Technology and information management

profilekylecs14
CSE171B_270BMOTII_FINALEXAMINATION.pdf

 

 

 

 

 

CSE 171B/270B, MOT II: FINAL  EXAMINATION 

S. Desa, CSE 171B207B Final 

Author: Zhaowei Gu  Students Identification Number: 1523932 

Institution: University of California Santa Cruz  Instructor: S. Desa. 

02/17/2020   

1. Planning (5 points) 

Define​ the Problem:  Create a plan and time schedule for completing the final exam. Use an appropriate table  (see Problem 7 below) to track how well you execute your schedule and make notes on  any obstacles and problems you encounter. 

Plan​ the treatment of the problem:  1. Create a project plan  2. Finished problem 6 below 

Execute​ the plan: 

Project Plan 

    Status 

Thursday, 12 March 2020  Receive the Final Examination, read through it  and ask questions if needed. 

✅ 

Friday, 13 March 2020  Start on Question 1 & 7  ✅ 

Saturday, 14 March 2020  Start and finish on Question 2 & 3  ✅ 

Sunday, 15 March 2020  Start on Question 4 & 5  ✅ 

Monday, 16 March 2020  Finish on Question 4 & 5  Start on Question 6 

✅ 

Tuesday, 17 March 2020  Due Date 5 PM  Finish on Question 6  Finish Question 1 & 7  Double-check the works 

✅   

   

PROBLEM 2: SCM DESIGN/ANALYSIS FRAMEWORK  (1.0 HOUR, 10 POINTS) 

Define​ the Problem:  You have been hired as a consultant by Poly (formerly Plantronics), a medium-sized  company “headquartered” in Santa Cruz, which is the world leader in communication  headsets. You have been asked to design their supply chain all the way from “high-level”  concerns (e.g., competitive strategy, “alignment”), through analysis/procedures (e.g.,  inventory management models) to the actual integrated software that will be used to  manage their Supply Chain.  Before you start, Poly has asked you to do the following: 

a) Describe the high-level framework (process) for performing supply chain  management from strategy to planning to operations for a typical high-tech  product.  

b) Create appropriate diagrams to help them visualize the structure of your  framework and associated procedures.  

Plan​ the treatment of the problem:  1. Answer Q#1  2. Answer Q#2 

Execute​ the plan:  1. Describe the high-level framework (process) for performing supply chain management  from strategy to planning to operations for a typical high-tech product 

1. Create a Competitive Strategy:   Figure out the competitive strategy that would be the best fit based on  other players’ strategies. 

2. Create a Product Development Strategy:   a. Figure out the product development strategy that would be the best fit the 

company  3. Supply Chain Strategy: 

a. Define the SC strategy, to be aligned with the competitive strategy  b. Design the supply chain to properly meet objectives for managing 

inventory, facilities, transportation, and easy communication of information. 

c. Determine the position on the IDU (Implied demand uncertainty) spectrum  d. Map the SC strategy onto a responsiveness spectrum  e. Determine where the company is located in the zone of strategic fit and 

figure out how the company can expand the scope of strategic fit across  the entire supply chain 

f. Determine the SC tradeoff between cost and responsiveness   

4. Market Strategy (Demand Forecasting):  a. Gather demand data from the market analysis and cash-flow analysis  b. Perform demand forecasting using the static method to compute initial 

estimates of the level, trend, and seasonality  c. Develop a product life-cycle model to determine where the company 

should lie in the zone of strategic fit  d. Perform demand forecasting using Moving Average, Simple Exponential 

Smoothing, Holt’s Model, and Winter’s Model.  e. Plot the data  f. Determine which forecasting method is the best forecasting method 

   5. Inventory Management (Cycle Inventory) 

a. Determine the optimal lot size and the optimal shipping frequency  b. Determine the lowest inventory size (safety inventory) that can be stocked 

for cost efficiency  c. Use aggregation to determine various costs. Use various kinds of 

aggregation such as simple aggregation and tailored aggregation for best  results. 

   6. Transportation 

a. Determine which mode of transportation minimizes total cost by different  modes of transportation 

b. Understand the best placement of facilities to reduce transportation costs  to customers 

c. Explore tailed transportation by customer density and distance as well as  by-product demand and value 

  2. Create appropriate diagrams to help them visualize the structure of your framework  and associated procedures.  

1. Create Porter’s fix (six) model to get a better view of the market. (associated with  competitive strategy) 

  2. Determine the Plantronics competitive strategy. 

  3. Create an Efficiency/Responsiveness, IDU and strategic fit diagram, product life 

cycle diagram 

 

 

  4. Creating a cycle inventory diagram to visualize when Plantronics should re-order 

for new stock. 

 

Check​ your work:  Is the work correctly in every detail?  Yes  Are the assumptions/planning reasonable?  Yes  Does the result make sense?  Yes  I checked all the work I did, they’re all perfectly done. 

Learn​ and Generalize:  I learned how to properly go through the process of approaching a supply chain network. 

PROBLEM 3: OPTIMAL LOT SIZE AND CYCLE  INVENTORY FOR SPECIALTY PACKAGING  COMPANY (SPC) (0.5 HOURS, 10 POINTS) 

Define​ the Problem:  If, in Problem 4 of the midterm, the holding cost h = 0.20 (rather than h = 0.15), what is  optimal lot size and the required cycle inventory for polystyrene resin? Use these new  numerical values in the problems below. 

Plan​ the treatment of the problem:  Go back to the midterm and recalculate the optimal lot size and required cycle inventory  for black plastic for new holding cost h = 0.2 

Execute​ the plan:  Go back to the midterm and recalculate the optimal lot size and required cycle inventory  for black plastic for new holding cost h = 0.2    D (Annual Demand) = 28770  S(Set up cost) = $300  d1 = 1000 pound units  h (holding cost per year) = 20%  C(unit cost) = $25    Optimal lot size: 

858.06 units/shipments Q*L = √ hC2DS = √ 0.2×252×28770×300 = 1   Cycle inventory: 

29.03 units2 Q*L = 2

1858.06 = 9  

Check​ your work:  Is the work correctly in every detail?  Yes 

Are the assumptions/planning reasonable?  Yes  Does the result make sense?  Yes  I checked all the work I did, they’re all perfectly done. 

Learn​ and Generalize:  I have a better understanding of how to calculate economic order quality, optimal lot size,  and cycle inventory.   

PROBLEM 4: SAFETY INVENTORY FOR  POLYSTYRENE RESIN AT SPC (1 HOUR, 20 POINTS) 

Define​ the Problem:  Use the results from Problem 3 for all calculations.    Answer the following questions about safety inventory for polystyrene resin at SPC: 

a) Why should SPC have a safety inventory? What is the average weekly demand for  black plastic (and therefore polystyrene resin) for 2007? If the coefficient of  variation (cv) for black plastic is 0.25, what is the standard deviation in the weekly  demand?  

b) The polystyrene supplier has a lead-time of 2 weeks. SPC would like its Cycle  Service Level (CSL) to be 0.95. Determine the necessary safety inventory (safety  stock) level​ for polystyrene resin ​for a continuous replenishment policy. What is  the Re-order Point (ROP)? What is the fill rate? What is the average inventory?  What is the average flow time?  

c) Create a diagram that shows all the relevant quantities from part (b).  d) In general, is the demand during the lead-time greater than or less than the lot 

size? Explain your answer with the help of the diagram from part (c). 

Plan​ the treatment of the problem:  1. Answer Q#1  2. Answer Q#2  3. Answer Q#3  4. Answer Q#4 

Execute​ the plan:  1. Why should SPC have a safety inventory? What is the average weekly demand for  black plastic (and therefore polystyrene resin) for 2007? If the coefficient of variation (cv)  for black plastic is 0.25, what is the standard deviation in the weekly demand?    D (Annual Demand) = 28770  The reason why SPC should have safety inventory is that when consumer’s present  demand that exceeds the forecasted demand it can help prevents the product shortage. 

 

The average ​weekly demand for black plastic is,​ (52 weeks in a year)DW = 52 annual demand  

53.269 units/weekDW = 52 28770 = 5

The standard deviation of weekly demand with a coefficient variance of 0.25 

w 0.25 53.269 .25 38.317units/week= D * = 5 × 0 = 1   2. The polystyrene supplier has a lead-time of 2 weeks. SPC would like its Cycle Service  Level (CSL) to be 0.95. Determine the necessary safety inventory (safety stock) level for  polystyrene resin for a continuous replenishment policy. What is the Re-order Point  (ROP)? What is the fill rate? What is the average inventory? What is the average flow  time?     Given Data:  Average weekly demand, DW = 553.269 units  Standard deviation of weekly demand, = 138.317  Lead time, L = 2 weeks  CSL = 0.95  QL* = 1858.06  From the sheet of the statistical table, we know that 1.65s (0.95) F −1 =   s .65 38.317 22.756s = 1 × 1 × √2 = 3  

The formula for Re-order point, ROP is 

OP sR = DL + s   53.269 106.54DL = DW × L = 5 × 2 = 1  

OP 106.54 22.756 429.29R = 1 + 3 = 1   Standard deviation of demand during L periods = 38.317 95.61√2 × 1 = 1   Level of safety inventory,  

SC − 22.756[1 s( )] 95.61 s( )E = 3 − F 195.61 322.756 + 1 × F 195.61

138.317  

SC − 22.756[1 s(1.65)] 95.61 s(1.65) E = 3 − F + 1 × F   SC − 22.756[1 .95] 95.61 .95E = 3 − 0 + 1 × 0   SC − 22.756[1 .95] 95.61 .95 69.692E = 3 − 0 + 1 × 0 = 1  

Fill rate = 90.9%1858.06 69.692)/1858.06 9085 F r = ( − 1 = . =   Average inventory = /2 = 929.03 units858.06 1   Average flow time = = / (2 * 553.269) = 1.68 days858.06 1     3. Create a diagram that shows all the relevant quantities from part (b).   

    4. In general, is the demand during the lead-time greater than or less than the lot size?  Explain your answer with the help of the diagram from part (c).    Based on the result I got, we can see the demand during the lead-time is less than the lot  size which 553 < 1858. And the demand during the lead-time suppose to be less than the  lot size because then that will avoid the backlog. 

Check​ your work:  Is the work correctly in every detail?  Yes  Are the assumptions/planning reasonable?  Yes  Does the result make sense?  Yes  I checked all the work I did, they’re all perfectly done. 

Learn​ and Generalize:  I learned how inventory cycling works and different equivalent terms. I have learned the  data correlates to reorder point. I have better understand how to calculate economic  order quality, optimal lot size, and total inventory costs.    

PROBLEM 5: SOURCING FOR SPC (0.5-1.0 HOUR  FOR READING; 0.5-1 HOUR TO SOLVE THE 

PROBLEM; 25 POINTS) 

Define​ the Problem:  Read the first four sections on “Sourcing Decisions in a Supply Chain” from the textbook  (Sections 14.1-14.4 Third Edition/Fourth Edition). Use the results from Problem 3 for all  calculations.    Julie Williams needs to make a choice between the following 2 suppliers of polystyrene  resin: 

● Supplier 1 ​: unit cost = $20 per unit (1 unit =1000lb.); average lead time= 1 week;  standard deviation of lead time = 0.5 week; Batch or lot size =3000 units 

● Supplier 2 ​: unit cost = $15 per unit (1 unit =1000lb.); average lead time= 2 weeks;  standard deviation of lead time = 1 week; Batch or lot size = 5000 units 

  Answer the following questions: 

a) Which supplier should Julie choose, based on minimizing total cost, if her  inventory holding cost h = 0.20 and her desired target CSL = 95%? 

b) Create a supplier scorecard that Julie can use to compare different suppliers.  (Hint: Use the Utility Function approach developed in CSE 171A/270A for choosing  between alternatives, as well as ideas from the text.) 

Plan​ the treatment of the problem:  1. Answer Q#1  2. Answer Q#2 

Execute​ the plan:  Given Data:  Average weekly demand, DW = 553.269 units  Holding cost = 0.2  CSL = 0.95  Supplier 1: unit cost = $20 per unit (1 unit =1000lb.); average lead time= 1 week;  

standard deviation of lead time = 0.5 week; Batch or lot size =3000 units  Supplier 2: unit cost = $15 per unit (1 unit =1000lb.); average lead time= 2 weeks;   standard deviation of lead time = 1 week; Batch or lot size = 5000 units  Standard deviation of weekly demand, = 138.317    Equation: 

● Annual material cost = demand * 52 * selling price  ● Average cycle inventory = lot size / 2  ● Annual cost of holding cycle inventory = Average cycle inventory * sell price * 

holding cost  ● Standard deviation of demand during lead time = SQRT(avg lead time * St.d of 

demand * avg cycle inventory * St.d of lead time)  ● Safety inventory required with current supplier = Fs^-1(CSL)* standard deviation of 

demand during lead time   ● Annual cost of holding safety inventory = safety inventory required with current 

supplier * sell price * holding cost    1.   Supplier 1: 

● Annual material cost = demand * 52 * selling price = 553.269 * 52 * 20 = $575400  ● Average cycle inventory = lot size / 2 = 3000/2 = 1500  ● Annual cost of holding cycle inventory = Average cycle inventory * sell price * 

holding cost = 1500 * 20 * 0.2 = $6000  ● Standard deviation of demand during lead time = SQRT(avg lead time * St.d of 

demand + avg cycle inventory * St.d of lead time) = √1 38.317 000 .5× 1 + 1 × 0 =25.26 

● Safety inventory required with current supplier = Fs^-1(CSL)* standard deviation of  demand during lead time = 1.65 * 25.26 = 41.69 

● Annual cost of holding safety inventory = safety inventory required with current  supplier * sell price * holding cost = 41.69 *20 *0.2 = $166.75 

● Annual cost of using current supplier = 575400 + 6000 + 166.75 = $581567    Supplier 2: 

● Annual material cost = demand * 52 * selling price = 553.269 * 52 * 15 = $431550  ● Average cycle inventory = lot size / 2 = 5000/2 = 2500  ● Annual cost of holding cycle inventory = Average cycle inventory * sell price * 

holding cost = 2500 * 15 * 0.2 = $7500  ● Standard deviation of demand during lead time = SQRT(avg lead time * St.d of 

demand + avg cycle inventory * St.d of lead time) = =52.69√2 38.317 500× 1 + 2 × 1  

● Safety inventory required with current supplier = Fs^-1(CSL)* standard deviation of  demand during lead time = 1.65 *52.69 = 86.945 

● Annual cost of holding safety inventory = safety inventory required with current  supplier * sell price * holding cost = 52.69 * 15 * 0.2 = $158.08 

● Annual cost of using current supplier = 431550 + 7500 + 158.08 = $439208    Based on the calculation, we can see that taking supplier 2’s option is the most  cost-efficient choice.    2. Create a supplier scorecard that Julie can use to compare different suppliers.   

Data  Supplier 1  Supplier 2 

Weekly Demand  553.269  553.269 

Holding Cost  0.2  0.2 

CSL  0.95  0.95 

Selling Price  20  15 

Average Lead Time  1  2 

Standard Deviation of Lead Time  0.5  1 

Batch or lot size  3000  5000 

Annual Material Cost  575400  431550 

Average cycle Inventory  1500  2500 

Annual cost of holding cycle inventory  6000  7500 

Standard deviation of demand during lead time  25.26  52.69 

Safety inventory required with current supplier  41.69  86.945 

Annual cost of holding safety inventory  166.75  158.08 

Annual cost of using current supplier  581567  439208 

 

Check​ your work:  Is the work correctly in every detail? 

Yes  Are the assumptions/planning reasonable?  Yes  Does the result make sense?  Yes  I checked all the work I did, they’re all perfectly done. 

Learn​ and Generalize:  Through this problem, I have a better understanding of how to dissect and provide a  company’s supply chain strategy and its characteristics to better aid me in the practice of  this method on my project.    

PROBLEM 6: TRANSPORTATION DESIGN FOR SPC  (1-1.5 HOURS; 25 POINTS) 

Define​ the Problem:  Read the section on “Trade-offs in Transportation design” from the textbook (Section  13.5 in Third Edition/Fourth Edition)    Answer the following questions about transportation design ​for transporting polystyrene  resin (PR) from the PR supplier to SPC: 

a) Create the appropriate table in Excel for comparing rail versus truck delivery  options for modes of transportation. 

b) Use the table from (a) to select the optimal mode of transportation. Provide  quantitative evidence to support your selection. (Make the appropriate  assumptions about transportation and other costs). 

Plan​ the treatment of the problem:  1. Finish Q#1  2. Finish Q#2 

Execute​ the plan:  1. Create the appropriate table in Excel for comparing rail versus truck delivery options  for modes of transportation.    Rail:  Replenishment lead time, L= 7 days + 5 days = 12 days   Holding cost = $12 x 0.12 = 1.44   Cycle inventory = Q/2 = 2,000/2 = 1,000 units  Safety Inventory = L/2 days of demand = (12/2)(37808.5/365) = 621.51 units  In-Transit Inventory = 37808.5(5/365) = 517.925 units  Total average inventory = 1,000 + 517.925 + 621.51 = 2139.435 units  Annual Holding Cost = 2139.435x 1.44 = $3080.79  Annual transportation cost = 37808.5 x 6.5 = $245755.25  Total annual cost = $245755.25 + $3080.79= 248836.04   

Truck:  Replenishment lead time, L= 7 days + 3 days = 10 days   Holding cost = $10 x 0.12 = 1.2   Cycle inventory = Q/2 = 2,000/2 = 1,000 units  Safety Inventory = L/2 days of demand = (10/2)(37808.5/365) = 517.925units  In-Transit Inventory = 31,292(3/365) = 310.75 units   Total average inventory = 1,000 + 517.925+ 310.75 = 1828.675 units  Annual Holding Cost = 1685.85753425 x 1.5 = $2743.01  Annual transportation cost = 37808.5 x 7.5 = $283563.75  Total annual cost = $2743.01 + $283563.75 = $286306.76   

   

2. Use the table from (a) to select the optimal mode of transportation. Provide  quantitative evidence to support your selection. (Make the appropriate assumptions  about transportation and other costs).    Based on the result I got, to minimizes the cost we should select Rail transportation  because it has lower cost compared to Truck 

Check​ your work:  Is the work correctly in every detail?  Yes  Are the assumptions/planning reasonable?  Yes  Does the result make sense? 

Yes  I checked all the work I did, they’re all perfectly done. 

Learn​ and Generalize:  It was a good review of calculating all the cost factor comparisons to pick the most  optimal transportation for the lost pricing.       

PROBLEM 7: EXECUTION OF YOUR PLAN (0.5  HOURS, 5 POINTS) 

Define​ the Problem:  Use a table to compare your plan from Problem 1 (column 1) with its execution (column 2).  Indicate the reasons for the difference between the plan and its execution (column 3).   Add additional columns to capture recommendations for improved execution of your  plans in the future. Write down three key lessons you learned in this course. 

Plan​ the treatment of the problem: 

Make a table 

Column 1: Problem 1 plan  Column 2: Problem 1 plan execution date  Column 3: the reason why there is a difference  Column 4: What I have learned 

Execute​ the plan: 

Problem 1 plan  Execution date  Reason for difference  what I have learned 

Receive the Final  Examination, read  through it and ask  questions if needed. 

Thursday, 12  March 2020 

No difference, plan was  well executed, and  work was done  accurately 

No improvements  needed because  everything went as  planned. 

Start on Question 1 &  7 

Friday, 13  March 2020 

This problem is pretty  straight forward, I have  completed this on time 

No improvements  needed because  everything went as  planned. 

Start and finish on  Question 2 & 3 

Saturday, 14  March 2020 

A lot to be done, took  me around 5 hr, then I  took a break from it. 

It was a really good  practice and I have  a better  understanding after  finish this problem  sets. 

Start on Question 4  & 5 

Sunday, 15  March 2020 

Took a long time for me  to figure out the  equations and numbers 

I had some problem  with the calculation  part and was not be  able to finish in one  day because I was  really busy 

Finish on Question 4  & 5  Start on Question 6 

Monday, 16  March 2020 

No difference  No improvements  needed because  everything went as  planned. 

Due Date 5 PM  Finish on Question 6  Finish Question 1 & 7  Double-check the  works 

Tuesday, 17  March 2020 

Took longer than what I  thought  

took some time and  got some ideas how  to do the Q#6 and  finally finish it in 2  hours. 

Check​ your work:  Is the work correctly in every detail?  Yes  Are the assumptions/planning reasonable?  Yes  Does the result make sense?  Yes 

Learn​ and Generalize:  It’s always important to keep tracking the work progress. This exam was a really good  practice and I have a better understanding after finish this problem sets. I had some  problems with the calculation part and was not be able to finish the problem in one day  because I was really busy Really hard final weeks, hopefully I will get good grades on  this. For this exam, from my experience, before I am able to handle the time very well, I  know which part I need to spend more time on.