Crew Planning exercise #2

Date 26 February 24, 2021

Report is due 9 March 2021 – Excel Report & Word Report on the schedule

Your company has been contracted to fly a dedicated route Toronto to Honolulu starting on 1 March 2021. You will fly all flights with no cancellations allowed. Please develop a crewing schedule while maintaining all Crew Fatigue Regulations as discussed in the class today and attached.

You are to manage the 28/90 day flight hours of 112/300 flight hour regulations for crews.

Make any assumptions you need to ensure we complete our crewing schedule as long as you note them on the report.

Flight Project start date is 1 March 2021 length is 60 days.

Aircraft : B767

Total Flight Hours: 12288 flt hrs

Last check completed 3C & 1C check at 12000 flt hrs

Time since last check: 288 flt hrs

Next check due: 112 flt hrs

Route:

Toronto to Honolulu round trip

Frequency : Weekly

· Monday ; Thursday ; Friday ; Sunday – Round trip

· Tuesday YYZ to HNL ( one way – aircraft remains overnight )

· Wednesday HNL to YYZ ( one way )

· Saturday ( no flying )

Assumptions:

Route flight times:

YYZ to HNL – 9.7 Hrs

HNL to YYZ – 10.6 hrs

Crew

YTD

90 DAYS

28 DAYS

NOTES

Pilot 1

120

220

60

Pilot 2

60

60

30

Pilot 3

90

110

42

Pilot 4

100

200

36

Vacation 5 to 9 March

Pilot 5

64

72

52

Pilot 6

92

138

41

Pilot 7

30

44

12

Chief Pilot

Pilot 8

30

44

12

Pilot Manager

Build a 60 day schedule to fly the aircraft as contracted using the crews and maintain the new regulations restrictions. Please schedule to aircraft maintenance as the hours accumulate ( 400 hrs ). Please note that is a tolerance of 5% +/- to meet the maintenance schedule.