, '17 May 14, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 2
ID
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
0%
0%
0%
0%
0%
0%
0%
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Apr 9, '17 Apr 16, '17 Apr 23, '17 Apr 30, '17 May 7, '17 May 14, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 3
ID
63
64
65
66
67
68
69
70
71
72
73
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Apr 9, '17 Apr 16, '17 Apr 23, '17 Apr 30, '17 May 7, '17 May 14, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 4
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
May 14, '17 May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17 Jun 18, '17 Jun 25, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 5
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
May 14, '17 May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17 Jun 18, '17 Jun 25, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 6
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
May 14, '17 May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17 Jun 18, '17 Jun 25, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 7
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
May 14, '17 May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17 Jun 18, '17 Jun 25, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 8
0% S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 9
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 10
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 11
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 12
0% S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 13
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 14
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 15
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Aug 6, '17 Aug 13, '17 Aug 20, '17 Aug 27, '17 Sep 3, '17 Sep 10, '17 Sep 17, '17
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
District4WarehouseMove
Page 16