Project 3

profileanngathu
CYB310_Network_ReconfigurationPlanning_Template_Ann_Gathungu.docx

CYB 310 Network Reconfiguration Planning Template

MP_SNHU_withQuill_Horizstack

Current Network State

Sales Department

· 3 PCs

· 1 switch

Subnet 2 Department

· 3 PCs

· 1 switch

Network 3 Department

· 4 PCs

· 1 switch

Server Network 3

· 1 PC

· 1 switch

Server Main PC

· 1 server main PC HRSwitch

Backbone (Network Device Infrastructure)

· Sales switch is connected to switch0

· Subnet 2 switch is connected to pfsense4-2

· Network 3 switch is connected to pfsense4-3 and R2

· Server Network 3 switch is connected to R2

· Server Main PC is connected to R1

· Pfsense4-2 is connected to switch0

· Pfsense4-3 is connected to switch0

· R1 is connected to switch0

· Switch0 is connected to pfsense4-1

· Pfsense4-1 connected to the internet

Network Reconfiguration (Future State)

Customer Experience Department

· 6pcs

· 1 switch

HR Department

· 3 pcs

· 1 switch

Network Servers

· 2 servers

· 1 switch

· 2 routers

Backbone (Network Device Infrastructure)

· CustExpSwitch port 0 connected to CoreRouter 0/1

· HR switch Port 1 connected to CoreRouter 1/0

· ServerSwitch connected to ServerRouter0/1

· CoreRouter 1/0 connected to BackboneSwitch port 1

· ServerRouter 0/0 connected to BackboneSwitch port 2

· ServerRouter 0/1 connected to ServerSwitch 0/1

· WebServer connected to ServerSwitch port 1

· AuthServer connected to Server Switch port 2

· CustExpPC 1-6 connected to CustExpSwitch ports 1-6

· HRPC 1-3 connected to HRSwitch ports 1-3

· Edge firewall connected to BackBoneSwitch Port 0 Edge Firewall connectd to cloud.

· WebServer firewall allows traffic from WAN on ports 80 HTTP and 443 HTTPS