Prince2-5.5
Change and Progress
PRINCE2® is a registered trademark of AXELOS Ltd, used under permission of AXELOS Ltd. All rights reserved.
In this unit, we will cover:
The Change theme, including the purpose of a Change budget
Key management products:
Change control approach
Configuration item record
Issue register
Issue report
Product status account
PRINCE2®’s minimum requirements for applying the Change theme
Types of issues
Recommended issue and change control procedure
Unit Objectives
PRINCE2® is a registered trademark of AXELOS Ltd, used under permission of AXELOS Ltd. All rights reserved.
Change
Change
Change control procedure
Guidance
Roles and responsibilities
Minimum requirements
Effective management
Documents
Capture
Assess
Propose
Decide
Implement
Problem or concern
Off-specification
Request for change
Baselines
Authority
Change control
Issues
Defined
Types of issues
Based on AXELOS Limited PRINCE2®material. Reproduced under license from AXELOS Limited. All rights reserved.
v 5.0
3
Don’t include in slide copies.
Key Learning Objectives (KLO’s)
Hints & Tips
Cautions
Purpose of the Change Theme
To identify, assess, and control any potential and approved changes to the project baselines.
v 5.0
4
Change Definitions
In PRINCE2® a Change is identified as an Issue
Issue: any event that happened, was not planned, and requires management action
Issue types:
Request for Change (RFC)
Off-specification
Problem / concern
Baseline: Reference levels against which an entity is recorded and controlled
Configuration Item Record: describes the status, version, and variant of a CI, and any details of important relationships between them*
* see also ITIL: Service Transition
PRINCE2® is a registered trademark of AXELOS Ltd, used under permission of AXELOS Ltd. All rights reserved.
v 5.0
5
Change Control Technique
Copyright © AXELOS Limited 2011. Material is reproduced under license from AXELOS Limited. All rights reserved.
Change Control Technique: Balance
Copyright © AXELOS Limited 2011. Material is reproduced under license from AXELOS Limited. All rights reserved.
Minimum Requirements for Change
Defined change control approach, which covers:
How issues are identified and managed
Assessing whether issues might have an impact on the business justification
Roles and responsibilities for change control, including change authority
Defining how product baselines are created, maintained and controlled
Maintaining an issue register to record identified issues and decisions
Ensuring project issues are managed throughout project lifecycle
Using lessons to inform issue identification and management
GK V1.0 Feb 2010
Effective Management of Change
Align with organization
Managing product baselines:
Levels, identification, authority and records
Size and complexity
Project delivery approach
Change authority
Change budget
Change Documentation
Required:
Change control approach
Issue register
Recommended:
Issue report
Daily log
Configuration item record
Product status account
Change Responsibilities
Project board
Project manager
Team manager
Project assurance
Change authority
Project support
GK V1.0 Feb 2010
In this unit, we covered:
The Change theme, including the purpose of a Change budget (11.1,11.3.6)
Key management products:
Change control approach (A.3.1)
Configuration item record (A.6.1)
Issue register (A.12.1)
Issue report (A.13.1)
Product status account (A.18.1)
PRINCE2®’s minimum requirements for applying the Change theme (11.2)
Types of issue (11.1, tab 11.1)
Recommended issue and change control procedure (fig 11.1, 11.4.1-5)
References are to the Managing Successful Projects with PRINCE2 by Axelos.
Unit Summary
PRINCE2® is a registered trademark of AXELOS Ltd, used under permission of AXELOS Ltd. All rights reserved.
Progress
In this unit, we will cover:
The Progress theme
Key management products:
Daily log
Lessons log
Lessons report
Work package
End stage report
End project report
Checkpoint report
Highlight report
Exception report
Unit Objectives
PRINCE2®’s minimum requirements for applying the Progress theme
Explain key concepts related to progress:
Event-driven and time-driven controls
Tolerances and exceptions, including how tolerances are set and exceptions are reported
Unit Objectives
PRINCE2® is a registered trademark of AXELOS Ltd, used under permission of AXELOS Ltd. All rights reserved.
Progress
“…to monitor and compare actual achievements against those planned”
Progress
Roles and responsibilities
Guidance
Controls
Progress
Minimum requirements
Effective management
Techniques
Delegating authority
Stage authorization
Tolerances and exceptions
Time and event
driven reporting
Baselines
Reviewing progress
Lessons
Reporting progress
Raising exceptions
Based on AXELOS Limited PRINCE2®material. Reproduced under license from AXELOS Limited. All rights reserved.
v 5.0
16
Don’t include in slide copies.
Key Learning Objectives (KLO’s)
Hints & Tips
Cautions
Purpose of the Progress Theme
To establish mechanisms to monitor and compare actual achievements against those planned
Provide a forecast for the project objectives and the projects’ continued viability
Control any unacceptable deviations
v 5.0
17
Progress
Progress is measured at all levels, but management is by exception only.
Monitor and control:
Work package
Stage
Project
Copyright © AXELOS Limited 2011. Material is reproduced under license from AXELOS Limited. All rights reserved.
Progress Control
Delegating authority to the level below
Dividing the project into management stages; authorizing one management stage at a time
Time and event driven progress reporting and reviews
Application of tolerances and raising exceptions
Project controls documented in the PID
Copyright © AXELOS Limited 2011. Material is reproduced under license from AXELOS Limited. All rights reserved.
Time and Event Driven Controls
Time driven:
Progress report such as Highlight or Checkpoint reports
Event driven:
End stage assessments
End stage report
Issue report
Exception report
Product status account
Application of Tolerances
Based on project objectives
Identified in SU/IP
Starting Up a Project (SU) and Initiating a Project (IP)
Applied in delivery
Used to measure performance
Documented in PID
Management of Tolerances
Managed by:
Corporate management for the entire project
Project board at project level
Project manager for day-to-day control
Team manager at work package level
Progress Controls
Baselines for progress control
Reviewing progress
Capturing and reporting lessons
Reporting progress
Raising exceptions
v 5.0
23
Minimum Requirements for Progress
Define approach to controlling progress in the PID
Manage by stages
Set tolerances
Managed by exception tolerances
Review business justification for exceptions
Learn lessons
Effective Management of Progress
Align with corporate processes
Program or portfolio controls
Delivery approach
Progress Techniques
Progress records:
Milestone charts
Earned value
S-Curve
Kanban board
Burn-down charts
Peer review
Progress Documentation
Issue Register
Product status account
Quality register
Risk register
Daily log
Lessons log
Checkpoint report
Highlight report
End stage report
End project report
Go to Text and Appendix A and make sure you know the Definitions at a minimum:
Daily log (A.7.1)
Lessons log (A.14.1, 12.2.2.3)
Lessons report (A.15.1)
Work package (A.26.1, 12.2.2.1)
End stage report (A.9.1, 12.2.2.4)
End project report (A.8.1, 12.2.2.4)
Checkpoint report (A.4.1, 12.2.2.4)
Highlight report (A.11.1, 12.2.2.4)
Exception report (A.10.1)
Key Management Products
PRINCE2® is a registered trademark of AXELOS Ltd, used under permission of AXELOS Ltd. All rights reserved.
Progress Responsibilities
Project board
Project manager
Team manager
Project assurance
Project support
GK V1.0 Feb 2010
In this unit, we covered:
The Progress theme (12.1)
Key management products:
Daily log (A.7.1)
Lessons log (A.14.1, 12.2.2.3)
Lessons report (A.15.1)
Work package (A.26.1, 12.2.2.1)
End stage report (A.9.1, 12.2.2.4)
End project report (A.8.1, 12.2.2.4)
Checkpoint report (A.4.1, 12.2.2.4)
Highlight report (A.11.1, 12.2.2.4)
Exception report (A.10.1)
References are to the Managing Successful Projects with PRINCE2® by Axelos.
Unit Summary
PRINCE2® is a registered trademark of AXELOS Ltd, used under permission of AXELOS Ltd. All rights reserved.
PRINCE2®’s minimum requirements for applying the Progress theme (12.2)
Explain key concepts related to progress:
Event-driven and time-driven controls (12.2.2)
Tolerances and exceptions, including how tolerances are set and exceptions are reported (12.2.1, fig 12.1, 12.2.3)
References are to the Managing Successful Projects with PRINCE2 by Axelos.
Unit Summary
PRINCE2® is a registered trademark of AXELOS Ltd, used under permission of AXELOS Ltd. All rights reserved.