PROJECT MANAGEMENT: PERT CHART

profileprpseosa
dataforpertchart_v5.xlsx

Sheet1

Task Time Immediate Predecessors Early Finish Late Finish Slack Critical Path
1 A 2 -- 2 2 0 A
2 B 3 A 3 5 0 B
3 C 3 B 5 8 0 -
4 D 7 B 5 12 0 -
5 E 6 B 5 11 0 E
6 F 1 C, D 12 13 -5 -
7 G 5 D, E 11 16 0 G
8 H 4 F, G 13 17 1 -
9 I 8 G 16 25 0 I
10 K 2 H, I 25 27 0 K