Excavations

10-Hour Construction Outreach

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

1

Excavations

Source of photos: NIOSH /John Rekus

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Excavation and trenching are among the most hazardous construction operations.

2

Excavations

Lesson Overview

Role of Competent Person

Excavation Hazards

Protection from Cave-ins

Protection from other Excavation Hazards

Employer Requirements

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Enabling Objectives:

Describe the role of a competent person at an excavation site.

Identify hazards associated with excavations.

Describe the methods for protecting employees from cave-ins.

Apply excavation hazard protection methods.

Recognize employer requirements to protect workers from excavation hazards.

3

Role of Competent Person

Required training and knowledge

Soil classification

Use of protective systems

OSHA’s requirements for excavation

Able to identify hazards and have the authority to eliminate hazards

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

What a competent person needs to know…

OSHA defines soil types: Stable Rock, Type A, Type B and Type C [see 1926 Subpart P Appendix A (b)].

Competent persons must be able to determine soil type based on at least one visual and one manual test performed at the job-site.

OSHA standards require that employers inspect trenches daily and as conditions change by a competent person before worker entry to ensure elimination of excavation hazards. A competent person is an individual who is capable of identifying

existing and predictable hazards or working conditions that are hazardous, unsanitary, or dangerous to workers, soil types and protective systems required, and who is authorized to take prompt corrective measures to eliminate these hazards and conditions.

4

This competent person is inspecting the excavation, surroundings and protective system. If a hazard is identified, they will remove the worker and take prompt corrective action.

Source of photo: OTIEC Chabot Las Positas

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Inspections must be made:

Before work begins.

After rainstorms, high winds, or other occurrences that may increase hazards.

When it can reasonably anticipated that a worker will be exposed to hazard(s).

It is the responsibility of the competent person to make those inspections necessary to identify situations that could result in hazardous conditions (e.g., possible cave-ins, indications of failure of protective systems, hazardous atmospheres, or other hazardous conditions), and then to insure that corrective measures are taken. It is, therefore, subject to the conditions present at each individual worksite whether or not a competent person is required to be present at the jobsite at all times.

Note: Identify hazards – soil type – sloping – materials at edge of excavation

5

Excavation Hazards

Cave-ins

Falls

Falling Loads

Hazardous Environment

Mobile Equipment

Underground Utilities

Source of photo: OSHA

This is a very dangerous situation!

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Ask the class how many of these exist in this photo?

Have the students brainstorm on what environmental hazards might be.

Ask the students which they feel is the greatest hazard?

6

Cave-Ins

Greatest hazard

It is natural for a trench to try to fill itself

One cubic foot of soil weighs between 90-130 lbs.

It will entrap, bury, or otherwise injure you

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Cave-ins pose the greatest risk and are much more likely than other excavation related accidents to result in worker fatalities.

Two workers die every month in trench collapses!

7

They Both Died

A crew was installing conduit in an 8’ deep by 2’ wide trench.

The trench collapsed.

Two workers were buried.

They both died!

Source of photo: CDC/NIOSH/FACE

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

8

Protection is Required

Never enter an unprotected trench that is 5 or more in depth

The competent person must first choose and implement a protective system

Even excavations less than 5 feet deep need to be deemed safe by the competent person

Cave-ins can happen without warning

This 6 foot deep vertical-sided, unprotected trench is dangerous!

Source of photo: OTIEC NRC WVU

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

9

Protective Systems

Support/shoring systems

Sloping and benching

Shielding systems (trench boxes)

Shoring

Sloping

Shielding

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

How does the competent person choose the most appropriate protective system design?

Designing a protective system can be complex because they must consider many factors: soil classification, depth of cut, water content of soil, changes due to weather and climate, or other operations in the vicinity. Employers are free to choose the most practical design approach for any particular circumstance. Once they have selected an approach, however, the system must meet the required performance criteria.

Protective systems are not require when an excavation is made entirely in stable rock or is less than 5 feet (1.52 meters) deep, if a competent person has examined the ground and found no indication of a potential cave-in.

10

Support/shoring Systems

Source of photos: NIOSH /John Rekus

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Shoring (Shoring system) means a structure such as a metal hydraulic, mechanical or timber shoring system that supports the sides of an excavation and which is designed to prevent cave-ins.

11

The Theory of Shoring

Shoring prevents cave-ins

Shoring, if designed and installed correctly, prevents movement of the excavated wall.

In order for the shoring to do its job, you must stay within the protection of the shoring even when entering and exiting

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

12

Improper Shoring

Make-shift, improperly designed shoring does little other then provide a false sense of security!

Source of photos: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

13

Sloping and Benching

This slope is safe for any soil classification!

Is this a 1 ½ to 1 slope?

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Some contractors may choose to slope the sides to an angle not steeper than 1-1/2:1; for example, for every foot of depth, the trench must be excavated back 1-1/2 feet. A slope of this gradation or less is safe for any type of soil.

Sloping at steeper angles will require the competent person to first classify the soil and then chose a slope which will protect you from cave-ins.

The photo above is actually depicting Type C soil and is not sloped properly.

14

The Theory of Sloping

Sloping prevents cave-ins

Sloping, if done correctly, removes the risk of cave-ins by sloping the soil of the trench back from the trench bottom

Source of photo: OTIEC NRC WVU

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

15

Shield System

Source of photo: OSHA

How many hazards can you find ?

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Shield (Shield system) means a structure that is able to withstand the forces imposed on it by a cave-in and thereby protect employees within the structure. Shields can be permanent structures or can be designed to be portable and moved along as work progresses.

Trench shields and boxes, if installed correctly, are designed to protect workers from the forces of a cave-in

In order for the shield to do its job, the worker must stay within the protection of the shield even when entering and exiting

Use a trench box or shield designed or approved by a registered professional engineer or based on tabulated data prepared or approved by a registered professional engineer.

Timber, aluminum, or other suitable materials may also be used.

Photo hazards: Improper use of ladder, trench plate can not be hung from strut, box is not stabilized, fall hazard trying to get in and out of box.

16

The Theory of Shielding

Trench shields and boxes, if installed correctly, are designed to protect workers from the forces of a cave-in

In order for the shield to do its job, you must stay within the protection of the shield even when entering and exiting

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

17

Falls

Source of photos: OSHA

Safe Alternative

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Class discussion

Ask the class if they have ever seen anything like the photo on the left?

Next ask them if they have ever had to cross a trench this way?

Have them come up with a conclusion of the worst possible scenario should they fall.

Explain why the photo on the right represents a safer solution.

18

Adjacent Structures

Structures become unstable when earth next to them is removed

For your safety, they must be supported

A competent person must ensure precautions are implemented.

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Excavations under sidewalks and pavements are prohibited unless you provide an appropriately designed support system or another effective means of support.

19

Underground Utilities

Source of photo: OSHA

As required, this worker’s employer used their state’s one call system to locate under ground utilities before breaking ground. Now he is hand digging to find the exact location.

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Before starting work, the OSHA standard requires your employer to do the following:

Determine the approximate location of utility installations—sewer, telephone, fuel, electric, and water lines; or any other underground installations;

Contact the utility companies or owners involved to inform them of the proposed work within established or customary local response times; and

Ask the utility companies or owners to find the exact location of underground installations. If they cannot respond within 24 hours (unless the period required by state or local law is longer) or cannot find the exact location of the utility installations, you may proceed with caution.

When finding the exact location of underground utilities, proceed with caution, by hand or other acceptable safe means.

Potholing is a practice used to determine the location of underground utilities by digging test holes to expose such a facility.

1926.651(b)(3) When excavation operations approach the estimated location of underground installations, the exact location of the installations shall be determined by safe and acceptable means.

The use of heavy equipment, such as a backhoe, for potholing is not a preferred method due to the riskiness of this endeavor compared to other methods of potholing. http://www.marc.org/Government/Local-Government-Services/pdf/Potholing

20

Spoil Pile

Source of photo: OSHA

Minimum

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

You must be protected from excavated or other materials or equipment that could pose a hazard by falling or rolling into excavations.

Protection shall be provided by placing and keeping such materials or equipment at least 2 feet (.61 m) from the edge of excavations, or by the use of retaining devices that are sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary.

Possibly could be further back due to “surcharge load”

21

Mobile Equipment

Source of photos: OSHA

Safe Alternative

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

When mobile equipment is operated adjacent to an excavation; the operator must have a clear and direct view of the edge of the excavation, or… A warning system shall be utilized such as barricades, hand or mechanical signals, or stop logs. If possible, the grade should be away from the excavation.

22

Vehicular or Traffic Hazards

Source of photos: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Excavations which expose workers to vehicular traffic require specific precautions and controls.

Employees exposed to public vehicular traffic shall be provided with, and shall wear, warning vests or other suitable garments marked with or made of reflectorized or high-visibility material.

All traffic control signs or devices used for protection of construction workers shall conform to Part VI of the MUTCD, 1988 Edition, Revision 3, or Part VI of the MUTCD, Millennium Edition.

23

Falling Loads

Source of photo: OSHA

Do you see any other hazards?

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Materials too close to the excavation.

Other Photo hazards: Improperly constructed ladder; improper protection of type C soil.

24

Hazardous Atmospheres

Source of photo: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Ask the class what the potential atmospheric hazards are depicted here?

A competent person must test any excavation deeper than 4 feet (1.22 meters) or where an oxygen deficiency or a hazardous atmosphere is present or could reasonably be expected, such as a landfill or where hazardous substances are stored nearby, before an employee enters it. If there are any hazardous conditions, your employer must provide the controls such as proper respiratory protection or ventilation.

In addition, employers are responsible for regularly testing all controls used to reduce atmospheric contaminants to acceptable levels.

If unhealthful atmospheric conditions exist or develop in an excavation, they must provide emergency rescue equipment such as a breathing apparatus, safety harness and line, and basket stretcher and ensure that it is readily available. This equipment must be attended when in use.

25

Water Accumulation

Source of photos: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Water changes everything and makes soil less stable.

Efforts must be make to keep water out of excavations.

Among the additional hazards stemming from water in an excavation are undermining the sides and making it more difficult to get out of the excavation. You must have adequate protection in excavations where water has accumulated or is accumulating.

If your employer uses water removal equipment to control or prevent water accumulation, you must ensure that a competent person monitors the equipment and its operation to ensure proper use.

Diversion ditches, dikes, or other suitable means can also be used to prevent surface water from entering an excavation and to provide adequate drainage of the adjacent area.

In addition, a competent person must inspect excavations subject to runoffs from heavy rains.

26

Access/Egress

Source of photo: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

You must have safe access and egress when working in excavations, including ladders, steps, ramps, or other safe means of exit for employees working in trench excavations 4 feet (1.22 meters) or deeper.

These devices must be located in the excavation within 25 feet (7.62 meters) of all workers.

Any structural ramps must be designed by a competent person if they are used for employee access or egress, or by a competent person qualified in structural design if they are used for vehicles. Also, structural members used for ramps or runways must be uniform in thickness and joined in a manner to prevent tripping or displacement.

27

Ladders

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

28

Hard Hats

Working below grade, overhead hazards exist

Hard hats must be worn in excavations because of overhead hazards

Source of photo: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

29

Responsibilities: Employer

Employers must:

preplan the work and use the one-call system to identify underground utilities

protect you from cave-ins and other excavation-related hazards

inspect the excavation at least daily and throughout the shift as needed

take prompt corrective action when a hazard is identified

respond to and correct hazards pointed out by you, the worker

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

30

Responsibilities: Employer

Employers must:

make sure a ladder is within 25’ of your work area when deeper than 4’

keep excavated dirt, rocks and other materials back 2’ from the excavation’s edge

Test and monitor the air within the trench in areas suspect to atmospheric hazards

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

31

Responsibilities: You

You must:

work defensively

Follow you company’s excavation and trenching safety rules

correct the hazards you are able to correct

report to your supervisor the hazards you are unable to correct

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

32

Case Study

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

The victims were members of a crew installing conduit in an eight-foot-deep by two-foot-wide trench. After approximately an hour, the crew leader grounded the bucket, turned the machine off and walked to the company trailer to check blueprints. As he exited the trailer, he was informed by one of the workers that the trench had collapsed and that the two employees had been covered up.

Ask the class for 3-4 things that may have contributed to these workers losing their lives.

Possible Answers: Improper safety oversight. No protective system. No way to get out. Spoil pile too close. Any others?

Ask the class for 3-4 recommendations for preventing a similar incident.

Possible Answers: Have a competent person. Evaluate the soil and implement a protective system. Have a ladder for egress. Educate workers. Any others?

33

Hazard Recognition

Identify hazards and what should be done

Source of photos: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Photo left: Unprotected trench, undermined-unsupported pavement, spoil pile too close.

Photo middle: Workers leaving protection of trench box. Inadequate box – open ends – need stackable box or lay sloping angle back. Unsupported utilities

Right photo: Fall hazard. Improperly constructed walkway – proper access egress needed

Have students propose solution for each.

34

Hazard Recognition

Identify hazards and what should be done

Source of photos: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Photo left: Fall hazard. Proper support? Engineering? Surcharge load of crane.

Photo middle: Work zone hazard, traffic with no barricades. Class of Vest?

Photo right: Fall hazard, undermined pavement, unprotected excavation. Engineering of all surface encumbrances.

Have students propose solutions for each.

35

Hazard Recognition

Identify hazards and what should be done

Source of photo: OSHA

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

Photo left: Unsafe loads being place on soil. Surcharge loads. Spoil piles.

Photo middle: Workers leaving protective system, unsupported utility pipe. Inadequate protection – sloping.

Photo right: Improperly installed protective system and potential worker exposure to traffic. Surcharge load.

Have students propose solutions

36

Always Remember

Never enter a trench 5’ or greater in depth unless a protective system is in place.

Trenches less than 5’ deep still require the competent person’s “OK”

If a trench box or shoring is used, never leave its protection while in the trench

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

37

Knowledge Check

What is the minimum distance that excavated materials, tools, and other supplies be kept back from the excavation’s edge?

1 foot

2 feet

7.5 feet

25 feet

b. 2 feet

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

38

Knowledge Check

At what depth must a ladder, ramp, steps, or runway be present for quick worker exit:

4 feet

5 feet

10 feet

It is never required

a. 4 feet

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

39

Knowledge Check

What is the greatest hazard facing a worker while working in a trench:

Hazardous atmospheres

Falls

Cave-ins

Falling Objects

c. Cave-ins

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

40

Knowledge Check

Unless made in entirely stable rock, at what depth is a protective system required for a trench:

Any depth if the competent person says so.

5 feet deep and greater

Both a and b

A protective system is never required in trenches

c. Both a and b

PPT 10-hr. Construction – Excavations v.05.18.15

‹#›

Created by OTIEC Outreach Resources Workgroup

41

Excavations in Construction

Questions?