| Task Name | Duration | Start Date | End Date | Predecessors | % Complete | Status | Assigned To | Comments | Start | Finish | Critical |
| 1. Intiation | 14d | 10/02/19 | 10/15/19 | | 99% | Complete | Jevin |
| 1.1 Recommendation & evaluation | 3d | 10/02/19 | 10/04/19 | | 100% | Completed | Jenny |
| 1.2 Project chart Deveelopment | 2d | 10/05/19 | 10/06/19 | | 100% | Completed | Jenny |
| 1.3 Outline of deliverable | 2d | 10/07/19 | 10/08/19 | | 100% | Completed | Mark |
| 1.4 Stakeholders analysis | 3d | 10/09/19 | 10/11/19 | 4 | 100% | Completed | Joe |
| 1.5 Charter signed by Authority | 4d | 10/12/19 | 10/15/19 | | 95% | In Progress | Joe |
| 2. Planning | 22d | 10/16/19 | 11/07/19 |
| 2.1 Make a scope management | 2d | 10/16/19 | 10/17/19 | | 0% | Not Started | Judy |
| 2.2 Design the project team | 4d | 10/18/19 | 10/21/09 | | 0% | Not Started | Molly |
| 2.3 Intial meeting to boost the project | 3d | 10/22/19 | 10/24/19 | | 0% | Not Started | Molly |
| 2.4 Development of project plan | 2d | 10/25/19 | 10/26/19 | 13 | 0% | Not Started | Judy |
| 2.4.1 Create the schedules | 2d | 10/27/19 | 10/28/19 | | 0% | Not Started | Alex |
| 2.4.2 Analysis the critical path | 3d | 10/29/19 | 11/01/19 | | 0% | Not Started | Alex |
| 2.5 Submission of Project plan | 4d | 11/02/19 | 11/05/19 | | 0% | Not Started | Tim |
| 2.6 Approval for project Plan | 2d | 11/06/19 | 11/07/19 | 12 | 0% | Not Started | Tiana |
| 3. Designing | 20d | 11/08/19 | 11/27/19 |
| 3.1 Meeting to boost the team | 2d | 11/08/19 | 11/09/19 | | 0% | Not Started | Mandy |
| 3.2 Verify the user requirements | 3d | 11/10/19 | 11/12/19 | | 0% | Not Started | Mandy |
| 3.3 Designing of system | 4d | 11/13/09 | 11/16/19 | | 0% | Not Started | Kathy |
| 3.4 procurement of software and hardware | 3d | 11/17/19 | 11/19/19 | | 0% | Not Started | Kathy |
| 3.5 Installation of development system | 2d | 11/20/19 | 11/21/19 | | 0% | Not Started | Tim |
| 3.6 Initiate testing | 3d | 11/22/19 | 11/24/19 | | 0% | Not Started | Harry |
| 3.7 Installation of live system | 2d | 11/25/19 | 11/26/19 | 20 | 0% | Not Started | Harry |
| 3.8 Training of users | 1d | 11/27/19 | 11/27/19 | | 0% | Not Started | Tiana |
| 4. Control | 20d | 11/28/19 | 12/18/19 |
| 4.1 Management of Project | 4d | 11/28/19 | 12/01/19 | | 0% | Not Started | Molly |
| 4.2 Meetings to track the status of the meeting | 4d | 12/02/19 | 12/05/19 | | 0% | Not Started | Molly |
| 4.3 Risk management | 8d | 12/06/19 | 12/13/19 | | 0% | Not Started | Manoj |
| 4.4 Updation of project management plan | 5d | 12/14/19 | 12/18/19 | | 0% | Not Started | Mandy |
| 5. Closing | 11d | 12/19/19 | 12/29/19 |
| 5.1 Audit procurement | 4d | 12/19/19 | 12/22/19 | | 0% | Not Started | Alisha |
| 5.2 Updating and revision of documents | 2d | 12/23/19 | 12/24/19 | 30 | 0% | Not Started | Prem |
| 5.3 Update records and files | 2d | 12/25/19 | 12/26/19 | | 0% | Not Started | Hari |
| 5.4 Receive the acceptance formally | 1d | 12/27/19 | 12/27/19 | | 0% | Not Started | James |
| 5.5. Archieve Documents and files | 2d | 12/28/19 | 12/29/19 | | 0% | Not Started | James |