Gantt Chart 1 question
1. Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of September 1, 2018. Assume that work can be done 5 days per week, with no work done on Saturdays or Sundays. Identify the Critical Path. When will the project be completed?
|
Task Number |
Activity |
Immediate Precedence |
Task Duration (Days) |
|
1. |
Strategic Planning Phase |
none |
20 |
|
2. |
Team Orientation |
1 |
28 |
|
3. |
Software Configuration |
2 |
60 |
|
4. |
Testing |
3 |
20 |
|
5. |
Training |
2 |
10 |
|
6. |
Facility Modification |
1 |
45 |