Gantt Chart 1 question

profilewiney123
CreateaGanttChartforthefollowingproject.docx

1. Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of September 1, 2018. Assume that work can be done 5 days per week, with no work done on Saturdays or Sundays. Identify the Critical Path. When will the project be completed?

Task Number

Activity

Immediate Precedence

Task Duration (Days)

1.

Strategic Planning Phase

none

20

2.

Team Orientation

1

28

3.

Software Configuration

2

60

4.

Testing

3

20

5.

Training

2

10

6.

Facility Modification

1

45