| Construction Progress Report
Name: Tyrell Wilson
Date: 11/28/2022 |
| Activity |
Days to Complete |
Start Date |
End Date |
| Construction Plan |
253 |
Tuesday, February 1, 2022 |
Wednesday, October 12, 2022 |
| Planning Activites |
30 |
Tuesday, February 1, 2022 |
Wednesday, March 2, 2022 |
| Finalize Plans |
28 |
Tuesday, February 1, 2022 |
Monday, February 28, 2022 |
| Sign Contract to Proceed |
2 |
Monday, Feburary 28, 2022 |
Wednesday, March 2, 2022 |
| Construction Activities |
45 |
Wednesday, March 2, 2022 |
Saturday, April 16, 2022 |
| Prepare Site |
7 |
Wednesday, March 2, 2022 |
Wednesday, March 9, 2022 |
| Prepare Foundation for Property |
13 |
Wednesday, March 9, 2022 |
Tuesday, March 22, 2022 |
| Establish Framing for Property |
25 |
Tuesday, March 22, 2022 |
Saturday, April 16, 2022 |
| Exterior Work Activities |
30 |
Saturday, April 16, 2022 |
Monday, May 16, 2022 |
| Install Roof |
7 |
Saturday, April 16, 2022 |
Saturday, April 23, 2022 |
| Install Windows |
1 |
Saturday, April 23, 2022 |
Sunday, April 24, 2022 |
| Install Doors |
1 |
Monday, April 25, 2022 |
Tuesday, April 26, 2022 |
| Install Bricks |
6 |
Tuesday, April 26, 2022 |
Monday, May 2, 2022 |
| Install Siding |
14 |
Monday, May 2, 2022 |
Monday, May 16, 2022 |
| Interior Work Activities |
120 |
Monday, May 16, 2022 |
Tuesday, September 13, 2022 |
| Install Insulation |
15 |
Monday, May 16, 2022 |
Tuesday, May 31, 2022 |
| Install Drywall |
15 |
Tuesday, May 31, 2022 |
Thursday, June 14, 2022 |
| Install Plumbing & Related Fixtures |
15 |
Thursday, June 14, 2022 |
Wednesday, June 29, 2022 |
| Install Electrical & Related Fixtures |
15 |
Wednesday, June 29, 2022 |
Thursday, July 14, 2022 |
| Install HVAC |
15 |
Thursday, July 14, 2022 |
Friday, July 29, 2022 |
| Install Cabinets |
15 |
Friday, July 29, 2022 |
Saturday, August 13, 2022 |
| Install Flooring |
15 |
Saturday, August 13, 2022 |
Sunday, August 28, 2022 |
| Install Appliances |
15 |
Sunday, August 28, 2022 |
Monday, September 12, 2022 |
| Grounds Work Activities |
15 |
Monday, September 12, 2022 |
Tuesday, September 27, 2022 |
| Install Driveway |
3 |
Monday, September 12, 2022 |
Monday, September 15, 2022 |
| Install Sidewalks |
3 |
Monday, September 15, 2022 |
Sunday, September 18, 2022 |
| Install Fencing |
3 |
Sunday, September 18, 2022 |
Wednesday, September 21, 2022 |
| Install Deck |
3 |
Wednesday, September 21, 2022 |
Saturday, September 24, 2022 |
| Lay Sod & Plants |
3 |
Saturday, September 24, 2022 |
Tuesday, September 27, 2022 |
| Final Acceptance |
14 |
Tuesday, September 27, 2022 |
Wednesday, October 12, 2022 |
| Clean Up Property for Inspection (Cleaning Service) |
4 |
Wednesday, September 28, 2022 |
Sunday, October 2, 2022 |
| Inspection by Local Government |
2 |
Sunday, October 2, 2022 |
Tuesday, October 4, 2022 |
| Address Issues from Government Inspection |
2 |
Tuesday, October 4, 2022 |
Thursday, October 6, 2022 |
| Inspection by Owner |
2 |
Thursday, October 6, 2022 |
Saturday, October 8, 2022 |
| Address Issues from Owner Inspection |
2 |
Saturday, October 8, 2022 |
Monday, October 10, 2022 |
| Turn Property Over to Owner |
2 |
Monday, October 10, 2022 |
Wednesday, October 12, 2022 |