VoIP Implementation WBS

Task Name Duration Start Date End Date Predecessors % Complete Status Assigned To Comments Start Finish Critical
1. Intiation 14d 10/02/19 10/15/19 99% Complete Jevin
1.1 Recommendation & evaluation 3d 10/02/19 10/04/19 100% Completed Jenny
1.2 Project chart Deveelopment 2d 10/05/19 10/06/19 100% Completed Jenny
1.3 Outline of deliverable 2d 10/07/19 10/08/19 100% Completed Mark
1.4 Stakeholders analysis 3d 10/09/19 10/11/19 4 100% Completed Joe
1.5 Charter signed by Authority 4d 10/12/19 10/15/19 95% In Progress Joe
2. Planning 22d 10/16/19 11/07/19
2.1 Make a scope management 2d 10/16/19 10/17/19 0% Not Started Judy
2.2 Design the project team 4d 10/18/19 10/21/09 0% Not Started Molly
2.3 Intial meeting to boost the project 3d 10/22/19 10/24/19 0% Not Started Molly
2.4 Development of project plan 2d 10/25/19 10/26/19 13 0% Not Started Judy
2.4.1 Create the schedules 2d 10/27/19 10/28/19 0% Not Started Alex
2.4.2 Analysis the critical path 3d 10/29/19 11/01/19 0% Not Started Alex
2.5 Submission of Project plan 4d 11/02/19 11/05/19 0% Not Started Tim
2.6 Approval for project Plan 2d 11/06/19 11/07/19 12 0% Not Started Tiana
3. Designing 20d 11/08/19 11/27/19
3.1 Meeting to boost the team 2d 11/08/19 11/09/19 0% Not Started Mandy
3.2 Verify the user requirements 3d 11/10/19 11/12/19 0% Not Started Mandy
3.3 Designing of system 4d 11/13/09 11/16/19 0% Not Started Kathy
3.4 procurement of software and hardware 3d 11/17/19 11/19/19 0% Not Started Kathy
3.5 Installation of development system 2d 11/20/19 11/21/19 0% Not Started Tim
3.6 Initiate testing 3d 11/22/19 11/24/19 0% Not Started Harry
3.7 Installation of live system 2d 11/25/19 11/26/19 20 0% Not Started Harry
3.8 Training of users 1d 11/27/19 11/27/19 0% Not Started Tiana
4. Control 20d 11/28/19 12/18/19
4.1 Management of Project 4d 11/28/19 12/01/19 0% Not Started Molly
4.2 Meetings to track the status of the meeting 4d 12/02/19 12/05/19 0% Not Started Molly
4.3 Risk management 8d 12/06/19 12/13/19 0% Not Started Manoj
4.4 Updation of project management plan 5d 12/14/19 12/18/19 0% Not Started Mandy
5. Closing 11d 12/19/19 12/29/19
5.1 Audit procurement 4d 12/19/19 12/22/19 0% Not Started Alisha
5.2 Updating and revision of documents 2d 12/23/19 12/24/19 30 0% Not Started Prem
5.3 Update records and files 2d 12/25/19 12/26/19 0% Not Started Hari
5.4 Receive the acceptance formally 1d 12/27/19 12/27/19 0% Not Started James
5.5. Archieve Documents and files 2d 12/28/19 12/29/19 0% Not Started James