Resource Scheduling Methods

profilesexyjenn99
CLCteamProject.docx

5

PROJECT OBJECTIVE

The addition of a coffee shop in the Blooming Market Store taking place within the year is not to exceed $1 million dollars. The addition will be used as historical data for the expansions to into other communities established in our long-term plan. The goal is to rebrand our identity as we welcome a one-stop-shop for growing families and community to have everything they need from retail, groceries and coffee all in one place.

There are three phases for this expansion. Phase one is design, planning and permits. Phase two is the expansion of the store, completion of the coffee shop and the inventory stocked. Phase three includes the staffing, marketing and the advertising. Communication between contractors and stakeholders are to remain a constant throughout the project.

DELIVERABLES

The project deliverables for the coffee shop are

· Expansion of 500 square feet to The Retail Store.

· All 3 locations will be done at the same time.

· Appliances and coffee equipment including automatic drip coffee makers for a basic product. Espresso machines, coffee grinders and bean roasters need to be installed.

· A refrigeration system, ovens, racks, containers and pumps, product storage, blenders need to be installed.

· Point of sale system needs to be installed.

· Booths, tables, high countertop tables, and chairs

· Interior designing to incorporate the community and family vibe layout and blueprint.

· Pictures, racks for books, additional products and a theme for each coffee shop.

· A sign engrafted with our mission statement to empower the heart of our retail store.

· List of products offered and pricing for basic products to premium products.

· Add the coffee shop online in order to draw customers to the store and cast the vision for the coffee shop addition.

· Job Description and outline for openings.

MILESTONES

Permits approved, contractors assigned for building, designs created and blueprints obtained– May 17

Foundation poured – June 12

Drywall in. Framing, sheathing, plumbing, electrical, and mechanical inspections passed – August 5

Final inspection – August 12

Interior Design completed- August 26

TECHNICAL REQUIREMENTS

Building code requirements are met.

Structure will pass seismic stability codes.

Pass all the health codes and requirements needed to be up and running successfully.

A business recovery plan will be made and filed with the Emergency Management office.

Security integrated into the build.

Wi-Fi services and charging stations are to be integrated into the interior design.

Meet all fire safety measures and requirements including an escape route.

Install all point of sale systems and make sure they are accurate and interconnected with the store.

LIMITS AND EXCLUSIONS

Limits for the project include design and specifications originally drafted.

The contractor reserves the right to contract out parts of the interior build.

The contractor is responsible for the subcontracted work and accepts responsibility for work stages being completed on time.

Work site times are to be limited to Monday through Friday 8:00 am to 6:00 pm. Any overtime for work will be authorized by the project manager.

Overtime is to be approved by the project manager.

THE CUSTOMER REVIEW

The customer review will take place with the senior management of the Blooming Market Store, the project manager, and the contractors. We will also obtain feedback from customers through surveys both in person and online through our website.

WORK BREAKDOWN STRUCTURE

A Work Breakdown Structure (WBS) has been created below to lay out the details of the project and make it more manageable. This chart will help clearly show the work that needs to be completed by the project team. The chart is broken down into deliverables and sub-deliverables that need to be accomplished within the project. The Work Breakdown Structure is a vital piece in helping establish an agreement between stakeholders and project team members to help determine the scope of the project. We have kept the WBS simple, but we have established a joint understanding of all the essential work necessary to be effective and successful in this project.

WP-4A create social media accounts

WP-4B host community event

WP-4C est app for E-Z pick up

WP-3A (est coffee shop needs)

WP-3B create hiring website

WP-3C est who will conduct interviews

Blooming Market’s Coffee Shop

WP-2A (order products)

WP-2B (est financial analysis)

WP-1A (finalized Blueprint)

WP-1B (permits)

WP-1C (hire contractors)

WP-1D (est. time line)

Foundation and Framing

pricing

Community outreach

Social media

Online ordering

Post openings

Hiring process

Establish job descriptions

Product range

contractors

Blueprints and permits

Design, Planning, and Permits

Expansion and Inventory

Staffing

Marketing and advertising